1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: New schedule and its implications Preparations for Steps II & III Spectrometer solenoids.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

1 MICE Project Board Schedule and risk discussion Introduction Project Management comment Schedule considerations Adapting the schedule/reacting to circumstances.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
1 MICE Video Conference Reception of FC magnets Andy Nichols, STFC,
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
1 Subsystem Reviews Reviews this week: RFCC modules RF Power Infrastructure MICE Infrastructure LH2 system.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 UKNF/MICE OsC PM report Summary assessment of MICE Risks, pressures and worries Project management Electrical substation, accommodation Redefining the.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
1 Schedule Discussion Background & aims Major milestones & drivers Summary of important dates Project risks MICE CM26, 24-27th March, 2010.
1 MICE CM28 STEP III or STEP IV? – some practicalities Andy Nichols/Tim Hayler, STFC 4 th October 2010 Considerations Step II Step III Step IV Conclusions.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
1 PM report International & UK programmes Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
1 MICE CM28 Schedule & Risk Comment Schedule reconstruction and management The ‘straight to Step IV’ discussion How a schedule meeting can work Risks (and.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
MICE CM28 Engineering Session Summary (On behalf of Wing)
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: New schedule and its implications Preparations for Steps II & III Spectrometer solenoids RFCC and AFC modules Diffuser Accommodation and facilities Project Management and planning Substation upgrade Plans/conclusions Andy Nichols, STFC, 18 th January 2010

2 Present top-level MICE schedule Agreed by iMICE – only reviewed at Collaboration Meetings This version – discussed at November, 2009 This is the important part Steps II &III combined Ready for February 2011 ISIS moderator change July 2010 – Feb 2011 Is confirmed Crucial that we take Advantage of shutdown time

Schedule implications For the UK project: Concerted effort to prepare for Steps II &III integration Domestic infrastructure is in place CCR cooling water is 95% done Solenoid controls rack (DL & LBNL) has begun CCR compressor racking is designed, material provided by INFN as CF contribution, all set to begin, material arrives next few days But Spectrometer solenoid delivery still a major worry, more later Parallel integration of Steps II & III will need more space at RAL – more later

Spectrometer solenoids Recap: LBNL are delivering two spectrometer solenoids They are being manufactured by Wang NMR in Livermore, CA They will have their fields mapped at FNAL (min eight weeks) They are the main parts of Steps II & III Magnet #2 suffered damaged He fill line last year Also some HTS leads burned out Had undergone five training quenches and reached 90% of design current Showstopper at September, 2009 Held review at LBNL in Late November, 2009 Some sort of recovery plan emerged Magnet #1 will be around two months behind #2 4

5 4 th single stage CCR HTS lead area This plate needs more Cross-section * These connections under Close scrutiny * * This is where the work is He fill/vent lines

Spectrometer solenoid Review at LBNL generally went OK: Recommended that given the circumstances, adding the fourth CCR was the right approach Thermal FEA study of magnet must be progressed urgently Operating margin must be evaluated accurately at cooldown – input to LHe top-up frequency The modifications to magnet #2 should proceed as planned Present status: Magnet #2 (the first one we get) is in final stages of leak- checking this week Cooldown begins 18 th January Powering tests occupy, say 25 th January to 20 th February* Ship to FNAL end February* This is our ‘green light’ for Step II start in UK * AN’s interpretation only! 6

Spectrometer solenoid What happens at the cooldown/powering: MICE has agreed some acceptance criteria via its Technical Board: Must sustain design current for min 24 hours LHe top-ups > six weeks apart (this is ‘not quite’ agreed yet) Declaration of conformity for pressure system is completed An as-built installation drawing and specification is completed We hope this decision point arrives around mid-February, if all is met and field mapping goes OK, then we get magnet #2 around mid-May. If not, we may have to face a ground-up rebuild (one year) and magnet #1 will overtake – this would be a major iMICE project re-appraisal 7

8 Magnet #2 is presently dismantled Enabling more comprehensive modifications Better thermal Connections to Rad shield Increased cross Section in these tubes

RFCC Reasonable progress also with the CC: –Problems in China are being solved slowly & carefully: –Engineering drawings of magnet will be done on time –Project management structure at HIT is being re-built –Aim is to let magnet contract to Qihuan by time of Riverside Collaboration Meeting (late March, 2010) –One set of RF cavities (four + one) have been delivered to LBNL – are being polished just now –Real delivery dates of CC magnet will become clear as order is placed - Integration/engineering needs to be driven by RAL group(s) –March 2010 is green light to begin worrying – if Qihuan contract goes wrong, iMICE needs plan B 9 RFCC module Part of Step V Managed by LBNL Some problems in China

AFC & LH2 –Design work on the FC making good progress at Tesla –Some nagging doubt that the integration between the LH2 absorber and the FC is not properly understood –Is being dealt with by Technical Board – Engineering integration needs to be handled by RAL –FC delivery still promised for July/August, 2010 –Request at CM to place solid absorber(s) in FC at Step IV –Some minor design/manufacture work to accommodate, will be done by Oxford, manufacture by Warwick? LH2: –Going well at AS scientific –R&D cryostat has performed thermally – ready to ‘mothball’ –Parts have arrived to complete the gas panel –Very clear that we have to resume work on the ventilation system during 2010 to be on time – this is a huge amount of work, will be in FY 10/11 project plan 10

AFC & LH2 11 All this has to be designed & built outside R5.2. Also a big safety overhead Exp. with PPS shown this takes >1 year

Diffuser Often forgotten, but a vital part of Step II –Manufacture complete at Oxford –But a few problems being sorted out: Pb disc transfer, making mock-up on bench to try principle Air pressure problems – affects motor speed, should be better at RAL though with 7 bar supply Manual control interface is working, would do in extremis for Step II operation Automated system ready by Easter Diffuser delivery to RAL still under review, regular Friday meetings Not on Critical path till late Autumn

Accommodation & Facilities New schedule has been built around Steps II & III being integrated more or less in parallel Baseline WAS for series assembly in R5.2 – this looked just about possible We do not have space there to do parallel operation safely MICE needs at RAL: Min 350 sqm of covered high headroom area Single & three phase power Water supply Min 15 tonne crane, or authority to purchase A-frame Discussions at RAL have not got very far R9, R79, R12 possible candidates, R40 is excluded Meeting fixed with Blueprint Accommodation rep for 25 th January – written proposal circulated Must get this resolved Q2/ – the UK must not be holding up the solenoids Desperately need some constructive advice 13

Project Management & Planning Practical steps have been taken to reinforce the project planning and control Guidance from UKATC Two successful approaches to outside consultants, Magna Parva and UKAEA Two sensible offers received Plan to parcel up the project planning, monitoring and reporting and financial reporting into one discrete package and engage project planner for say six months – this is being actioned Have discussed with STFC Management and within MICE, but no joy Important that we do this now, as the engineering overhead will be increasing this CY, leaving even less time for the above – aim is to make system engineering the full-time job it needs to be 14

Project management and planning One (not unforseen) consequence of deleting the engineering effort (to fit the un-descoped project in the allocation) : Integration/dimensional problems are beginning to fall between the cracks, specifically: Survey data and layout dimensions of TOFI, TOF II & KL in beamline Dimensional clashes between LH2 absorber and FC hardware This was identified as a huge risk and it must be mitigated as we move to a new engineering regime Need to reinforce the hands-on design effort from within EID at RAL This is being written into the costed plan for FY 10/11 15

2MVA substation upgrade Still a big worry Has potential to cost up to £600K Lead time for major components still > 1 year As we have additional CCRs on spectrometer solenoids, risk might move from Step IV to Step III DL group presently evaluating this Some help for payment requested thro’ TIARA – See KL’s slides 16

Plans/conclusions MICE has a very clear idea of its technical objective for 10/11 Matt Hills & Tim Hayler are preparing engineering project plan Aim to have skeleton and milestones for 25 th January It will be the technically limited ‘ideal’ Built around major subsystem deliverables and dates Will request resources to allow UK to honour the iMICE schedule and NOT to hold it up 17

Conclusions Delivery of spectrometer solenoids is clearly our biggest technical worry Schedule of step V similarly at risk from RFCC uncertainty in HIT/LBNL Local engineering effort MUST be rebuilt this year Integration/assembly space MUST be found at RAL this year Project Management assistance plans are going ahead The UK project has delivered what it should - the spirit is really good, despite the pressures – must keep up the momentum 18