NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) NCSX PWR System PROTECTION – REVIEW February 22.

Slides:



Advertisements
Similar presentations
Submitted by: Name:Rajendra Kumar Choudhury Branch:Electrical Engg.
Advertisements

ECE Electric Drives Topic 6: Voltage-Fed Converters Spring 2004.
HYDRAULICS & PNEUMATICS
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
Power Supply System John Joseph LBNL Spectrometer Solenoid Test Plan Review Feb 17 th 2012.
E951 POWER SUPPLY 5/13/02 IOANNIS MARNERIS Brookhaven National Labs.
AIMS TF Upgrade Update 6/18/14. Breaker & Contactor Control & Status 6 Pulse Dual Converter with Lockout Controls (and Shoot-through Protection) Auto-Crowbar.
Chapter 7 Input Modules.
Elec467 Power Machines & Transformers
EUT 1040 Lecture 10: Programmable Logic Controllers.
Introduction To Programmable Logic Controllers
E951 POWER SUPPLY SAFETY REVIEW 9/06/02 IOANNIS MARNERIS Brookhaven National Labs.
electronics fundamentals
G GE Power Management MMII Intelligent MCC Controller.
Shipboard Electrical Distribution …“Shifting the Electric Plant to a Normal Full Power Lineup.”
PLC Fundamentals Module 2: Hardware and Terminology.
Submitted By Ravi Raj Rajeev Kumar Vipul Batra. FUNCTIONS PERFORMED BY THE RELAY MADE 1.OVER VOLTAGE PROTECTION 2.OVERCURRENT PROTECTION.
Section 4: Electric Motors
2 Instructor Training MPTT Flow Loop System VLP-TRN-MPTT.
DPCL Solid State Device Discrete Control Lecture.
SCADA and Telemetry Presented By:.
7/11/01Steven Hays E/E Support Page 1 NuMI Beam line Power Supplies  The supplies in the line is detailed  Main Ring Style…………………..…1  PEI/Transrex.
TF Joint Voltage Drop Instrumentation Robert Marsala (609) Hans Schneider (609) Engineering Operations August 7, 2003 TF_JOINT_Final_Design_Review.ppt.
Industrial Machine Control
REQD FUTURE POWER SYSTEM CHANGES  Following additional work is required to be performed to restore full capability of the machine: 1. Provide power feed.
1 RWM P OWER FEED TO EACH COIL S. Ramakrishnan. 01/29/20102 RWM COILS Existing Status The Six RWM coils are grouped in pairs Each Pair is fed from one.
POWER PLANT USED IN TELECOM
TF FLAG JOINT HIGH CURRENT TEST FIXTURE INSTALLATION TO BE IN THE NSTX TRANSITION AREA Features Assembled Components: Flag and Mating Section of TF Center.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
Electrical Distribution Training
NCSX NCSX CDR May S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX CDR May
NSTX Centerstack Upgrade: initial discussions of the Machine Protection System (MPS) Robert Woolley 4 November 2009.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
SC Project Review of NCSX, April 8-10, 2008 S. Ramakrishnan - 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PWR System April
SmartMQn Motor Horner APG, LLC September 9, 2008.
MICE Power Supply System John Joseph LBNL Spectrometer Solenoid Controls & Monitoring Review Dec 11 th 2012.
Chapter 6 Series and Parallel Circuits 1 of 81 MECH of 81 Chapter 6 Series and Parallel Circuits MECH1100 Topics Identifying Series- Parallel Relationships.
C-12 ELECTRICAL CW3 RIESE 18 APRIL DC SYSTEM -24V, 34 AMP HOUR NICKEL CAD BATTERY A 30V DC STARTER/GENERATORS -AN EXTERNAL DC POWER SYSTEM.
Main contacts closed – RED Colour with ON
FEB Slide 1 Task No.:Point(s):1Only one answer is correct.Cat. No. To measure electrical … A current, the ammeter must be in line with the current.
Diagnostics of photovoltaic power plants operation Vitezslav Benda, CTU Prague, Faculty of Electrical Engineering.
Submitted by:.  Project overview  Block diagram  Power supply  Microcontroller  MAX232 & DB9 Connector  Relay  Relay driver  Software requirements.
Self Switching Power Supply. Introduction Self Switching Power Supply  Embedded system requires a regulated power supply.
1 Mario Sedita - INFN-LNS (Italy) - Power Supplies EMI Cabling Elimed - Elimaia Technical Workshop Harfa - Prague.
ACTIVE LEARNING ASSIGNMENT TOPIC NAME :- DC MOTOR STARTERS ELEMENTS OF ELECTRICAL DESIGN ( ) AY Course co-ordinator:- SAMIR B PATEL PREPARED.
Technical Panel Session. Sunday January 11, DC System Failure Modes IEEE PES SBC Winter Meeting. January 11 – 15, New Orleans, LA Part 3.
SEMINAR ON ISLANDING BY PAWAN. What is islanding? Normally all Power generators are interconnected to form a network called ‘GRID’. Some times it so happens.
S A Griffiths CM42 June 2015 Electrical & Control.
Electrical Configuration and System Protection
ARDUINO BASED UNDERGROUND CABLE FAULT DETECTION
SINGLE PHASE INDUCTION MOTOR SOFT START BY STEPPED DELAY OF REDUCING FIRING ANGLE Submitted by:
Industrial Star Delta Starter For a 3-Phase Induction Motor
Single Phase Induction Motor Speed Control
THREE PHASE FAULT ANALYSIS WITH AUTO RESET ON TEMPORARY FAULT AND PERMANENT TRIP OTHERWISE Submitted by:
Arduino Based Industrial appliances control system by decoding dual tone multi frequency signals on GSM / CDMA network. Submitted by:
OVER VOLTAGE OR UNDER VOLTAGE
MEDIUM VOLTAGE APPLICATIONS.
AUTOMATIC STREET LIGHT CONTROL USING LDR
PC Mouse operated Electrical Load Control Using VB Application
INDUCTION MOTOR PROTECTION FOR SINGLE PHASING, OVERVOLTAGE AND OVER TEMPERATURE Submitted by:
SOFT START OF SINGLE PHASE PUMP MOTOR
GROUND-FAULT GROUND-CHECK MONITOR
SC1R Cold Box PDR Controls
Robicon Perfect Harmony.
Model Output Current Battery Life BATPSU VDC 2A 1.2Ah BATPSU VDC 2.3Ah
Presentation transcript:

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) NCSX PWR System PROTECTION – REVIEW February CONTRIBUTORS M. CROPPER, R. HATCHER, R. MARSALA, S. RAMAKRISHNAN

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 2 Electrical Power System OVERVIEW Provide Source of all Electric Power for NCSX –All AC Power At all Distribution Voltage levels »4.16kV,480V, 208/120V »Includes Experimental AC Power »Includes AC Power to NB »Includes all Auxiliary AC Power up to Power Panels –All DC Experimental Power Provide DC power for stellarator coil systems –2 Modular, and 3 PF coil circuits »PS requirements based on Initial Ohmic Scenario »Clear path for future upgrades (other scenarios, flexibility) Provide Diagnostics support for Sensor cabling Grounding

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 3 AC SYSTEM- USE EXISTING C- SITE SYSTEM WITH NEW 480/120 SYSTEM FOR TEST CELL ESAT RECTIFIERS - USE EXISTING – 6 ROBICONS/ 1 PEI - RECONFIGURE - ASSIGN FOR NCSX LOADS AS NEEDED SDS- USE EXISTING UNITS IN TEST CELL BASEMENT WITH CHANGES REQUIRED - NEW PWR CABLING FROM SDS TO COILS HCS- PURCHASE AND INSTALL PLC. - NEW CABLING AS NEEDED MEASUREMENTS- USE SHUNTS IN PWR SUPPLIES - USE NEW FIBER OPTIC TRANSMITTERS CONTROLS - PLC, CABLING AS IS & MODIFIED PROTECTION - USE EXISTING WITH CHANGES & ADDITIONS - NEW CABLING AS NEEDED KIRKEYS- USE EXISTING WITH CHANGES OVERVIEW CONTD.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 4 PPPL Site Plan NCSX C-Site Location NCSX Control Room Location C- Site Power Supplies

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 5 C-Site Power Supplies C-site Rectifier power supplies used for Coil circuits –Six (6) Robicon Rectifier Supplies. Each of (2) 6-pulse, 2- quadrant converters in parallel - 12-pulse rectified DC output. –One (1) PEI Rectifier Supply. Two 6-pulse rectifier bridges in parallel - 12-pulse DC output Sufficient power available for First Phase Future upgrades with D-Site Supplies Ron Hatcher has tested (Dummy Load) the C-Site supplies

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 6 Power Supplies Assignment 1st plasma & Magnetic Configuration CircuitPower Supply Current 1.5s / 180s VoltsPeak MW M1P1010kA200V2 M2 + M3P5-1 & 4 (parallel)10kA300V3 PF4 P5-2 in series with PEI5kA800V4 PF6 P5-35kA300V1.5 PF1aP2020kA500V10

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 7 Typical Circuit Arrangement Contd. Disconnect and grounding switches provided for each circuit Some of Existing cables used from Rectifier Supplies to Disconnects in Test Cell Basement New Cables (4/c- 500mcm, 600V) from Disconnects to the Bus Stubs in the Tunnel/ Coil Terminals Current/ Voltage transducers provided Changeover to CDX possible by LINKS at top of Disconnects.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 8 PS Control and Coil Protection GENERAL  PS Control  PLC will be provided for Controls (Mark Cropper) –Modern PLC based system –Additional interlocks as needed –Some protective features included  PROTECTION  Coil / Pwr. Loop protection provided (R. Marsala) Overcurrent (Built-in the Pwr. Supplies) Ground fault (new) Pulse duration & period (PDP) limit (new)

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 9  COILS WILL USE built-in protection in C-Site Rectifiers enhanced by additional features.  PROTECTION LEVEL FOR PERSONNEL SAFETY SAME AS TFTR /NSTX.  KIRK- KEY LOCKS WILL ALSO BE PROVIDED AS NEEDED.  ALL THESE WILL BE ENHANCED WITH ADMINISTRATIVE CONTROLS.  MACHINE COILS BEING FED FROM C-SITE POWER SUPPLIES OF LIMITED CAPABILITY AS COMPAREDTO COIL RATINGS. BUILT-IN PROTECTION IN POWER SUPPLIES ARE ADEQUATE. EVEN SO, THESE ARE AUGUMENTED THROUGH ADDITIONAL FEATURES  GROUND FAULT DETECTION AND PROTECTION WILL BE PROVIDED NCSX - PROTECTION

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 10 NCSX - PROTECTION  A. C-Site Rectifiers Protective Features: 1. Cooling water flow loss 2. SCR Over-temperature 3. SCR Junction temperature high 4. Conversion transformers Primary Instantaneous Over-current 5. Conversion Transformers Over-temperature 6. Rectifier door interlock to trip contactor in case door is opened. 7. Over/under AC Voltage conditions 8. DC OUTPUT OVERCURRENT 9. DC OUTPUT OVERVOLTAGE 10. MOVs & CR SNUBBERS TO SUPPRESS OVERVOLTAGE  The settings of the currents in these units will be such that the coils will not be overloaded.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 11 B. Additional Coil Protection based on PLC logic 1. Power Supply Arm permissive: 1.1 Power supply enable command must be high 1.2 Power supply must be enabled (contactor limit switch feed back) 1.3 No thermal trip on corresponding coil. 1.4 Corresponding disconnect switch ready permissive 1.5 Corresponding disconnect closed 1.6 Computer arm command high ( the computer arm command is issued TBD seconds before the shot and removed TBD seconds after the shot. This can be bypassed by the operator) 1.7 Remote interlock – Coil temperature normal for start

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide Power Supply Enable permissive: (COMMON TO TRIP ALL POWER SUPPLIES) - any one of these failures will trip all supplies) a) Pulse duration - Trip Power Supplies (PS) if there is presence of COIL current at a level (adjustable) for more than an adjustable duration of time. This is established by looking at the current. b) Pulse interval - Trip the power supplies if more than one pulse is imposed before an adjustable waiting period.).This is also established by looking at the current. Also failure of the following will remove the Power Supply Enable Permissive- thus trip the power supplies. c) PLC running- not faulted d) Coil Cooling OK e) All Power supplies in remote mode f) Test Cell door interlock closed g) RSView computer online (Programming/Operating computer for AB PLCs) h) No E-stop Additional Coil Protection based on PLC logic Contd.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide PLC Power Supply Enable permissive: (INDIVIDUAL TRIP TO AFFECTED POWER SUPPLY) -these trips will only trip the affected supply) a) Summed permissive from Power supply b) No ground fault on power supply cable c) 4160 KV breaker closed d) No thermal trip on coil (this will prevent enabling but will not trip the supply once it is enabled) C. Pulse Duration & Period Timer. 1. Pulse duration (If the pulse duration is more than an adjustable setting, the permissive to the supplies will be removed). This is based on a Start of Pulse (SOP) command received, and WITHOUT looking at the current. 2. Pulse interval (If the pulse INTERVAL is more than an adjustable setting, the permissive to the supplies will be removed). This is based on a Start of Pulse (SOP) command received, and WITHOUT looking at the current. D. Ground Fault Protection: Coil Ground fault detection and protection will be provided for all circuits. One common Ground Fault relay will be used.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 14 PROTECTION FOR UPGRADE  WILL USE D- SITE RECTIFIERS & ASSOCIATED BUILT-IN PROTECTION  NEW ANALOG COIL PROTECTION DEVICE (ACP) WILL BE DESIGNED & INSTALLED FOR EACH CIRCUIT The ACP will Invoke Level 1  On Coil Overcurrent  If there is presence of current at a level 0 to 10%(adjustable) of the full scale (i.e. 0 to TBD A) for > an adjustable duration of time in increments of 0.1 second (0.1 to 99.9 seconds) shall trip the Power Supplies.  If more than one pulse is imposed before an adjustable waiting period of 1 to 999 seconds in one second increments.  If the (I^2)*t is more than TBD  Simulate coil cooling using a single exponential decay adjustable from TBD seconds to TBD seconds. –ACP Design: –a). Two ACPs one redundant to the other - assemblies in Rack in D- Site –b) The ACP design to be standardized. Signal from DCCTs brought to signal Conditioner. Output from the signal conditioner will be fed as the input signal to the PCB of each circuit/coil or if summing in required, to a summing module before being fed to PCB for that circuit. Appropriate testing features to be installed in chassis.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 15 B. Pulse Duration & Period Timer. New Pulse Duration and Period to be installed in D-Site. This timer will give permissive over an adjustable window of time (adjustable in one second increments from TBD to TBD seconds) when a Start of Pulse (SOP command is received). The timer will also prevent any additional pulsing for an adjustable 600 to 900 seconds even if more SOP command is received within that time. C. Coil Protection Calculator(CPC). If considered necessary a CPC will be designed and installed. D. Coil temperature signal at start of pulse.: The signals to be received from the C-Site shall include the final signal from the PLC which will compute the resistance of the modular coils. However potential leads (#16 insulated wires) from the machine modular coil terminals shall be brought out as part of MIE project, to enable resistance measurement. IT IS SUGGESTED THAT WE MAY BRING OUT THE MODULAR COIL LEADS FROM ONE COIL ONLY FROM EACH PERIOD AND BELONGING TO DIFFERENT GROUP I.E MA, MB, AND MC. LEADS FROM OTHER COILS IF REQUIRED CAN BE TAKEN AFTER THE COLD/HOT BOX (this will thus include the coil leads and hence will not be the coil only). Additional Interlocks as needed from C-Site will be introduced.

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 16

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 17 Coil Resistance Measuring Scheme A constant current power supply will be provided to measure the coil resistance. This Resistance Test Power Supply (RPS) will be connected AT THE Disconnect switch in the C-Site Basement, directly across the input from the supply feeding the coil. Thus the RPS will be connected directly across this power supply. During pulsing the supply will be kept disconnected by a contactor. See Sketch 2 for details. Also resistances R1 & R2 (Values TBD) are connected as shown. The RPS current and the Coil voltages will be fed into a Resistance Measuring Device (RMD). The RMD is yet to be designed or this function will be incorporated in the PLC itself. The output from the RMD will be sent to PLC as needed. The PLC will give permissive to the Power Supplies only if the value is normal for the start of the pulse. For MA coils the value is about 1.1 milliohms. We could keep the current control of the RPS at 50 Amps always (Current controlled), in which case the RMD will be just a voltage measuring device. The trip level can be either set at the PLC or designed and built into the RMD

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 18 Coil Resistance Measuring Scheme

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 19 Coil Resistance Measuring Scheme

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 20 POWER SYSTEM BLOCK DIAGRAM

NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 21