Introduction to Theory of Constraints Competitive Manufacturing Management.

Slides:



Advertisements
Similar presentations
7 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Constraint Management (Short-term Capacity Planning) 7.
Advertisements

Theory of Constraints Scheduling APICS PDM January 14, 2009.
Theory of Constraints Part II: TOC Concepts
Management Accounting: A Road of Discovery. Management Accounting : A Road of Discovery James T. Mackey Michael F. Thomas Presentations by: Roderick S.
1 Presentation by: Tim Sullivan CIRAS (Center for Industrial Research and Service) Iowa State University Extension.
Systems Thinking and the Theory of Constraints Any intelligent fool can make things bigger, more complex, and more violent. It takes a touch of genius.
Cost Analysis for Control
23–1. 23–2 Chapter Twenty-Three Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 18 Synchronous Manufacturing and the Theory of Constraints
1 Ardavan Asef-Vaziri Nov-2010Theory of Constraints 1- Basics Practice; Follow the 5 Steps Process Purchased Part $5 / unit RM1 $20 per unit RM2 $20 per.
Copyright © 2007 Prentice-Hall. All rights reserved 1 Special Business Decisions and Capital Budgeting Chapter 25.
7 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Constraint Management 7 For Operations Management, 9e by Krajewski/Ritzman/Malhotra.
Throughput World. 2 Ardavan Asef-Vaziri Nov-2010Theory of Constraints: 2- Basics Systems Thinking and TOC  TOC Premise 1: The Goal of a business is to.
© The McGraw-Hill Companies, Inc., Synchronous Manufacturing and Theory of Constraints.
Managerial Accounting Concepts and Principles
1 Ardavan Asef-Vaziri Nov-2010Theory of Constraints 1- Basics Purchased Part $5 / unit RM1 $20 per unit RM2 $20 per unit RM3 $25 per unit $90 / unit 110.
C H A P T E R 9 Evaluating Personnel and Divisions.
Operations Scheduling. Scheduling in a Process-Focused Environment.
20 Variable Costing for Management Analysis
1 Slides used in class may be different from slides in student pack Chapter 18 Synchronous Manufacturing and the Theory of Constraints  Goldratt’s Rules.
Traditional Cost Management Traditional Cost Management C H A P T E R 6.
Production Activity Control
Supply Chain Management: The Game Developed for the Engineering Management Program James R. Holt, Ph.D., PE.
Ricardo Ernst Top Management Program in Logistics & Supply Chain Management (TMPLSM) Production and Operations Management 6: Theory of Constraints.
On Target Group Coaching
Chapter 2 Basic Managerial Accounting Concepts
Accounting Principles, Ninth Edition
1 The budgeting process The traditional goals of the planning and control process are: - to identify the economic goals and how to achieve them - to measure.
Chapter 17 – Additional Topics in Variance Analysis
Chapter 10 The Use of Budgets for Cost Control and Performance Evaluation.
Introduction to Theory of Constraints
Chapter 26 Part 1.
Introduction to the Theory of Constraints (TOC) & Critical Chain Project Management (CCPM) Major Mark McNabb.
ENGINEERING ECONOMICS ISE460 SESSION 2 CHAPTER 2, May 28, 2015 Geza P. Bottlik Page 1 OUTLINE Questions? News? Chapter 2 – Financials Chapter 8 - Costs.
 Copyright, Ansari, Bell, Klammer and Lawrence, Management Accounting: A Strategic Focus, Irwin-McGraw-Hill, THE THEORY OF CONSTRAINTS AND THROUGHPUT.
TOC 1 Theory Of Constraints. TOC 2 Theory of Constraints How does TOC differ from the conventional shop control theory? Throughput definition * Emphasis.
Chapter 25 Short-Term Business Decisions
Systems Thinking and the Theory of Constraints Any intelligent fool can make things bigger, more complex, and more violent. It takes a touch of genius.
Theory of constraints Slovak University of Technology Faculty of Material Science and Technology in Trnava.
Inventory Management FIN 340 Prof. David S. Allen Northern Arizona University.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved. 1.
Synchronous Manufacturing and Theory of Constraints
Aggregate Planning Chapter 13. MGMT 326 Foundations of Operations Introduction Strategy Managing Projects Quality Assurance Facilities & Work Design Products.
The Theory of Constraints
Differential Cost Analysis
© The McGraw-Hill Companies, Inc., Chapter 17 Synchronous Manufacturing and the Theory of Constraints.
© 2007 Pearson Education Constraint Management Chapter 7.
Introduction The dilemma for companies is to find tools that allow the evaluation of managers at all levels in the organization. How would the evaluation.
1 Session 18 Implementation of TOC at Tosoh, SMD Laura Blum Production and Inventory Control Manager.
Differential Cost Analysis
The Goal A Process of Ongoing Improvement Eliyahu M. Goldratt and Jeff Cox.
Module 10: Theory of Constraints Operations Management as a Competitive Weapon.
2.3 How do businesses survive?1 Must prepare a business plan/forward plan (set objectives) to ensure that: Meet customer needs and wants Manage costs effectively.
12-1 Performance Assessment C hapter 12 Prepared by Douglas Cloud Pepperdine University.
Constraint Management Chapter 7 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
5 © The McGraw-Hill Companies, Inc., 2002 McGraw-Hill/Irwin 5 5 Slide 5-1 Target Costing,Theory of Constraints, and Life-Cycle Cost.
Ratio Analysis…. Types of ratios…  Performance Ratios: Return on capital employed. (Income Statement and Balance Sheet) Gross profit margin (Income Statement)
Introduction to the Theory of Constraints (TOC) & Critical Chain Project Management (CCPM) Major Mark McNabb.
McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved
MODULE 3 Manufacturing Methodologies
Synchronous Manufacturing and Theory of Constraints
Introduction to Theory of Constraints
The Theory of Constraints
Synchronous Manufacturing
Constraint Management
The Goal.
Goldratt's Theory of Constraints (TOC)
Theory of Constraints Part II: TOC Concepts
Synchronous Manufacturing and Theory of Constraints
Presentation transcript:

Introduction to Theory of Constraints Competitive Manufacturing Management

Where it all began In 1984, Eli Goldratt wrote an international best seller on operations management -- The Goal. In this text, which was written in the form of a novel, he outlined his views of operations management -- specifically, finite capacity scheduling. Since it was first published, he and others have continued to expand the systems thinking he laid out in The Goal.

Product P $90/unit 100 units/week Product Q $100/unit 50 units/week Resource D 15 min/unit Resource D 5 min/unit Resource C 5 min/unit Resource C 10 min/unit Resource B 15 min/unit Resource A 15 min/unit Resource B 15 min/unit Resource A 10 min/unit RM 1 $20/unit RM 2 $20/unit RM 3 $20/unit Purchased Part $5/unit Weekly OE = $ each of resources A, B, C, & D 2400 min/week

Base Scenario What is the most profitable product mix? How much money can be made in 1 week given the above information?

Base Scenario WCPQRequiredAvail A B C D

Base Scenario PQ Selling price$90$100 Materials Contribution Total Direct labor60 min. 50 min. CM/DL min$.75 $1.20 therefore make Q’s first, then P’s

Base Scenario If we make Q’s first then P’s, we can make 50 Q’s and then 60 P’s PQ CM make*60*50 Profit = OE -300 profit

Base Scenario If we make P’s first then Q’s, we can make 100 P’s and then 30 Q’s PQ CM make*100*30 Profit = OE +300 profit

Base Scenario PQ Selling price$90$100 Materials Contribution Total Constraint 15 min. 30 labor min. CM/Con. min$3.00 $2.00 therefore make P’s first, then Q’s

Theory of Constraints The constraint determines Throughput (the rate at which a company makes money through sales.) An hour lost on the constraint is an hour lost for the system. An hour saved on a non-constraint is a mirage.

Five Focusing Steps of TOC Identify the constraint. Decide how to exploit the constraint Subordinate everything else to the decision made in step 2. Elevate the constraint. If the constraint is broken in step 4, start over and do not allow inertia to become a constraint.

Alternate scenario 1: changes to the base scenario Your engineer is all kinds of excited and tells you that he has found a way to modify one of the processes -- a process is a chain of work centers -- so that it will take now take 21 minutes to to complete rather than 20 minutes AND it will only cost $3000 to do it. Should you fire the guy on the spot or allow him to finish his explanation? If you haven't fired the engineer, he continues his explaination by telling you that the middle process can be revised such that WC B can do the job in 14 minutes if WC C works an additional 2 minutes. What would be the result of the revision in terms of product mix and weekly profit? How long will it take to recover the investment?

Alternate scenario 2: changes to the base scenario Your marketing department has found an alternate market for your products in Japan. The US and Japanese markets are perfectly segmented (i.e. the sales price in one country will not affect the sales price in the other country). The catch is that while the Japanese will buy P and Q in the same quantities as the US they are only willing to pay 80% of the US price -- $72 for P and $80 for Q. Additionally, you can purchase another B machine for $100,000. You will need to hire another person to run it for $400/week which brings weekly operating expenses to $6400. Should you sell to the Japanese? What about product mix and weekly profit? How long will it take to recover the investment in new machinery?

The PQ Problem Now we have already solved this problem and know that the way to exploit the constraint (resource B) is to make the “least profitable” product first P’s and 30 Q’s yield a $300/week profit. This is true because we focus on and exploit the constraint.

Y Y YYY Z Z $5 6 min/unit8 min/unit 10 min/unit 20 min/unit $5 $10 $52$55$50 Product A Product B Product C Product D 10 min/unit 5 min/unit

Which Product Should be Made? Product Price - Materials - Labor cost/unit = PROFIT MARGIN A$50 - $20 - (36 min. X $10/hr) = $24.00 B (38 min. X 10/hr) = C (35 min. X 10/hr) = D (35 min. X 10/hr) = 26.17

The Accounting Perspective: Product D profit = revenue - material expense - labor expense =($52 X 16u) - ($20 X 16u) - (2 wkrs X 8 hrs X $10) = $352 / day Your accountant would recommend making product D for a daily profit of $352. If the firm makes only product D, then in an 8 hour day, since 30 minutes per product are required in work center Z, 16 units (8 hours/30 minutes) can be reproduced.

The Marketing/Sales Perspective: Product C profit = revenue - material expense - labor expense =($55 X 16u) - ($25 X 16u) - (2 wkrs X 8 hrs X $10) = $320 / day Marketing in many instances is measured by the revenue generated and since product C generates $55 per unit, it is the logical choice. Second, salesmen commissions are generally based on a percentage of selling price, C again is the logical candidate.

The Operations Perspective: Product B profit = revenue - material expense - labor expense =($50 X 24u) - ($25 X 24u) - (2 wkrs X 8 hrs X $10) = $440 / day From the plant manager’s point of view, product B is the logical choice. It gives a 90% utilization of work center Y and a 100 % utilization of work center Z.

Traditional Performance Measures: Limitations Standards and Variances, Direct Labor productivity, and Machine Utilization place emphasis on achieving goals in and of themselves. Overhead Allocation by direct labor investment is also inappropriate. When this method was developed, DL comprised most of a product’s cost; now the percentage is usually less than 10%.

Traditional Performance Measures: Limitations Traditional measures also tend to: –ignore inventory status and lead time; –be organized by functional silos; –and, emphasize past and near-future (short-term) results. Many of the tools and processes we have discussed this term tend to increase (rather than decrease) costs in the short-term, but the long- term benefits are undeniable.

Enlightened Measures: Productivity Traditional measures tend to separate OH (IL) and DL, causing managers to focus on DL reduction. As world-class companies embrace empowerment, etc., many IL duties are shifted to DL employees.

Enlightened Measures: Principles Competitive Focus Emphasis on Clear, Common Sense Measures Emphasis on Trends and Long-Term Improvement

Aligning Functional Decisions with Organizational Goals At the organizational level, companies use three main types of measures: profitability, returns, and solvency. Often companies use Net Profit, ROI, and Cash Flow. All three should increase (or at least not decrease. The impact of decisions made at lower levels in the organization on these three measures is not readily apparent, so companies use other measures (e.g. commissions, utilizations, etc.)

Company President Firm Plant Manager Plant Profit and Loss Statement Vendors -quality -cost -delivery Purchasing Dept. $ Saved -volume discounts -variances -make vs. buy Production Dept. Utilization Efficiency Workers -keep busy -absenteeism -grievances -safety Transportation Dept $ Saved -transportation -warehousing Truckers -costs - $ damaged Income Statement Balance Sheet Funds Flow Statement President -net profit bonus Sales Dept. Manager -revenues generated Salesmen -commissions Customer Satisfaction -product -price -quality -time A simplified manufacturing organization chart illustrating the performance measurement dilemma Net Profit, ROI Cash Flow

Y Y YYY Z Z $5 6 min/unit8 min/unit 10 min/unit 20 min/unit $5 $10 $52$55$50 Product A Product B Product C Product D 10 min/unit 5 min/unit

What We’ve Already Seen Accounting would choose to make Product D yielding a profit of $352/day. Marketing and Sales would choose to make Product C yielding a profit of $320/day. Operations would choose to make Product B yielding a profit of $440/day.

What about Product A? ABCD SP RM T Z min =T/CM From a Theory of Constraints perspective, Product A is best. profit = revenue - material expense - labor expense =($50 X 24u) - ($20 X 24u) - (2 wkrs X 8 hrs X $10) = $560 / day

Throughput, Inventory and Operating Expense Goldratt suggests three measures: Throughput - the rate at which a company makes money through sales (Cash coming in should increase) Inventory - all things purchased by the company which might be resold (Cash going out should decrease) Operating Expense - the money a company spends turning Inventory into Throughput (Cash going out should decrease)

How do T, I, and OE Relate to Net Profit, ROI and Cash Flow? Net Profit = T - OE –As T increases so does profit –As OE decreases profit increases ROI = (T - OE) / I –As T increases so does ROI –As OE and/or I decreases ROI increases Cash Flow = T- I - OE –As T increases so does Cash Flow –As OE and/or I decreases Cash Flow increases

How do T, I, and OE Relate to Net Profit, ROI and Cash Flow? Net Profit increase ROI increase Cash Flow increase T increase I decrease OE decrease

Prioritizing TIOE First, increase Throughput. Second, decrease Inventory. Third, decrease Operating Expense. This is the opposite of what most companies will do. Two other TIOE measures: –Throughput-dollar-days –Inventory-dollar-days

Paradigm Shifts Cost accounting and T, I, OE are different paradigms. You should be able to see the world through both. You will certainly encounter cost accounting where you work, and you should know how to tell when it is misleading.

A Setup Example Resource V 20 min/unit Resource U 20 min/unit Resource W 5 min/unit (3 hour setup) If the market will take all that we can make, how many units should Resource W run on each setup? We could minimize total setup time per week by executing only one per week; however W can make 444/week and U (or V) can only make 120/week. Inventory increases. Or we could examine the constraint(s) U & V. Forgetting setup time; what percent of the time must W run to keep both U & V busy? Since W only needs to run 50% of the time, the other 50% can be spent in setup - run 3 hours then setup for 3 hours - 36 units. Resource W 5 min/unit (3 hour setup)

A Make/Buy Example Resource A 25 min/unit Resource B 5 min/unit Purchased part $5/unit This is your current process (a greatly simplified example). You have two resources A & B. You currently purchase a part that costs $5/unit. Option 1: You could make the part for 5 minutes of “A” time and a $3/unit raw material. The cost to make the part is $4/unit. Option 2: You could make the part for 15 minutes of “B” time and a $4/unit raw material. The cost to make the part is $7/unit. Which is the better decision?

Make/Buy: Option 1 You could make the part for 5 minutes of “A” time and a $3/unit raw material; given that you pay workers $12/hour, the cost to make the part would be less than the purchase price. [Calculated as follows: ($12/hr *.083 hr + $3/unit) = $4/unit to make]. Shouldn’t you make the part? Resource A 25 min/unit Resource B 5 min/unit Resource A 5min/unit Raw Material $3/unit Given that Resource A is the constraint, the true cost to make must include the impact on T -- which would be lower. You would be better off buying the part for $5/unit.

Make/Buy: Option 2 Resource A 25 min/unit Resource B 5 min/unit Resource B 15 min/unit Given that you are already paying someone to man Resource B and it is not the constraint, the only variable cost to make is $4/unit of raw material. You would be better off making the material -- T would increase. You could make the part for 15 minutes of “B” time and a $4/unit raw material; however, given that you pay workers $12/hour, the cost to make the part would be greater than the purchase price. [Calculated as follows: ($12/hr *.25 hr + $4/unit) = $7/unit to make]. Shouldn’t you buy the part? Raw Material $3/unit

Constraint Management The constraint determines Throughput (the rate at which a company makes money through sales.) An hour lost on the constraint is an hour lost for the system. An hour saved on a non-constraint is a mirage.

How do we Exploit the Constraint on the Shop Floor? We now know that the constraint must run at 100% efficiency to make the most money. Question: Should the non-constraints be required to run at 100% capacity? The answer is: NO! If non-constraint resources run at 100% capacity, then WIP is increased.

Drum-Buffer-Rope Production scheduling system following TOC principles. It is a hybrid push/pull system. The purpose DBR is to exploit the constraint.

The Drum The constraint determines the throughput of a plant. If we have an internal resource constraint, how do we maximize throughput? –Manage the constraint closely. If the constraint has such a significant effect on our operations, shouldn’t we consider it when we prepare the master production schedule (MPS)?

The Drum (con’t) The pace of the whole plant is determined by the pace of the constraint Therefore, we base the MPS on maximizing the constraint. Where do we want to minimize setups? We may want to try to group similar batches on the constraint to save setups We can use lot-for-lot (LFL) on non- constraints

Buffers We want to protect the throughput of the system from inevitable variability Inventory is a form of buffer, as is time. Location of buffers is critical –What points in the system need protection?

Buffers Required processing time: 40 hours Scheduled lead time: 40 hours Shipping due date: 40 hours What happens if an operation is disrupted?

Buffers (con’t.) Hrs Let’s add 20 hours of safety inventory as follows: What happens if there is a 10 hr. delay at Op. #1? A 10 hr. delay at op. #5? 4 Hrs

Buffers (con’t.) Hrs A better way to arrange our 20 hours of safety inventory might be: Now what happens if there is a 10 hr. delay at Op. #5?

Buffers (con’t.) Hrs What if operation #3 is a constraint and our safety inventory is in front of shipping? If operation #3 is a constraint, a disruption at operation #1 or #2 will reduce T for the system

Buffers (con’t.) Hrs A better way to arrange our 20 hours of safety inventory would be to protect both the constraint and the shipping schedule: 10 Hrs

The Rope The constraint acts as the Drum setting the pace for the whole system Inventory Buffers protect the shipping schedule and the constraint What else do we have to do to operate the system? –Have to tell everyone else what to do. Material release points and non-constraints

The Rope (con’t.) What do we have to tell material release points? To ensure that material gets to the constraint when needed, material release points need a schedule of: –What material to release –The quantity to release –The time to release it –The Rope ties material release to the constraint

Other Control Points Divergence points Assembly points These operators also need a detailed schedule. What do we have to tell operators of non-constraints? If material release points only release material at a rate to keep the constraint busy, non-constraints will have some idle time (no queues or short queues) => Operators of non-constraints just need to be told to work on things as they come in, FCFS