LBT Q1 2007 Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.

Slides:



Advertisements
Similar presentations
Network Design Issues Design and Documentation Prepared by: Aline L. Mendoza.
Advertisements

LBT Q Eng/SW Review ALPC – Primary Mirror Aluminum Shooting.
LBT Q Engineering Review ALPC – Primary Mirror Aluminum Shooting.
SUNY Canton Facilities Project Update Miscellaneous.
INTD 51 human environments building systems. heating/ventilation/air-conditioning (HVAC) maintain a comfortable indoor climate control temperature and.
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 21 July 2003 Sam Burke UCSB HEP Group.
Cable and Service Installation David Warner Colorado State University May 11, 2009.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
By Spencer Mendible. My Perfect Family Room  Color of Walls: Red  Floor: Tan Carpet  Windows: 2  Lights: Wooden Ceiling Fan.
The Evolution of the TERRA Crystal Galleries Mineral Showroom.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 LBT Q Engineering Review PWR: Site electrical power, includes power install on levels 1, PEPSI bridge, and 4, and power monitoring.
1 LBT Q Eng/SW Review ECS: Enclosure Control System.
LBT Q Engineering Review Swing Arms (SWA) Apr-04LBT Q Engineering Review Highlights (Q4/2007) The PF SAs lost their cable trays The.
LBT Q Engineering and Software Review ENGG Engineering General.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
1 LBT Q Engineering Review ICS – Instrument Cooling System.
1 LBT Q Eng/SW Review PLMG: Plumbing. 2 Highlights (Q2/2008) Have recently replaced worn contactors in the Primary Loop chillers Have recently replaced.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
LBT Q Eng/SW Review MCSC – Mount Control System.
EHN1 North Wall Dismantling Schedule Bastien Rae.
QBC Europe and its facilities. Building purchased – 1 st August 2006 Open for business – 6 th October 2006.
LBT Q Engineering Review DYB. 21-Dec-2007LBT Q Engineering Review Highlights (Q4/2007) Currently in Commissioning Phase Currently in Commissioning.
LBT Q Engineering Review Instrument Cooling.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
CTRA Green Features. 1. Green Roof 2. Hot Water Solar Heaters These are a type of solar panel. It is called evacuated tube collectors and they heat our.
NA YETS: schedule week by week S. Evrard.
LBT Q Engineering Review SAB Static Balancing.
1 LBT Q Engineering Review PLMG: Plumbing, includes IC system, chiller systems, instrument lab cooling, and LUCIFER cryo-compressor cooling.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
1/21/2016D.S. Sachdev1 Internal Cladding Systems in Buildings.
1 LBT Q Eng/SW Review PWR: Site electrical power.
Students will: Learn about the complexity of sending messages over the Internet Translate URLs into IP Addresses Practice creative problem solving.
LBT Q Eng/SW Review CIN/NIN -Computer and Network Infrastructure.
LBT Q Engineering Review ESW Engineering Software.
1 LBT Q Engineering Review PWR: Site electrical power, includes power install on levels 1, PEPSI bridge, and 4, and power monitoring.
1 LBT Q Engineering Review ECS: Enclosure Control System, includes the dewpoint sensor, CA system upgrades, grounding, enclosure track performance.
LBT Q Eng/SW Review CIN/NIN -Computer and Network Infrastructure.
Advanced Energy Engineering Technology Modeling Building Energy Systems Session 9: Modeling heating and cooling systems.
1 LBT Q Eng/SW Review PWR: Site electrical power.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
Page 1 MCQUAY DIGITAL SCROLL SYSTEM Installation.
LBT Q Engineering Review HBSC Hydrostatic Bearing System.
LBT Q Engineering Review PMCD. 21-DEC-2007LBT Q Engineering Review Highlights (Q4/2007) Draft of System Overview and O&M manual complete except.
September 30, 2008 Jim Van Dyke, Web:
LBT Q Engineering Review DAQ. 19-Apr-2007LBT Q Engineering Review Housekeeping System Requirements Interface directly to the Agilent 34970A.
Wired Transmission 24 Wired Transmission 24. Wired Transmission 24 This is about the method used to actually transmit or send data That means actual wires.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
1 LBT Q Eng/SW Review PLMG: Plumbing, Chiller Systems.
LBT Q Engineering Review Swing Arms (SWA). 10-Jul-2007LBT Q Engineering Review Highlights (Q2/2007) The right secondary arm is wired and the.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
School network wireless, and land based By Benjamin Houlton.
1 LBT Q Eng/SW Review PSPI: PEPSI installation preparation.
Computing room PC farm UPS.
HVAC Building & Floor Cooling System
What is energy? Energy is the ability to do work or cause a change.
B245 Modifications & Cabling Update
Question & Suggestions March 17th
Tagger Microscope Mounting, Shielding & Cooling
Progress Report 11/10/11.
Pump House wall before installation.
.., - I ':\ ' !' #
Minuteman Vocational Technical Regional High School Progress
The computer laboratory
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications

2 Highlights (Q1/2007) Install conduit for FO Install conduit for FO Install LIU at bridge location Install LIU at bridge location Install 36 fiber FO cable computer room to PEPSI bridge Install 36 fiber FO cable computer room to PEPSI bridge

3 Open Issues Technical Technical Painting floor and walls Painting floor and walls Schedule Schedule Not yet Not yet Financial Financial None None Resource Resource Identify paint and paint contractor Identify paint and paint contractor

4 Progress (Q1/2007) Fiber optic cable and conduit has been installed Fiber optic cable and conduit has been installed LIU is installed LIU is installed

5 Planning (Q2/2007) Terminate fibers Terminate fibers Define and install the connection point box Define and install the connection point box Install some services Install some services

6 Planning (before 2008) Install services Install services install E-net, install E-net, install E-stop install E-stop install telephone install telephone install cooling water, 47 deg install cooling water, 47 deg install clean, dry air install clean, dry air install power and conduit install power and conduit Move florescence lights up to 4 M Move florescence lights up to 4 M Insulate all pipe carrying liquids Insulate all pipe carrying liquids Move J box up to 4 M Move J box up to 4 M Epoxy paint entire floor Epoxy paint entire floor Paint walls with epoxy paint Paint walls with epoxy paint Install the support brackets on the telescope gallery Install the support brackets on the telescope gallery