ERCOT Planning Overview

Slides:



Advertisements
Similar presentations
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Advertisements

ERCOT Planning Overview and Summer 2014 Assessments Update
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Navarro to Houston Presentation to ERCOT RPG August 27, 2013.
Outage Coordination Overview D.W. Rickerson ERCOT Outage Supervisor 12/1/2008.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
NERC LTRA Update / CDR Capacity Counting Issues
ERCOT PUBLIC 10/21/ RTP Update October 21, 2014.
Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary1.
ERCOT PUBLIC 10/21/ LTSA Update October 21, 2014.
ERCOT PUBLIC 5/20/ RTP July 22, ERCOT PUBLIC 5/20/ Outline  Updates to 2014 RTP  RTP Next steps.
ERCOT PUBLIC 8/19/ LTSA Scenario Results Updates August, 2014.
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
ERCOT PUBLIC 4/22/2014 Updates for 2014 LTSA Scenario and Data Assumptions 4/22/2014.
RTP Update RPG Meeting July 21, RTP update  Reliability analysis for the contingencies where load shed is not allowed is complete.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
ERCOT PUBLIC 4/21/ Loss of Load Probability Assessment for NERC April, 2015.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
ERCOT PUBLIC 5/20/ RTP Inputs and Assumptions-Updated April 22, 2014.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
ERCOT PUBLIC 5/20/ RTP Inputs and Assumptions May 20, 2014.
ERCOT PUBLIC 4/22/ RTP Inputs and Assumptions April 22, 2014.
December 7, 2012 Transmission Needs Analysis Scenario 5/7 Update.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Impacts of Environmental Regulations in the ERCOT Region Dana Lazarus Planning Analyst, ERCOT January 26, 2016.
Long Term Study Transmission Results May 21 st, 2013.
Long Term Study Resource Expansion Process: Study Findings and Lessons Learned Jenell Katheiser Doug Murray RPG May 21, 2013.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Panhandle Renewable Energy Zone (PREZ) Study
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
2006 Report on the Capacity, Demand, & Resources for the ERCOT Region Technical Advisory Committee June 1, 2006 Kenneth A. Donohoo. P.E. Manager, Transmission.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
ISO Confidential Overview of California’s Current Drought and its Effects on the Energy System Dede Subakti, P. E. Director, Operations Engineering Services.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
ERCOT Transmission Planning Overview
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
2010 Northwest Regional Forecast Resource Adequacy Technical Committee April 22, 2010.
Houston Import Study Update
2018 LTSA Workshop August 2017 RPG Meeting Welcome to.
Transmission Planning in ERCOT- Overview
2016 RTP Update November, 2016 RPG Meeting.
Barrilla Junction Area Transmission Improvements Project
ERCOT 2009 Five-Year Transmission Plan Update
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
DEC System Voltage Planning - June 2018
Presentation transcript:

ERCOT Planning Overview

Objectives Discuss what resource adequacy entails. Understand the objective of the Capacity, Demand and Reserve Report (CDR) Understand the objective of the Seasonal Assessment of Resource Adequacy (SARA) Identify the remaining reliability issues requiring Constraint Management Plans (CMP) for 2015 Understand the Panhandle export stability limit and its possible effects on operations

ERCOT System Planning Load Forecasting Transmission Planning RTP LTSA RPG Reviews GINR Studies RMR Studies Dynamic Studies Resource Adequacy CDR Study SARA Study Loss of Load Study Drought Model Generation Availability Risk Analysis Load Forecasting Near-term Forecasting Long-term Forecasting Meteorology Load Profiling

What is Resource Adequacy? Resource adequacy is the ability to provide sufficient resource capacity to meet peak load requirements “Sufficient” resources includes a capacity reserve margin to account for weather variation, generation outages and load forecast error The traditional focus is the ability to supply resources for the ERCOT system’s annual peak load hour ERCOT comes up with an advisory minimum capacity reserve margin needed to maintain a low probability of involuntary load shedding (1 event in 10 years) Comparing the forecasted reserve margins reported in ERCOT’s reliability assessments with the minimum capacity reserve margin is a gauge of resource adequacy

Capacity, Demand, and Reserves Report Provides estimated ERCOT system-wide capacity reserve margins for ten years (Summer and Winter Peak Season) Peak load forecast based on expected (normal) weather conditions Load resources and utility demand response programs counted Existing resource counted based on status and capacity. Seasonal sustainable capacity ratings (Summer / Winter) Capacity contribution of Wind, Hydro, DC Ties, PUNs and Solar (future) resources based on historical performance during peak periods Switchable, Retired, Mothballed resources accounted for based on reported availability from Resource Entities Planned resources with executed SGIA, air emissions permits and water supplies (if required) counted based on projected in-service dates

December 2014 CDR Summer Expectations Current “minimum planning reserve margin” is 13.75% ERCOT region exceeds minimum PRM criterion through 2018

Renewables Being Added at a Rapid Pace… Not included here are over 14,000 MW and 6,100 MW of planned wind and solar capacity, respectively, for which interconnection requests have been made, but have not executed an interconnection agreement. Not included in the chart are over 14,800 MW of planned wind and 5,900 MW of planned solar capacity for which interconnection requests have been made but no interconnection agreement have been executed yet.

…Resulting in Fewer Dispatchable Resources like Gas and Coal

Seasonal Assessment of Resource Adequacy (SARA) A deterministic scenario-based view of near-term resource adequacy (for two upcoming seasons-Spring Summer, Fall or Winter) Focuses on sufficient operating reserves to avoid Energy Emergency Alerts (EEAs) Incorporates A) seasonal peak load forecast and B) latest available information on resource outages Illustrates a range of likely resource adequacy outcomes including extreme weather/unit outage scenarios Increasing emphasis on forecasting winter resource adequacy due to weather-related gas curtailments

2014-15 Winter SARA (Final) Item Winter 2014/2015 1 Forecasted Season Peak Load Extreme Load/Expected Generation Outages Extreme Load/Extreme Generation Outages 1 Total Resources (MW) 77,350 2 Peak Demand (MW) 52,837 3 Reserve Capacity (MW) 24,513 4 Extreme Peak Load Adjustment (MW) -- 6,805 5 Maintenance/Forced Outages 7,880 11,524 16,552 6 Uses of Reserve Capacity (MW) [4+5] 18,329 23,357 7 Capacity Available for Operating Reserves [3-6] 16,633 6,184 1,156 * * Less than 2,300 MW available for Operating Reserves indicates risk of EEA1

Regional Transmission Plan (RTP) - Objective Regional Transmission Plan is developed annually by ERCOT in coordination with the RPG and the TSPs Annual assessment to identify transmission needs of ERCOT system over next six years Projects identified to meet the ERCOT/NERC reliability requirements (Reliability projects) and to reduce system congestion (Economic projects) that meet the ERCOT economic criteria The RTP system upgrades identified need to be further reviewed by the appropriate TPs to determine the need for an earlier in-service year

2014 Regional Transmission Plan (RTP) - Process Case Conditioning Future projects review and update Future generation review and update (addition and retirement) Load comparison and adjustment Transmission outages, DC tie dispatch, and SOL updates Reliability Analysis Run N-1 SCOPF to obtain initial list of overloads Run G-1 + N-1 and X-1 + N-1 screening to identify generator and transformer outages to study Add, or improve existing, transmission projects to mitigate overloads Economic Analysis Run economic analysis Add or improve projects that meet the economic criteria

2014 Regional Transmission Plan (RTP) – Overview of Results 117 reliability improvements identified 40% resulted from, or were impacted by, the new X-1+N-1 criteria Large number of unresolved reliability issues for 2015

Transmission Improvement Planned Improvements Map Index Transmission Improvement In-service Year 1 Temple Switch – Bell County East 345 kV line upgrade 2015 2 New Lobo –North Edinburg 345 kV line (Valley Import) 2016 3 New North Edinburg – Loma Alta 345 kV line (Cross Valley) 4 New Fowlerton 345 kV station with 345/ 138 kV transformer 2017 5 Add second Jewett 345/ 138 kV transformer 6 Add second Jordan 345/ 138 kV transformer 7 Add second Twin Buttes 345/ 138 kV transformer 8 McDonald Road – Spraberry 138/ 69 kV line upgrade 9 New South McAllen 345 kV station with 345/ 138 kV transformer 10 Tradinghouse – Sam Switch 345 kV line upgrade 11 New Jones Creek 345 kV station with two 345/ 138 kV transformers 12 Houston Import Project 2018 13 Venus – Navarro 345 kV line upgrade 2019 14 Big Brown – Navarro 345 kV line upgrade 15 Trinidad – Watermill 345 kV line upgrade 16 San Antonio Transmission System Addition Project 17 Jack County 345/138 kV transformer addition 2020

Planned Improvements

2015 Reliability Issues Needing Constraint Management Plans (CMP) Map Index Transmission Element 1 Bosque Switch – Olsen TNP 138 kV line 2 Olsen TNP 138/69 kV transformer 3 Collin Switch – Frisco138 kV line 4 Flat Top TNP – Barilla Tap 138kV tie 5 McDonald – Spraberry 138 kV lines 6 Big Lake  138/69 kV transformer 7 Big Lake – Big Lake Phillips Tap 69 kV line 8 San Angelo Concho – San Angelo Mathis Field 69 kV line 9 Wink – Odessa Basin SS 69 kV line 10 Twin Buttes 345/138 kV transformer 11 Campwood – Montell - Uvalde 69 kV line 12 Skywest – Driver 138 kV line 13 Alice – San Diego 69 kV line 14 Freer  – San Diego 69 kV line 15 Asherton – Carrizo Springs 69 kV line 16 Asherton 138/69 kV transformer 17 Pleasanton 138/69 kV transformer  18 Howard  – Somerset 138 kV line A lot of these issues are in West and South Texas.

2015 Reliability Issues Needing Constraint Management Plans (CMP)

2015 Reliability Issues Needing Constraint Management Plans (CMP)

Comparison of Number of Unresolved Issues

Projected Constraining Element Remaining Congestion Map Index Projected Constraining Element 2017 Congestion 2020 Congestion 1 Baytown Energy Center 345/138 kV transformer   2 Dupont Switch – Dupont PP-1 (Ingleside) 138 kV line 3 Escondido – Eagle Hydro 138 kV line 4 Glen Rose – Meridian 69 kV line 5 Goldthwaite – San Saba Switch 69 kV line 6 Hamilton Road – Maverick 138 kV line 7 Jack Creek – Twin Oak Switch 8 Jewett – Singleton 345 kV line 9 Kiamichi Energy Facility – Kiowa Switch 345 kV line 10 Loop 337 – GPI Switch 138 kV line 11 Morris Dido – Eagle Mountain 138 kV line 12 Nevada – Royse Switch 138 kV line 13 Randolph – Weiderstein 138 kV line 14 Singleton – Zenith 345 kV line 15 Spur – Aspermont 138 kV line 16 Wolfgang – Rotan 69 kV line 17 Panhandle Export Limit Some congestion seen in 2017 is not seen in 2020 due to reliability projects being built in the interim timeframe relieving the congestion (e.g. Singleton – Zenith due to HIP). Congestion Color Key   None Low Medium High

Remaining Congestion

Panhandle Study ERCOT completed a Panhandle study in April, 2014 Study was initiated for a number of reasons: 2012 Long-Term System Assessment Significant expansion of wind resources in the Panhandle under a range of future outcomes. If the northwestern-most portion of the Panhandle CREZ system becomes over-subscribed, voltage stability limits will constrain wind power delivery to the rest of the ERCOT System Generation projects will exceed the CREZ design capacity for the Panhandle area (based on the CREZ Reactive Study “Initial Build” recommendations) No near-term Panhandle transmission projects being developed post CREZ 2013

Panhandle Study Identified the challenges and needs to integrate large wind generation capacity in the Panhandle region The results provide a roadmap to both ERCOT and TSPs that includes the upgrade needs and the associated triggers in terms of wind generation capacity in the Panhandle

Panhandle Region

Panhandle Study Results Stability challenges and system strength are identified as the significant constraints for Panhandle export The Panhandle is a weak grid Not what most operators are used to seeing

Stability Studies Planning study results: multiple thousands MW wind generation connect to the Panhandle Oscillatory Response Voltage Collapse

Ongoing Evaluation of the Panhandle ~3500 MW of wind capacity meeting planning requirements is enough to model the Panhandle export stability limit for transmission studies 1000 MW already in-service More than 3500 MW slated to be in-service by 2016 At that level of wind capacity, the Panhandle export stability limit is likely to be binding Wind plants may need to be curtailed to avoid violating the Panhandle export stability limit

Lower Rio Grande Valley Limited generation and transmission infrastructure High risk of rotating outages Can be at risk even when the rest of the ERCOT grid remains in normal operations Projects to improve reliability are underway

Availability of the Frontera Facility 170 MW of capacity will not be available to ERCOT starting January 1, 2015 The entire Frontera Facility will not be available to ERCOT after the Lobo – North Edinburg and North Edinburg – Loma Alta lines are energized in 2016

Effects of Frontera’s Availability on the Valley TOs will need to maintain a high voltage profile (~1.03 pu) in the Valley region during high-demand periods Stability issues will require transfers into the Valley to be limited at lower demand levels than in the past Planned outages for major 345-kV lines and generation in the Valley will be further limited Additional system upgrades will likely be required to reliably serve Valley load after 2016 if the Frontera Facility is not available after summer 2016 Valley load is quite remote. Are additional 345-kV lines the best system upgrade options? Planning studies will need to consider higher voltages and / or HVDC.

LNG Additions

Long-Term System Assessment (LTSA) - Objectives Focused on the 10-15 year time-horizon Different potential future scenarios are studied Projects are evaluated across these scenarios to determine what system upgrades may be needed under different future conditions

2014 LTSA - Takeaways There is the potential for a lot of solar generation to be built in the Panhandle and in West Texas Would affect the Panhandle export stability limit similarly to wind generation May require significant transmission investment to move power from sites favorable to solar to load centers System ramping requirements would need to be monitored closely in the morning and in the evening May cause there to be two system peaks – one around 5pm (peak load) and one around 8pm (peak load without solar generation) Six major potential reliability projects were identified across scenarios There is a large rate of change issue regarding solar build-out. We may have to deal with issues sooner than people think.

2014 LTSA - Takeaways Three stories: 1-4 are about growing load and lack of generation being built close to the load; 5 is about large solar build; 6 is about effects of LNG.

New Planning Criteria Compare to slide 12.

Questions ? ?

1) What is the study time horizon for the Capacity Demand Reserves (CDR) report and the Seasonal Assessment of Resource Adequacy (SARA)? 10 years and the upcoming season (Spring) 5 years and the upcoming season (Spring) 10 years and 2 upcoming seasons (Spring, Summer) 5 years and 2 upcoming seasons (Spring, Summer) None of the above.

2) Which of the following is not an input to the Capacity Demand Reserves (CDR) report? Load forecast for summer and winter peak seasons Seasonal resource capacity ratings Delivered natural gas prices Capacity contribution of wind and solar resources Projected in-service dates of planned resources

3) Which ERCOT Resource Adequacy study takes into account estimated resource outages during the forecasted peak load hour for the upcoming season(s)? Capacity Demand Reserves (CDR) report Loss of Load Probability (LOLP) study Seasonal Assessment of Resource Adequacy (SARA) A and B None of the above

4) What region(s) within ERCOT have the most remaining reliability issues requiring CMP for 2015? Houston area West Texas South Texas B and C All of the above

5) Which of the following pieces of evidence indicate that the Panhandle export stability limit may be a significant reliability constraint? It is highly congested in both 2017 and 2020 economic simulations conducted for the 2014 RTP The Panhandle study indicates possible stability issues for the number of wind IAs currently in the queue Significant solar build-out in the Panhandle for several LTSA scenarios, affecting the limit similarly to wind All of the above None of the above