CMR Contract Documents Jon Walden Manager of Contracts & Compliance Ohio School Facilities Commission Lisa Conomy Construction Counsel The Ohio State University.

Slides:



Advertisements
Similar presentations
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Advertisements

Construction Engineering 221
Bob Smith, P.E. Region 1 Benjamin Acimovic, P.E., Region 1
Construction Contracting
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Presentation by: Tshewang Gyeltshen. The SBD is prepared in line with the PRR 2009 & SBD Large Works General principals of procurement to be applied prescribed.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
Chapter 15 Closing the Bid. Objectives Upon completion of this chapter, you will be able to: –Describe the estimate summary process –Describe items that.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect.
Your Presenters Lisa Dal Gallo Dave Kirn Regional Executive/Justice Market Leader Partner, LEED AP
Click here to add text The Single Prime Contractor Delivery Method Ohio School Facilities Commission Ohio Construction Reform.
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
4 th ANNUAL JOINT CSU/UC PSSOA CONFERENCE March 25-26, 2003 “Emerging Construction Methodologies in CSU – What Public Works Contract Specialists Should.
1 MOSS ADAMS LLP | 1 Case Studies in Contract Close Out Audits May 2014.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Your Deliver Method... …Pick it Early
Alternative Project Delivery Mechanisms The J. K. Spruce Experience Katherine Yates Assistant General Counsel.
Alternative Project Delivery
Lunchtime Topics Craig Weise Construction Reform Program Director Lisa Conomy Construction Counsel OSU Office of Legal Affairs.
Procurement and Tendering Presentation to [NAME OF CLIENT] [YOUR NAME] [DATE]
Facilities Institute July , 2012 Houston, Texas Click to edit Master title style
ATMES Spring Meeting April 26-27, 2012 Myrtle Beach, South Carolina International Projects.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
Construction process Types of contracts Halmstad University Construction management Piotr Mazur Paulina Wawryca Paweł Bilski.
KFUPM, Department of Construction Engineering and Management CEM 520 LIABILITY ALLOCATION AMONG THE PARTIES TO FIXED-PRICE CONSTRUCTIN CONTRACTS IN SAUDI.
Delivery Methods  The Players from Handbook of Architectural Practice, Chapter 9.1 by Phillip Bernstein FAIA  Variables from Handbook of Architectural.
ESTIMATING By Laith Jacob.
PROCEDURES FOR SELECTING THE CONTRACTOR
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
The Construction Specifications Institute Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT)
Design–Build Contracts G. Hardy Acree Director of Airports Sacramento County Airport System Advantages of of During Turbulent Times.
Chief Legal Counsel, OSFC
Construction Contracts and Project Delivery Methods
CEM 520 Construction Contracting Dr S. Almohawis Course Content.
IDENTIFYING THE STRENGTHS & WEAKNESSES OF YOUR CONSTUCTION PROJECT McCune Construction Services Group, L.C.C.
Welcome to the OCR Academy. Overview of Rules & Law Craig Weise Construction Reform Program Director.
January 24, …a delivery method which entails a commitment by the Construction Manager to deliver the project within a Guaranteed Maximum Price (GMP).
January 31, …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.
CONSTRUCTION CONTRACTS DOCUEMENTS
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Agency Construction Management :CM NOT AT-RISK
Generic Documents for the Design, Build, Operate Contract for a Solid Waste Facility.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
You passed the Bond or secured some funds What do we do now? 2014.
FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING SPRING SEMESTER ASSOC.PROF.DR. İBRAHİM YİTMEN CIVL 493 CONSTRUCTION MANAGEMENT.
Project Delivery Methods CM CONSTRUCTION DOCUMENTS Kevin A. Delorey 11 Feb 2010.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
Construction Auditing Tuesday, September 15, :00-5:15 pm Presented By: John Humphries Kelly Business Consultants 8084 Watson Road, Suite 200 St Louis,
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
IT PROJECT MANAGEMENT B U D I L U H U R U N I V E R S I T Y POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Construction Management At Risk Process
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 2 Construction Contracts.
CONSTRUCTION MANAGEMENT AT RISK Prepared by: Nancy Fouad Carey Attorney AGC Alabama Birmingham Section Meeting November 5, 2012.
Dallas Area Rapid Transit Pre-Bid Conference Solicitation No. B Bus stop Amenity Cleaning April 13, 2016.
“702 KAR 4:160, Capital construction process” 1.  To be developed as procedures document for K-12 school construction projects  Allows KDE to update.
Construction Contracts By: David Adelstein 1. What Contract Should I Use? Objectives (1)What are my design and construction objectives? Project size,
CSM Buildings Modernization DESIGN-BUILD QUALIFICATION CONFERENCE
CM at Risk v. Design-Bid-Build
PROJECT DELIVERY METHODS
Designers’ Manual Overview and Chapter Contents
Design-Build Process Utilizing Negotiated Selection
PROJECT DELIVERY METHODS
COST OF THE WORK: Tricks and Traps to Avoid in Contract Drafting
Construction Contracts
Presentation transcript:

CMR Contract Documents Jon Walden Manager of Contracts & Compliance Ohio School Facilities Commission Lisa Conomy Construction Counsel The Ohio State University

CMR Contract Documents General Thoughts Construction Manager at Risk (CMR) Contract is the State of Ohio template document Other Public Authorities (Counties, etc.) can use other CMR Contract templates: AIA, ConsensusDOCs, DBIA, EJCDC

CMR Delivery Method RC 9.33, A delivery method where the public owner transfers cost overrun risks at a certain point to a contractor who manages and builds the project under a Guaranteed Maximum Price (GMP)

CMRGC Owner A/E CMR Sub Owner A/E GC Sub

CMR Delivery Method The CMR serves as agent to the owner during the design process, but becomes the “contractor” during construction The GMP is a lump-sum, fixed cost (i.e. not cost reimbursable) paid on a progress basis

Selection of Key Players A/E Selection Similar to current model, RFQ CMR Selected using Best Value Process – Selection Process with the award resulting from consideration of both performance and pricing to determine the offer deemed most advantageous and best value to the public authority

CMR Contract Documents CMR Contract Documents consist of a group of documents all incorporated into the CMR Contract – Definitions – Agreement Form – GMP Amendment – General Conditions

Contracting Definitions The CMR Contract Documents add many new terms to the public construction lexicon Most of the Defined Terms contained in the Definitions rather than within the General Conditions

CMR Agreement Form – Sets forth basic contract information and evidences entry into the contract when completed and signed by the CM and Contracting Authority

CMR Agreement Form Identifies Scope of work, EDGE commitments, and Compensation Compensation broken out by Preconstruction Stage and parameters for Construction Stage Compensation

CMR Agreement Preconstruction Stage Compensation (Art 2 and also Article 9.1 of GCs) Construction Stage Compensation Key Personnel, Consultants

CMR Agreement General Provisions Enumerated Documents Shared Savings

Preconstruction Stage Payments Preconstruction Stage Payments from Three Buckets Fee Personnel ExpensesReimbursables Stipulated SumHourly, not to exceedAt Cost, no markup

General Conditions Preconstruction CMR Role in preconstruction is similar to a CM Agent Role of the CMR at each phase of preconstruction is to review and confirm documents align with the (a) scope, (b) schedule, (c) budget CM may engage Design-Assist Contractor as consultant

Preconstruction Services Program Verification Stage Schematic Design Stage Design Development Stage GMP Proposal and Amendment Construction Document Stage

Program Verification Stage Verification Project schedule and construction budget Review preliminary building needs, design, schedule, budget Site issues

Program Verification Stage Review of Provisional Program Documents Clarity, completeness, and coordination of documents Constructability Budget and schedule opinions

Schematic Design Stage Verify and Advise Project schedule and construction budget Refinement of program requirements Assist Owner and A/E with required filings Preliminary analysis of types and quantities of labor Recommendations for alternate approaches

Schematic Design Stage Review of Provisional Schematic Design Documents Clarity, completeness, and coordination of documents Constructability Budget and schedule opinions

Design Development Stage Verify, Advise, Refine Project schedule and construction budget (more detailed) More detailed project requirements (cost, safety, labor)

Design Development Stage Verify, Advise, Refine (cont’d) Assist Owner and A/E with required filings Preliminary analysis of types and quantities of labor Recommendations for alternative approaches

Design Development Stage Review of Provisional Schematic Design Documents Clarity, completeness, and coordination of documents Constructability Budget and schedule opinions

Design Development Stage CM Submission – Updated schedule – Detailed cost estimates – Refined Subcontracting Plan Proposed list of prequalified prospective Bidders for each Bid package and Bidding schedule

Design Development Stage CM Submission (cont’d) – The fully developed Subcontractor prequalification criteria

Subcontractors – Article 4 Article 4 of the GCs defines applicability of bidding requirements, exceptions for – General Conditions work – Certain Non-specialty work – Balance of terminated subcontracts – Self Performed work

General Conditions Costs Include only CMR’s costs to provide GC Work – General Conditions Work set out in exhibit See definition for list, but includes: – Scheduling and coordinating the work – Telephone, postage, photocopying, hand tools – Bond premiums – Builder’s Risk premium (if CM purchases)

Subcontractors – Article 4 Bidder Prequalification Criteria Bidder Prequalification Process – No later than 30 days before soliciting bids Bidding Process – No later than 60 days before work scheduled

Subcontractors – Article 4 Evaluation of Lower-Tier Subs Self Performed Work Use of State of Ohio Subcontracting Form

Self-Performed Work Article 4 sets forth parameters for self- performed work – Identified in Subcontracting Plan – Public Authority permission required – Prequalification

Self-Performed Work Article 4 (cont’d) – Bidding Document notification – Separation of CMR personnel managing and bidding – Early submission of bid to Public Authority – No use of contingency

Construction Documents Stage Continue to Align and Detail Scope Schedule Budget

Construction Documents Stage Refine Documents Project and Construction Progress Schedules Schedule of Values Front Ends and Division 1 (Manual) Opinion of Document Characteristics

Construction Documents Stage CD Submission Staffing Schedules Cash-flow Subcontracting Plan Logistics

Contract Sum Total CMR compensation From date of GMP Amendment through close-out Proper, timely, complete performance of the work Lump sum, Fixed cost

GMP Process CMR Preconstruction Services CMR Preconstruction Services GMP Proposal Parties Meet Adjust Clarify Parties Meet Adjust Clarify CMR Revised GMP Proposal GMP Proposal MEETS Budget GMP Proposal MEETS Budget Public Authority Accepts GMP Amendment GMP Amendment GMP Proposal EXCEEDS Budget GMP Proposal EXCEEDS Budget Terminate CMR Agreement Terminate CMR Agreement Select Alternate Delivery Convert to CM Agent Convert to CM Agent

Change Order Owner Reserve Contract Sum

GMP Amendment Basis documents – Includes Statement of Design Intent Assumptions and clarifications Estimates Schedules Staff

GMP ≠ Guaranteed or Maximum Things MAY c hange, such as: Scope E&O Differing Conditions

Phased GMP GMP may be phased Separate GMP Amendments by Phase

Change Order Owner Reserve Contract Sum

Three Buckets FeeCost of the CM WorkContingency

Contract Sum Fee ProfitOverhead Cost of Work CM Contingency Subcontracts Personnel General Conditions Self Performed

CM Use of Contingency Cost of WorkCM ContingencyOwner Reserve Buyout Savings Use of Contingency

Contingency Review Dates CM Contingency Fee Owner Reserve

Familiar Provisions Construction and Close-Out (Art. 6) Contract Modifications (Art. 7) Dispute Resolution (Art. 8) Suspension and Termination (Art. 11) General Provisions (Art. 12)

Bonding Requirements Contracting Industry expressed concern about exhausting bonding limits Working Group identified “Gap Bonding” as means to conserve contractor bonding capacity Surety industry rejected

Bonding Requirements Preconstruction Before signing Agreement 100% Preconstruction Stage Compensation Bond increases if compensation increases

Bonding Requirements GMP Amendment Condition Precedent 100% Contract Sum Surety consent to increase required for payment

Insurance Builder’s Risk Employers Liability Business Auto Commercial General Pollution

Insurance Professional CM Professional Subcontractors Additional Property – If demolition, blasting, excavating, tunneling, or shoring If Needed: Aviation, Watercraft, Ocean Marine

Umbrella Insurance Coverage in addition Plus $2M for listed specialty Work Plus $5M for – Caissons/piles – Demolition – Excavation/utility work – Sheeting/shoring/underpinning – Window washing equipment – Wrecking

CMR Contract Documents Questions: Lisa Conomy Construction Counsel, OSU Jon Walden Manager of Contracts and Compliance, OSFC