Muon Campus Controls Update Brian Drendel 8/6/13.

Slides:



Advertisements
Similar presentations
Transition from the Long Shutdown to Hot Checkout: Pre-Hot Checkout Steve Suhring Operability Manager 6/6/13.
Advertisements

Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
Muon g-2 Inflector AEM Meeting 11/25/2013 Chris Polly Muon g-2 Project Manager.
Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Fermilab 1 AP Dept. Activities Report September 20, 2006Dixon Bogert AP Dept. - Activities Report Dixon Bogert - AP Dept. Meeting September 20 th, 2006.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Thomas Jefferson National Accelerator Facility Page 1 IPR October 18-20, 2011 John J. LeRose Independent Project Review of 12 GeV Upgrade Jefferson Lab.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Delivery Ring AIP Jerry Annala Dec 12, µ Scope Beam line aperture improvements Beam line aperture improvements Beam line power supply upgrades Beam.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Beam Transport AIP Beam Transport to Delivery Ring Instrumentation and Controls Update Brian Drendel December 15, 2014.
Mu2e WBS 2 Accelerator Progress Report Mu2e WGM 6/15/2011 Steve Werkema L2 Manager for the Accelerator Systems.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
12 GeV Upgrade Project Status Allison Lung Hall C Users Meeting Jefferson Lab January 18, 2008.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
AGS RSVP Weekly Meeting P. Pile 16 September 2004 AGS RSVP Weekly Meeting, 16 Sep 2004 AGS Project Office - status of funding, comments on RSVP
Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012.
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
HFT face-2-face F.Videbaek Brookhaven National Lab.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Mu2e Cost and Schedule Ron Ray Mu2e Project manager Fermilab PAC Meeting November 3-4, 2008.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
Executive Session Director’s Progress Review of the NOvA Project August 4-5, 2010 Dean A. Hoffer.
End Station A Test Beam (ESTB) Carsten Hast and Mauro Pivi August 23 th 2012 Proposals, Procedures, Schedule.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Director’s Review 5/5/03 Spalding DRAFT RLS 1 Project Planning  Documentation to DOE June 1  DOE Review ~July 22 Documents Summary Project Overview,
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Mu2e WGM 11/16/2011 R. Ray Mu2e Project manager. Review of the past few months In September it became apparent that the cost of Mu2e was well in excess.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Mu2e Mu2e CD-2 Review Template Eric Prebys Extinction October 21-24, 2014.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Fermilab 1 SNUMI Civil Issues September 18, 2006Dixon Bogert SNUMI Civil Design & Site Considerations; Issues and FESS work Dixon Bogert SNUMI Meeting,
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
News Y2K June 25, Summary of June 12 Face-to-Face Meeting.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
What we have now – the Pbar source 1 1/23/2013 J. Morgan.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Brian Drendel September 11, Funding and Deadlines Muon Campus Controls  Controls plan for existing buildings  Controls plan for new buildings.
Muon Department Meeting Jerry Annala Staged Commissioning of Muon Campus 17 December 2015.
Audits & DOE Walkthroughs ISO and OHSAS surveillance audits August 18 th – 20 th –CD, ESH&Q, and FESS organizations to be audited Software.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Brian Drendel February 7, Mu2e and g-2 overview Look at controls  Beam Abort Loop  Beam Line Controls  Storage Ring Controls Homework.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
Brian Drendel October 31, This talk  Beams-doc private/DocDB/ShowDocument?docid=4474https://beamdocs.fnal.gov/AD-
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted.
Head, Office of Project Management Oversight (OPMO)
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
News and brief overview of Beamline plans for the next few months
Hall C SHMS & Configuration Status
X-Ray Endstations Update
Details supporting the increase
Test Beamline System Requirements and Charge to PDR Committee
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Muon Campus Controls Update Brian Drendel 8/6/13

Recent Reviews Independent Design Review of AIP and the Accelerator portion of g-2 (June 5-7) – Controls Talk: GM2-doc-1039 – Technical Review – Closeout presentation – GM2-doc-1113 Director’s Review for g-2 (July 23-25) – Controls Talk: GM2-doc-1151 – Cost Review – Close-out presentation -

Independent Design Review Controls and Safety Findings – The new accelerator components will be controlled through the standard Fermilab Accelerator controls system and controls devices. During the construction of the Muon Campus communication signals from the accelerator complex will be disconnected to the entire area and reconfigured. Only the portion of the work involving MC-1 is charged under the g-2 project. – Personnel and equipment safety will be handled through the existing safety systems for the accelerator complex. – The radiological environment for g-2 throughout the complex will be at or well below the historical levels of this area. The beam power on target will be 20% of the power on target for antiproton production. The beam power in the tunnels and in the Delivery Ring will be 1% of that under previous running conditions. – The shielding design for M4 and M5 enclosures and shielding upgrades to the Delivery Ring straight sections are driven by Mu2e, not g-2, considerations. The enclosures are not part of the g-2 project. – All radiation safety parameters for the g-2 muon experiment are well within acceptable limits. Comments – Appropriate consideration is being given to the delivery of control signals and communications to the Muon Campus, in particular re-routing of signals to the Delivery Ring and its service buildings and to MC-1. – Radiation and personnel safety issues have been appropriately addressed. Recommendations – None.

What worked Detailed BoEs. Plain English Documentation of plan and costing. Vendor Quotes and Sample PO’s. Beams-doc-4327

Mu2e Any Delivery Ring, Beam Line or Mu2e controls specific to Mu2e Beam Transport Controls – Mu2e-doc-1572 – Charge to “AD-Mu2e-Accelerator PED ” Delivery Ring Controls – Mu2e-doc-1468 – Charge to “AD-Mu2e-Accelerator PED ” External Beam Line Controls – Mu2e-doc-2136 – Charge to “AD-Mu2e-Accelerator PED ”

Muon g-2 Controls, Communications and Safety System to the MC-1 Service Building. Charge all time to “AD-g-2 Ctrls-Instrmt CD A005” MC-1 Controls and Communications – GM2-doc-728 MC-1 Safety System – GM2-doc-896

Delivery Ring AIP Beam Transport AIP Reestablish Controls to existing Muon Campus service buildings (AP10, AP30, AP50, AP0, F23 and F27) Delivery Ring Controls (Beams-doc-4338): Charge to “AD-Delivery Ring AIP CD ” Beam Transport Controls (Beams-doc-4377): Charge to TBD (charge to the other AIP for now, and we will fix the charges later).

Cyro AIP Establish Cryo controls to the MC-1 Cryo room. Cryo AIP Controls (Beams-doc-4327): Charge to “AD-

Accelerator Controls Scope New controls and communication connectivity will be established from the cross gallery to the MC-1 service building. Brian Drendel, Muon g-2 CD1 Director's Review, July

Accelerator Controls Scope Controls Ethernet Hot-Link Rack Monitors Timing Link Beam Synch Link Beam Abort Link Site Emergency Warning System Fire and Utility System RADMUX Phone 10 Brian Drendel, Muon g-2 CD1 Director's Review, July

Accelerator Interlocks Scope 11 Brian Drendel, Muon g-2 CD1 Director's Review, July Pbar-style interlocks – Delivery Ring enclosure extended. – New Extraction enclosure. Rack Mounted Safety System (RMSS) – MC-1 Experimental Hall Oxygen Deficiency Hazard (ODH) system for MC-1.

Controls and Communications to AP30 Controls and communications signals will enter AP30 via the existing and unused Cryo duct.

Controls to AP30 Controls and communications cables enter AP30 and go to nearby racks.

Near Term Schedule September 13 th : All PO’s for cable and hardware purchases turned in. Both for AP30 and MC-1 pulls. September - October: Cleaning up Cryo Duct October 1: Order cable and hardware November – December?: Inner duct pulls, cable pulls and terminations.

Mu2e Schedule 15 July 2014CD-2/3 signoff May 2014DOE CD-2/3 review Mar. 2014Director’s Review Feb. 2014Documentation complete Dec. 2013L2 documentation complete Nov L3 documentation input complete Background simulations complete Aug. 2013CD-2 configuration completely defined. Ron Ray Time 8/1/2013Mu2e Accelerator L3 Meeting

Other Mu2e Project Management Schedule is updated Monthly – Mu2e-doc-3001 Earned Value Management System (EVMS) – Requires monthly progress reports on the schedule Start dates Finish dates Resources %Complete Hours remaining New BoE form specific to Mu2e is on the way (Mu2e-doc-3181)

Funding profile and current lab guidance An additional site power feeder ($1.1M) is included here; if needed in 2017 or 2018, it will actually have to be done as a new GPP Beam Transport and Delivery Ring AIPs have not been baselined yet Muon Campus AIPs and g-2 have been given high priority for Accelerator Division manpower in FY14 17 M Convery, Muon g-2 CD1 Director's Review, July

Muon g-2 Accelerator Schedule CD-0 Forecast KPPs Satisfied CD-1CD-2/3aCD-3CD-4 Conceptual Design Prelim/Final Design - Accelerator Safety system AP2/AP3 disassembly M2/M3 installation M4/M5 installation D30 Straight Section reconfiguration DR extraction installation Prelim/Final Design – Ring & Detector (& D30) Target Station Ctrls to MC-1 may shift based on funding Instrumentation, magnets, stands, etc, not shown but will be prepared prior to installation. Beamline power supply work also not shown and may be ongoing throughout implementation phase. Beam Studies Lehman CD-1 Review Sept

Path to CD-1 Lehman Review for g-2 Lehman Review: September All material posted: Tuesday, September 3 Freeze schedule: Tuesday, August 13

Questions from Chris Jensen I need to verify that there are sufficient spares of the Camac cards that he needs at MI50, AP30 and AP50 {total cards = C479 (x4), C284 (x4), C217 (x5)}. I'd like to reserve the cards that he needs for his use if possible. I need labor estimates (engineer and technician) for both (design and implementation) to implement the Camac controls for each of Chris' kicker systems. Chris would prefer HRMs at MI-52, AP30 and AP50 for the analog readbacks. Since we don't have HRMs planned for these buildings, this would mean additional cost. From previous cost estimates I have this as $15.5K per HRM, with labor of Electrical Engineer (1 week/HRM), Electrical Technician (1 week/HRM) an Computer Professional (1 week/HRM). Chris needs to verify that beam synch clock at the MC-1 service building for the kicker into the g-2 ring. I know we will be providing beam synch via one of the multimode fiber pairs that run from cross gallery to MC-1. I need to verify that our HRMs at MC-1 will be able to decode beam synch, since we have no Camac in that service building.

Questions from Cryo Need to verify Cryo schedule

Updates Go around the room and get updates:

Summary We have a busy schedule ahead with – Preparing g-2 for CD-1 Lehman Review Fall/Winter Beam Studies – Preparing Mu2e for CD-2 EVMS New BoEs Reviews – Getting the AIP’s approved