Christine Krall, SW Region Environmental Winter 2015
Erosion Control Implementation Plan (ECIP) Importance of ECIP review process Select Sites Erosion Control Order Form Releases 2
Requirement of DNR/DOT Cooperative Agreement and TRANS 401 Communicates the contractors means and methods to perform work Communication tool between DOT, contractor, subcontractors, and DNR Removes the need to have DNR general permits Meet the intent of the Clean Water Act 3
Erosion control – part of the construction project TRANS 401 Project Leaders – Complete Inspections and Orders TSS – Liaison to DNR, support to project leaders SW region ECIP review checklist provides process for review 4
Project leader reviews ECIP submittal for completeness and rejects if necessary Erosion control staff, project leader, project manager, and DNR review ECIP Erosion Control Engineer works with contractor to incorporate review comments ECIP accepted and approved (SW region process – each region is slightly different) 5
Submittals do not include: Complete schedule Plan sheets with temporary and final erosion control measures Select Sites with complete information 6
Schedule Narrative Construction staging Plan sheets Structures Select sites 7
Schedule limits the erosive land exposed. SS (4) The schedule coordinates temporary erosion control measures with the permanent erosion control measures to ensure economical, effective, and continuous erosion control. SS (2) Include all erosion control mobilizations Includes all subcontractors 8
“Contractor means and methods are out of our control.” “DOT doesn’t dictate means and methods.” DOT must have a current schedule Schedule provides the shortest practicable duration for exposure SS (4) Plan for best erosion control methods 9
The special provision requirements been met The contractor is prepared for rain events All waterways are protected Erosion protection is in place where water leaves the site and at cut/fill transitions Staging area locations are noted? Usage dates, and material type stored are provided 10
Submitted plan sheets show the contractor has accounted for erosion control at all stages of the project Plan sheets submitted include stages and temporary erosion control for each stage Limit open area Erosion control bid items are shown at interim stages The final erosion control plan is complete 11
Structures over waterways are highly sensitive Grade separation structures require large open slopes and grade changes that need to be addressed 12
Special provisions for water dates, animal issues, invasive species Debris capture system and removal plan Is USACE (corps) permit amendment required? Dewatering plan Stockpile and staging locations Water diversion plan 13
Commercial Sites: NR 216, DNR Construction Permit or DSPS Permit Current stormwater permit is on file with permitting agency Private Sites: Sites are approved under ECIP Need a reclamation plan and storm water plan Site must be used exclusively for one DOT project 14
Be Proactive Plan ahead for rain events Reduce Risk Limit exposure to erosion control Watch the weather Finish permanent slopes, install permanent erosion control items as soon as possible Install adequate temporary erosion control items 15
Reduce the sediment content to not more than that of the stream or lake into which the water is discharged. SS (7) DNR technical standards provides guidance Place pump intake in clear stone Treat effluent 16
17 Water leaving our project should be as clean or cleaner than receiving water
Seed placed after growing season Protect against erosion Establish seed and permanent measures Plan for winter is included if project will be finished in late fall 18
ECIP amendments are needed when there is a change in design, construction, operation or maintenance at a project site that has a potential for a discharge and is not addressed in the ECIP. Examples: Dewatering Increasing exposed erosive land Adding select sites Schedule changes that effect commitment dates 19
Provides timeframes for completing work 8, 24, or 72 hours Necessary documentation to elevate issues before major releases occur Key component in enforcement process Provided in TRANS
Defined by: Deposition of material outside of our right-of-way Turbid water – Water that is dirtier than the receiving water Fill out release form and submit to erosion control engineer Include pictures Plan to clean up release 21
Releases must be reported to DNR within 24 hours Corps is notified by erosion control engineer or environmental coordinator Cooperative Agreement requires annual compilation of releases 22
Erosion Control Standard Specifications (Legal) and 628 (Bid Items) Wisconsin State Legislature, Chapter Trans 401 Construction and Materials Manual 6-45 Wisconsin State Legislature, Chapter 216 Storm Water Construction Technical Standards (WDNR) 23
Christine Krall, P.E. Phone: Covering La Crosse, Monroe, Juneau, Vernon, Richland, Sauk, Crawford, and Grant Counties Brad Schultz, P.E. Phone: Covering Columbia, Dodge, Iowa, Dane, Jefferson, Lafayette, Green, and Rock Counties 24