Review of the Cryogenic By-pass for the LHC DS collimators Ph. Lebrun on behalf of the Review Committee CERN, Kjell Johnsen auditorium 26 May 2011.

Slides:



Advertisements
Similar presentations
19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
Advertisements

Cold Powering of the HL-LHC magnet system WP6 Motivation Work Package description Tasks Partners & resources Amalia Ballarino HL-LHC Design Study – 3 rd.
Improved anchoring of SSS with vacuum barrier to avoid displacement Ofelia Capatina (speaker), Katy Foraz (coordinates all the activities), Antonio Foreste,
ColUSM #51 30 th January, 2015 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, Q. Deliege, V. Baglin, F. Savary.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
12th HL-LHC Parameter and Layout Committee meeting.
January 4, 2007 RHIC II Project Internal Cost Review Existing RHIC power supply Modifications Don Bruno & George Ganetis January 4, 2007 Power Supply Modifications.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
HL-LHC Standards and Best Practices Workshop (11-13 June 2014)
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
The integration of 420 m detectors into the LHC
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Integration options for collimators in the DS zones V.Parma, CERN, TE-MSC With contributions/input from: V.Baglin, A. Bertarelli, M.Karppinen, H.Prin,
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
TE-CRG Activities D. Delikaris, TE-CRG.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE) Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE)
A. Perin TE-CRG, 06 April LMC 08 April 2009 Consolidations related to pressure protection on DFBs and DSLs A. Perin, TE-CRG.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Movable beam pipe and NNC Study & prototype development Manchester 14/12/20091D. FP meeting.
Crab Cavity Technical Coordination meeting:
News and Introduction from CERN June 15th, 2005
Project overview, boundary conditions, configuration, cost & schedule
HL-LHC IT STRING and Series test of SC link
SLHC –PP WP6 LHC IR Upgrade - Phase I.
Roadmap for triplet cryostats
Equipment simplified model SMR UR safety
Cryostat procurement, status and plan, QA/QC
The LHC - Status Is COLD Is almost fully commissioned
LS1 Committee January 24th, 2014
Comparison between 1) HL-LHC BASELINE: Q5 at point 6 at 1
Consequences of warming-up a sector above 80 K
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Accelerator and Experiment Interface Session: LS2, LS3
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
From Design to Installation courtesy R. Folch S. Atieh TS / MME
J.M. Jimenez On behalf of TE-VSC group
The 11T cryo-assembly: summary of design and integration aspects
TEST PLANS for HL LHC IT STRING
DS Collimators TE-MSC-CI
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Review of the Cryogenic By-pass for the LHC DS collimators Ph. Lebrun on behalf of the Review Committee CERN, Kjell Johnsen auditorium 26 May 2011

Mandate The proposed DS collimators require an important modification of the continuous cryostat: addition of a cryogenic by-pass (QTC) as well as modifications to the position of the DFBA and SSS. The aim of the review is to assess the risks to the LHC integrity associated to modifying the existing continuous cryostat. The outcome of the review will be used as input to the DS collimator review of June Specifically –Review the proposed technical design of the QTC and its integration –Assess the impact and potential risks with the concerned technical systems –Review the proposed implementation and risks: work organization, strategy for manufacturing, testing and installation –Review other proposed modifications to the continuous cryostat –Review estimated cost, resources and planning

Miscellanea Review appointed by EN and TE Department Heads Reporting line –EN and TE Department Heads –LMC and Director of A&T Date of the review: Thursday 26 May 2011 (full day) Place of the review: Kjell Johnsen auditorium, 30/7-018 Review committee: –J. Bremer/TE –A. Dudarev/PH –C. Hauviller/EN –Ph. Lebrun/DG (chair) –D. Perini/PH

QRL DS collimators: Left side of point 3 Q11 Q10 Q9Q8 Q7 DFBA DQS TCLABTVM QRL 4’500 mm 46 mm Q11 Q10 Q9Q8 Q7 DFBA DQS TCLABTVM R33RZ33R34 11L310L39L38L37L3 IP3 Conn.cryostat Short Conn.cryostat New Collimator assembly (LTC) New Collimator assembly (LTC) V. Parma

Q11Q10Q9Q8Q7 DFBA DQS TCLA QRL 4’500 mm 46 mm New Collimator assembly (LTC) New Collimator assembly (LTC) Q11Q10Q9Q8Q7 DQS QRL DFBATCLA DSLC 11L310L39L38L37L3 R37R38 IP3 DS collimators: Right side of point 3 Conn.cryostat Short Conn.cryostat V. Parma

Main hardware implications (3L+3R) Disconnect and remove: –16 dipoles, 8 SSS, 2 Connection Cryostats, 2 DFBA Displace by 4.5 m: –TCLA, DQS, BTVM (3L only, displacement to de defined) Important cable re-layout work: –~600 cables to be shortened, ~800 cables to be extended (warm and cooled cables) –Re-routing (through new cable duct UP33/R34); connections Civil engineering: –Remove, displace and fix jacks to ground –Grind passage wall (3-5 cm) on 2x100m length –Drilling new cable duct UP33/R34 Modification of jumpers of Q7, Q9 and DFBAs (on surface or in the tunnel) Shortening of DSLC (cryostat+superc.cables) in 3R Produce new equipment: –4 (+1) DS collimator assemblies (LTC) –2 (+1) Short Connection Cryostats (SCC) –2 QRL extensions Re-install and interconnect DFBA, magnets, SCC, LTC V. Parma

QTC layout Standard interconnects Collimator with independent support/alignment “Standard” baked vacuum sector BLM’s Manual quick connect flanges, electrical and water plugs, but not remote handling Collimator replacement without re-alignment Sector valves 4.0 m m interc. = 4.5 m installation length D. Duarte Ramos

Cost Estimate (P+M) To date, M expenditure < 3 MCHF (estimate) Includes design studies (also commited) Components/materials ordered (end caps, supports, raw material…) V. Parma

General schedule Long Shutdown Cryo by-pass - CERN production Jan-13 Opening of the inter-connections 8 months QTC1 QTC2-3 QTC4-5 Sept-13 Jul-13 Opening of the inter-connections 8 months Avr-14 /!\ Detailed planning and length to be adjusted according to co-activities and resources Earliest date Latest date SCC1 SCC2 SCC3 Short Connection-cryostat - CERN production J. Coupard

General findings [1/3] The review committee –wishes to acknowledge the good preparation of the review, the quality of the presentations by the speakers and the open spirit of discussions –however remarks that presentations were made available very late on the INDICO site, thus precluding thorough preparation by the reviewers –is impressed by the amount of design work performed and engineering resources engaged for a project which is not yet approved The cryogenic by-pass for the DS collimators –is an important and complex project, involving many systems and interfaces –information presented however does not allow to assess all possible risks; this would require the results of some ongoing and yet-to-be-done studies In response to the specific questions of the mandate, the review committee has found that –the technical design of the project is essentially done –its integration is partially studied but not yet completed –its impact and potential risks within the concerned technical systems are generally correctly addressed –work organization, manufacturing and testing strategies are broadly defined –logistics and installation have to be considered in relation with many other co- activities competing for resources during the shutdown

General findings [2/3] The review committee wishes to draw attention on the following elements of technical, organizational and schedule risks –the project does not only consist in building and installing new equipment, but also involves profound modifications, refurbishing and displacement of critical items, for which no spares exist (DFBA, DSLC) –integration and installation in a very crowded tunnel area will require a number of ad hoc solutions, e.g. numerous in situ welds, some of which will have to be performed with non-standard procedures: that implies specific risk, to be mitigated by thorough preparation, planning and execution follow-up (refrain from improvisation!) –the general planning presented shows parallelism within the project between manufacturing/testing of components and tunnel activities: this may indicate absence of contingency and conflict of resources (e.g. for specialized staff such as qualified welders) –as stated in the presentations, the execution schedule will eventually be determined by the level of co-activity and resources available; in view of the pressure of other shutdown activities and the complexity of the project, “latest date” installation planning should therefore not be considered as a viable option: the project should make full use of the installation planning “window”

General findings [3/3] Overall, the review committee estimates that –the cryogenic bypass (QTC), although complicated in design and heavily constrained in space occupancy, appears technically feasible; pending proper manufacturing and installation, it should permit operation of the collimator while maintaining all functionalities of the LHC technical systems concerned – cryogenics, powering, vacuum - in the DS region –the new connection cryostats and transfer line extensions essentially make use of technical solutions already implemented elsewhere in the machine, and thus should not bring particular issues –in situ modifications to the electrical feed boxes (DFBA) and superconducting links (DSLC) are more delicate, but also appear feasible with proper preparation and care –a major element of risk for the project stems not so much from the exotica of new or modified components, but rather from the removal and reinstallation of a significant number of standard LHC components and of their ancillaries in a very crowded and intricate area of the machine

Specific remarks and questions [1/2] Overview, configuration, cost & schedule –the effort made to re-use standard solutions and components for the QTC is appreciated, but should not be pushed to the point where it unduly over-constrains the design –in view of the tight general schedule, is a full prototype of the QTC really necessary? –a proper risk analysis of the proposed modifications to civil engineering in the area around Point 3 should be performed Mechanical design of the QTC –In view of their transverse space occupancy close to the beams, are RF-shielded sector valves absolutely necessary? –Assembly of He vessel around bus bars is a change from usual practice of separating sheet-metal work from electrical buswork assembly: risk of damage during welding requires mitigation measures and enforcement of procedures –Assembly of vacuum vessel around cold mass: risks of deformation (addressed), risk of damage, issue of cleanliness during welding carbon steel: mitigation measures and enforcement of procedures required New SCC and modifications to SSS –options taken already applied successfully at other locations in the machine –new SCC to be built provides opportunity to improve weak points of existing ones

DFBA & DSLC modifications and cryogenic line extensions –jumper extensions: similar to already done (P2) –DFBA critical element (no spare): concern about interventions in very crowded area, also affecting ancillaries and cabling –modification to DSLC (cut, shorten, displace and reconnect), to be performed in awkward location: concern, needs thorough study and preparation to mitigate risk Cryogenic design –the need for a continuous He IIp annular duct around the He IIs pipe is not clearly established: potential for simplification? –a criterion for minimum He II cross section per bus bar channel to ensure their safe cooling in all conditions, including accidental (e.g. degraded insulation vacuum) should be formulated and its fulfillment checked Electrical circuits –cross-talk due to proximity of bus bars could create a protection issue (spurious triggering of QPS): mitigation solution presented, likely to work –3-D analysis of field errors in region of QTC lyre must be performed –quench hot-spot calculations to be done for specific configuration of bus bars in QTC, with assessment of consequences of potential temperature difference between M1 and M3 Specific remarks and questions [2/2]