NATIONAL ENERGY CONSERVATION AWARD 2007
PRESENTED BY : A.GANESAN EXECUTIVE ENGINEER (E) BSNL ELECTRICAL DIVISION MADURAI
THE BUREAU OF ENERGY EFFICIENCY HAS ANNOUNCED NATIONAL ENERGY CONSERVATION AWARD 2007
CTO BDLG. MADURAI CTO BUILDING MADURAI IS ONE OF THE TWO BUILDINGS SELECTED BY THE PCE(E) FOR NOMINATION TO THE AWARD
BUILDING PROFILE CTO COMPLEX CTO BUILDING CTMX BUILDING LEVEL IV BUILDING CTO COMPLEX IS COMPRISING OF THREE BLOCKS
BUILDING PROFILE A- CTO BUILDING G- FLOORPROPOSED SIGNLE WINDOW CSC I FLOORSFMSS EQPT+ ADMN. OFFICE+ IQ II FLOOROFFICE + IQ III FLOORO/oGM(DEV)+CONFERENCE HALL
BUILDING PROFILE B - CTMX BUILDING G - FLOORCELL MSC-II + EWSD MDF I - FLOOR STR EQUIPMENT ( IN PROG ) + INTERNET EXCHANGE ( PROPOSED ) II - FLOOREWSD EXCHANGE - 10K III - FLOORADMN. OFFICE
BUILDING PROFILE C - LEVEL-IV BLDG. G - FLOORSTR POWER ROOM + OUTDOOR OFFICES I - FLOORCELLONE CSC + STR MUX EQUIPMENT II - FLOORSTR OFFICE + GM (DEV) OFFICE III - FLOORCONFERECCE HALL + STR OFFICE
ENERGY CONSUMPTION CHART
CONSUMPTION PATTERN
REDUCTION IN SPECIFIC ENERGY CONSUMPTION AS A RESULT OF VARIOUS ENERGY CONSERVATION MEASURES ADOPTED THE ENERGY EXPENDITURE HAS COME DOWN DESPITE INCREASE IN CONNECTED LOAD
CTO BUILDING - MADURAI ON THE BASIS OF THE ACHIEVEMENTS OF VARIOUS ENERGY CONSERVATION MEASURES ADOPTED, THIS BUILDING HAS BEEN SELECTED FOR THE CONTEST
MAJOR ENERGY SAVING MEASURES ADOPTED REPLACEMENT OF 54 NOS. OLD W/T A/C UNITS BY 34 NOS. NEW SPLIT A/C UNITS REPLACEMENT OF CONVENTIONAL TYPE POWER PLANT WITH SMPS POWER PLANT REPLACEMENT OF ( 6 X 7 TR)OLD PACKAGE A/C PLANT WITH ( 4 X 7 TR ) NEW PACKAGE A/C PLANT REPLACEMENT OF DEFECTIVE CAPACITORS BY NEW CAPACITORS AND GOOD PF MAINTAINED
REPLACEMENT OF AC UNITS OLD UNIT REPLACED BY NEW S/T AC UNIT
REPLACEMENT OF AC UNITS 54 NOS. OUTLIVED A/C UNITS UNITS HAVE BEEN REPLACED BY 34 NOS NEW S/T A/C UNITS RESULTING IN A SAVING OF RS.8,99,360/- PER YEAR.
REPLACEMENT OF AC UNITS Energy consumption details for W/T,S/T AC Units DescriptionsOld After replacement NewExisting No. of units Power consumption (in KW)2.42 No of working hrs/day888 No. of days working365 Total Energy consumption in KWh Total Energy consumption before replacement (for107 AC units) in KWh Total Energy consumption after replacement for(34 new units +53 old units) 87 Ac units in KWh Savings in energy Savings in Rs.5/
REPLACEMENT OF CONVENTIONAL POWER PLANT WITH SMPS POWER PLANT
THE EXISTING CONVENTIONAL TYPE POWER PLANT HAS BEEN REPLACED WITH SMPS POWER PLANT RESULTING IN A SAVING OF RS.62,550/- PER YEAR
REPLACEMENT OF CONVENTIONAL POWER PLANT WITH SMPS POWER PLANT Power saving by replacing conventional power plant by SMPS power plant Description Conventional Power plantSMPS power plant Efficiency of power plant82.64%95% Output power ( KW)7.5 Input power (KW) Total energy consumption/year (Kwh) Total cost of the energy (Rs.) Savings in Energy /year (Kwh) Savings in cost/year (Rs.) 62550
REPLACEMENT OF DEFECTIVE CAPACITORS
THE DEFECTIVE CAPACITORS IN THE POWER FACTOR IMPROVEMENT PANEL HAVE BEEN REPLACED RESULTING IN A SAVING OF RS. 30,799/- PER YEAR. POWER FACTOR ALWAYS > 0.98
REPLACEMENT OF PACKAGE AC UNITS 4+2 X 7 TR REPLACED WITH 3+1 X 7 TR
REPLACEMENT OF PACKAGE AC UNITS THE EXISTING 4+2 X 7 TR PACKAGE AC PLANT HAS BEEN REPLACED WITH 3+1 X 7 TR PACKAGE AC PLANT RESULTING IN A SAVING OF RS /- OLDNEW EXPENDITURE
REPLACEMENT OF PACKAGE AC UNITS Energy consumption details for PAC units DescriptionOldNew No. of units43 Power consumption (in KW) No of working hrs/day18 No. of days working365 Total Energy consumption in KWh Savings in energy Cost of Rs.5/-unit Savings in cost other savings Cost of not providing 2 nos 7TR PAC Rs.3,50,000/unit (A) Saving in energy for 1 hrs/day working for 365 days Cost of Rs.5/-unit (B) Total savings (A+B)
PROPOSED ENERGY SAVING MEASURES IN CHANGE OF EB TARIFF OF 21 NOS S/Q 2. REPLACEMENT OF FL. FITTINGS WITH ENERGY EFFICIENT FITTINGS 3.PROVISION OF WATER LEVEL CONTROLLER FOR PUMPS 4. CREATING AWARENESS AMONG STAFF BY CONDUCTING PROGRAMMES & THROUGH SLOGANS
CHANGE OF EB TARIFF OF S/Q AT PRESENT 21 NOS S/Q ARE BEING FED FROM SUB STATION & ENERGY COST IS RS.5/- PER UNIT ALL ELECTRICAL WORKS FOR GETTING SEPARATE SERVICE CONNECTION FOR S/Q ARE COMPLETED WHEN SERVICE CONNECTION WITH RESIDENTIAL TARIFF IS EFFECTED THERE WILL BE A BI-MONTHLY SAVING OF RS 14,700/- [ 21 S/Q X (RS 5 - RS 2.8) X 250 UNITS ]
WATER LEVEL CONTROLLER FOR PUMPS NEARLY 225 EMPLOYEES ARE WORKING & 13 NOS PUMPS ARE AVAILABLE ALL THE PUMPS ARE BEING OPERATED MANUALLY THERE IS A GOOD SAVING POTENTIAL BY PROVIDING WATER LEVEL CONTROLLER FOR THE PUMPS
INSTALLATION OF ENERGY EFFICIENT LIGHT FITTINGS 598 NOS TWIN FITTINGS & 316 NOS SINGLE FLUORESCENT TUBE LIGHT FITTINGS ARE AVAILABLE CONNECTED LOAD OF THESE FITTINGS WORKS OUT TO 60 KW IT HAS BEEN PROPOSED TO REPLACE THE ABOVE WITH ENERGY EFFICIENT FITTINGS IN A PHASED MANNER ON COMPLETION OF THE TASK THERE WILL BE A REDUCTION OF 18 KW OF LOAD
AWARENESS PROGRAMME ENERGY CONSERVATION AWARENESS WILL BE CREATED THROUGH PROGRAMMES AND SLOGAN STICKERS
APPLICATION SENT IN VIEW OF THE ABOVE MEASURES & ACHIEVEMENTS & AS PER THE INSTRUCTIONS OF THE PCE(E) & SE(E), APPLICATION FOR THE ENERGY CONSERVATION AWARD HAS BEEN SENT TO BUREAU OF ENERGY EFFICIENCY
WE HOPE THAT CTO COMPLEX MADURAI WILL RECEIVE THE ENERGY CONSERVATION AWARD FROM BUREAU OF ENERGY EFFICIENCY