1 Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London Heat Exchanger.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

April 05 Jason Tarrant CCLRC1 PRR of SCT off-detector cooling system l Cooling System »Design - Off-cylinder & On-cylinder »Installation – Off-cylinder.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
2.3.9 Student Book © 2004 Propane Education & Research CouncilPage Identifying Procedures for Purging Containers & Injecting Methanol Prior to.
ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
Hydraulics.
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
G.Barber Tracker Update, Berkeley 10 Feb Tracker Progress Contents:- Station Space Frame Patch Panel / Vacuum Seal Light Guide Map Position of Degrader/Support.
TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
Improvements for next parts PIMS production meeting February 2013 Rolf Wegner.
S Temple CLRC1 End-cap Mechanics FDR Cooling Structures Steve Temple, RAL 1 November 2001.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Respirator Safety This Training Covers Respirator Inspection User Fit Checks Respirator Cleaning Respirator Storage.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
Substrate-Paddle-Base Peter Cooke. Peter Cooke 28 Feb - 1 March VELO PRR2 Substrate- Paddle-Base Substrate Production Paddle – Base – Feet Component.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
Electronic Systems Support LHC Crates 2005 Paul Harwood PH Electronic Systems Support Group (PH-ESS) Meeting Sept 1, 2004.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
John LeRose March 12, A Program of three “projects” to assemble the Super BigBite Spectrometer for a series of experiments in Hall A There is a.
ATF2 quads status 22Nov05- Cherrill Spencer 1 Status Report on the Design and Fabrication of 29 quads for ATF2 By Cherrill Spencer, SLAC, for ILC-BDS weekly.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
WP4 Equipment Bids (Tim). Bids ATLAS – Case for the Purchase of Equipment for the Testing of Cooling Loops (£15k) – Case for the Purchase of Equipment.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
Student Book © 2004 Propane Education & Research CouncilPage Performing Gas Distribution System Leak Checks Requirements for vapor distribution.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
What tests are necessary to make sure your kegs are being cleaned, sanitized and filled correctly By Andrew J. Brewer
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
Hybrid panel heated plate study Currently the curing of the ASIC glue for the hybrid panels are done at room temperature. This is a study to determine.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
CM 28 – 6 th October 2010 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
PASI OsC meeting 12th July 2012
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
Stave - Electrical Break Richard French The University of Sheffield Material from the ATLAS SCT/IBL/PIXEL community.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
Workshop Sponsored by: Home Grown Food Rain Barrel for Under $40.
LAT Transport Container1 GLAST LAT Project8 September 2005 LAT Transport Container Design Review 8 September 2005 LAT Transport Container Design Review.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
P.Barclay CLRC1 SCT HEX PRR ( ) Design and qualification of fittings and filters l Background comments: »Space and assembly constraints prevent us.
CAD CAM. 2 and 3 Dimensional CAD: Using 2-dimensional CAD software, designers can create accurate, scaled drawings of parts and assemblies for designs.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
13 Januar 2011 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Cooling Cooling Meeting Karlsuhe.
Cleanrooms Keith Middleman. Particulates and Clean rooms What is a particulate? Small discrete mass of solid or liquid. Human hair is microns in.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Stator Plan & Schedule Chris Booth 2nd March 2009
ATLAS Internal ID Service Integration
What is Stave Carrier Frame Required to Do?
Ti/SS transitions A.Basti INFN-PISA*
Helium Balloon for the SHIP Decay Volume
CAD CAM.
Experimental Setup.
Cryomodule Assembly Plan
Tests of Endcap capillary & Heat exchangers at CERN
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

1 Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London Heat Exchanger Production at QMUL

2 Outline  Component Manufacture  Assembly  Cleaning  Testing & QA  Storage & Shipping  Schedules Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

3 Component Manufacture Dedicated Machines: Dedicated machines have or will be set up for various in-house operations : coil winding, turning and milling (end fittings etc) These will remain set up solely for the purpose and duration of production. Parts Mass Production: Filters, connectors and some pre-formed pipework will be supplied by RAL. In the interest of efficiency and releasing machinery asap all parts will be made in a single production run for both Barrel and Endcap HEX. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

4 Component Manufacture (contd) 90 complete sets to be made for the Barrel, initially 74 to be fully assembled. 60 complete sets to be made for the Endcap, initially 44 assembled. Remaining parts held as spares. Timescales: Majority of bought-in components are on order and should arrive within next few weeks. In-House activities: estimated timescale 4 weeks to complete parts production for Endcap and 4 weeks for Barrel. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

5 Component Manufacture (contd) Pre-Clean: In an effort to reduce final cleaning times any component which fits inside our ultrasonic bath (500mm x 250mm x 250mm) will be cleaned in this manner. Larger parts will require hand cleaning with a final alcohol rinse. By this stage most of the large particles will have been removed. Storage: Most components will be of manageable size. Placed in bags and stored in plastic bins. A simple pipe rack will be used to store longer pipe sections Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

6 Assembly Assembly: General assembly, soldering etc will be carried out in a dedicated area of the main workshop. Area to be cleaned before production starts. Prototype HEX Jigs: A great deal of time and effort has already gone into the making of various jigs, pipe benders and support blocks for the production of earlier prototypes. Some of these jigs are still useful and will be modified if necessary for future use, for example, creating the oval section of the Barrel HEX. However, these can only be finalised once all drawings have been received and signed off. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

7 Assembly (contd) Final HEX Assembly Jigs The Endcap HEX jig design is well under way. Most of the forming of pipes is carried out in situ on a flat surface aided by support blocks at key points. The system is adaptable and can be easily altered to accept variations required in the overall design due to the use of dowelled alignment blocks. The Barrel HEX jigging will be of a similar design, however, this will require a frame support structure rather than just a flat surface due to its physical size (~2.5m long). Datum points are to be supplied by RAL in the near future and will use alignment blocks specifically built for each variant (currently 11). An electrical pipe heater has been purchased for soldering and modified to accept different pipe diameters. Power is controlled by a Variac to ensure precise heating of the joints. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

8 Assembly (contd) Transport Jigs: Once assembled the HEX will be transferred onto a more simplified jig capable of holding 3-4 HEX at a time. They will remain on this frame throughout the cleaning, leak and pressure tests. The intention is to have several jigs in order to keep production on going. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

9 Cleaning Overview Internal cleaning of the heat exchangers, Barrel and End Cap, will be done with a special solvent named Swansolv. This solvent was chosen at RAL for its efficiency and its compatibility with the ATLAS cooling system specifications. The internal cleaning procedure required the construction of a dedicated cleaning rig and the setting of a dedicated cleaning area within the QMUL physics dept to comply with the specific requirement associated with the use of Swansolv (Toxic Vapour). This cleaning rig is fully functional as of the 30 th March and is described in detail in the following slide Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005Jerome Morin – Queen Mary, University London

10 Cleaning

11 Cleaning (contd) The external cleaning of the heat exchangers will be done with ethanol and did not require any specific investment. Procedures The cleaning procedures are presented in the following slide. One can see that apart from the cleaning rig, the cleaning set-up is composed of 3 trays capable of holding up to 4 HEX each. These trays are used to transport in a safe manner the HEX between the different working stations used for soldering, cleaning and pressure testing them. Safe transport of the trays betweens the various stations will be done via a modified trolley. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005Jerome Morin – Queen Mary, University London

12 Cleaning (contd) Welding of HEX Mounting on tray Tray full? (4) Move tray to cleaning area Connect HEX to cleaning rig Flush HEX with Swansolv 2 hours Remove Swansolv / flush with dry air or N2 Is it clean (criteria to be defined) 10 min Unconnect filter / check cleanliness (same room?) Reconnect filter Flush with dry air/N2 All night Bring empty tray Unconnect hex/move tray to pressure/leak testing - area Pressure and leak tests Test OK Investigate with a external leak test, label fault and store bad HEX

13 Cleaning (contd) It is expected that in a day, a maximum of 3 HEX will be assembled and soldered. The internal cleaning process takes also a day to be completed. The HEX are cleaned during the day and left to dry overnight. The HEX are then pressure and leak tested the following day. 3 trays are therefore used to ensure continuous operation. The trays are designed to contain any possible leakage and to facilitate the connection between the HEX and both the cleaning and the pressure testing rig. The trays are made of a structure constructed from 25mm aluminium square profile (‘speedframe’), and a thin sheet of aluminium supported by a 9mm plywood. The various jigging located on the trays and used to fix down the HEXs will accommodate the different ‘flavour’ of HEX. The setting of the dedicated room is presented in the following slide. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005Jerome Morin – Queen Mary, University London

14 Cleaning (contd) Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005Jerome Morin – Queen Mary, University London

15 Testing & QA Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London Pressure Test: The HEX will be pressure tested using O.F.N to 25bar. This allows for a 50% safety margin beyond the 16bar working pressure. The test will be carried out in a protective enclosure and should not take any longer than 10 mins per unit. Visual inspection to follow. Only highlights catastrophic failure. Helium Leak Test: A global leak test will be carried out by placing the HEX inside a helium filled enclosure (pos as used for pressure test) and applying a vacuum to the HEX ports. Leak rates less than l/s will be considered within spec. Leak detector to be supplied by RAL within the next few days

16 Testing & QA (schematic1)

17 Testing & QA (schematic2)

18 Testing & QA (contd) Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London Duration: At present there is no real feel as to timescales for this operation. Estimate 1 hour per unit, perhaps slightly less. Depends on achievable pumping speeds and helium dispersion between testing each HEX. Database: Still need to resolve labelling of individual HEX Some form of database / spreadsheet will be required to log QA. Not yet addressed.

19 Storage & Shipping Packaging: At this point the HEX will have all openings sealed with plugs or foil before removal from their transport frame. There is a possibility of sealing HEX within a plastic bag for added protection. HEX stored directly in transport crate. Transport Crate: Size and construction of the crates have yet to be agreed and will vary between the two systems. Size of crate will also be determined by quantities required on site at any one time. A suitable company needs to be found. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

20 Storage & Shipping (contd) Costs: Custom built crate : currently no details. Transport : at the level of shipping one off it has been expensive. Needs further investigation Transit & Delivery: Transit time via shipping agent Calberson is 3-5 days and depends on meeting their collection day schedule. Transit time does not include customs release period. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

21 Schedules Endcap HEX: Current effort suggests being able to produce 6 (possibly 9) completed HEX per week. This equates to 12 weeks in order to produce the required 72 HEX and does not include the 4-week machining period. Barrel HEX: Figures for the Barrel HEX are similar at 5 per week, however only 44 are required initially and therefore should take 9 weeks to complete. Once again this does not take into account the 4-week machining time, which may take the same length of time due to the number of variants. Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London

22 Schedules (contd) Production and QA of Barrel / Endcap Heat Exchangers ATLAS SCT PRR April 13 th & 14 th 2005John Morris – Queen Mary, University London Contingency: In addition a two-week contingency should be applied to both Barrel and Endcap schedules. Timescales: Schedules: Endcap HEX -16 weeks Barrel HEX – 13 weeks Contingency – 4 weeks Total Production Time – 7 months Still need to find some additional time for completing Barrel and Endcap Finalised jigging.