Project Update & The Success of the Integrated Project Management Office Metro Goldline East Extension Los Angeles January 19, 2007 ASCE Construction Institute.

Slides:



Advertisements
Similar presentations
2012 State Board of Directors Orientation “Its good business to do business with an AGC member”
Advertisements

Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.
California High-Speed Train Project Los Angeles Union Station Alternatives Analysis January 7, 2010 Board Presentation.
CALIFORNIA HIGH-SPEED RAIL: GETTING ON TRACK Silicon Valley Leadership Group Transportation Committee January 9, 2013.
Phase 1 Project Status: Design Continued development of alternative station design concepts for stations in the vicinity of USC and Expo Park Received.
The Alameda Corridor: Lessons Learned Presented to: UCI Conference on the New Generation of Transportation Financing in California Costa Mesa, CA Gill.
Los Angeles County Metropolitan Transportation Authority Douglas R. Failing, P.E. Executive Director, Highway Program Public Private Partnerships CTF Transportation.
Dulles Corridor Metrorail Project 23-mile new Metrorail line branching off the Orange Line after East Falls Church 11 new stations 5 in Phase 1: East Falls.
T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority.
Whitestown: 20 Year Strategic Plan for Municipal Services “The best possible service at the lowest possible cost.”
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
New York State Department of Transportation
New York State Department of Transportation
Guiding principles for the Federal acquisition system
Process Engineer’s Role in Project Management Dr Abdullah Malik.
CALTRANS PARTNERSHIPS AND UTILITY COORDINATION By: Paul Pham April 22, 2009.
Tucson Modern Streetcar Project Overview July 15, 2011.
CALIFORNIA HIGH-SPEED RAIL: GETTING ON TRACK Silicon Valley Leadership Group Transportation Committee January 9, 2013.
North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013.
Anaheim Regional Transportation Intermodal Center Project Update.
FasTracks Moving Forward: Regional Transportation Plan (RTP) Amendment Staff Recommendation Phillip A. Washington and Team August 7, 2012.
The Importance of the Qualifications Based Selection (QBS) Process
1 November Accomplishments: Design and Construction Began sanitary sewer, gas, waterline and electrical relocations between 18th and 23rd Streets Continued.
New York State Department of Transportation
 Do you have an Interest in Math and Science?  Do you have good problem solving skills?  Do you approach problems in an analytical manner?  Can.
Ottawa’s Light Rail Transit Project OLRT Tunnel Geotechnical Update Technical Briefing December 21, 2010 John Jensen Director Rail Implementation Office.
Produced by: Integrated Asset Planning for Nuclear Power Plants Matt Kohal Southern California Edison.
Mid-City Exposition Light Rail Transit Project Closed Session Presentation March 2, 2006 Exposition Metro Line Construction Authority.
Fraud Awareness Conference FEDERAL TRANSIT ADMINISTRATION Corey Walker Office of Program Management Sound Transit Steel Casing Product Substitution Review.
North Metro Rail Line Request for Proposals (RFP) Commerce City Council August 19, 2013.
Project Status: Design Initiated development of alternative station design concepts for stations in the vicinity of USC and Expo Park Received 85% design.
1 Governance Council Meeting Fiscal Year 2004 LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY GATEWAY CITIES SERVICE SECTOR December 18, 2003.
Public-Private Partnership Program 2015 Update 2015 American Council of Engineering Companies ACEC – Los Angeles Chapter Luncheon, July 8, 2015.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
Department of Transportation Consideration of Potential City of Pasadena Position Related to SR710 Extension Alternatives Being Considered By Metro City.
Metro Gold Line Eastside Extension Four Quadrant Gate Feasibility Study Summary.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
New York State Department of Transportation Accelerated Bridge Program Phase 1B Design-Build Projects Request for Proposals Informational Meeting April.
Metro Gold Line Eastside Extension. Eastside Extension Community Little Tokyo Mariachi Plaza Mariachi Plaza Kiosk Mural in East LA.
December Accomplishments: Design and Construction Continued trenching for and laying of storm drain pipe in Flower Street from I -110 to 23rd Street Started.
Elk Run Interchange Design-Build Project S.P (TH 52) Elk Run Interchange Design-Build Project S.P (TH 52) PROJECT INFORMATIONAL MEETING.
1 August Accomplishments Conducted the 4 th Urban Design Committee meeting, which consisted of a tour of the Metro Orange Line. Conducted one-on-one briefings.
Construction Quality Management Metro Goldline Eastside Extension Los Angeles January 19, 2007 ASCE Construction Institute Conference.
Los Angeles County Metropolitan Transportation Authority Overcoming Multi-Jurisdictional Challenges Lessons Learned Implementing Bus Signal Priority.
Tom Norton, Executive Director Colorado Department of Transportation American Association of State Highway and Transportation Officials September 9, 2003.
May’s Accomplishments Mobilized Authority and Design Build Contractor staff to Authority offices at 707 Wilshire Three Open House meetings were held in.
METROPOLITAN TRANSPORTATION COMMISSION Key Steps to Delivering Project 1.Lead agency submits final project scope, budget and schedule to MTC 2.MTC.
July Accomplishments: Authority and Design Build Contractor staff conducted the 3rd Urban Design committee meeting. Committee members viewed proposed station.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
February’s Accomplishments Met extensively with FTA staff and received the Record of Decision from FTA Finalized Negotiations with the top ranked Design.
Safe & Sound Bridge Improvement Program. Purpose of Meeting Introduction of Team Today’s discussion  History of Safe & Sound  DBFM to MDBB/DB split.
Planning & Community Development Department Zoning Code Amendment Public Hearing Proposed elimination of the 50% review step from the design review process.
Mercer Corridor Stakeholder Committee November 4, 2015 Sound Transit.
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
LACCD Building the Future THOMAS HALL Director Facilities Planning and Development.
CAHSR Board Meeting August 6, 2009 Section Update Los Angeles to San Diego (via the Inland Empire) Slide 1 of 10.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
The Design/Build Contract. What Is A Design/Build Contract? Contract that combines design & construction into one agreement The design/build team provides.
Verizon Florida, LLC Hurricane Season Preparation PSC Workshop – May 1, 2008.
Office of Major Project Development (OMPD) Overview November 2015.
North Metro Competitive Procurement RTD Board FasTracks Monitoring Committee October 8, 2013.
Upgrade, Renewal, Construction of Second Track and Construction of New Double-track Line on Sections of Railway Line Dugo Selo-Novska, Phase 2 & 3 Croatia.
Expo Line Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update October 2, 2008.
Subtitle Statement of Capabilities.
Proposal Writing Tips Ivan Page L.A.C.M.T.A.
Proposal Writing Tips Ivan Page L.A.C.M.T.A.
Central Ohio Intelligent Transportation System (ITS) Committee
Los Angeles County Metropolitan Transportation Authority
AN INVESTMENT IN CALIFORNIA’S FUTURE
Presentation transcript:

Project Update & The Success of the Integrated Project Management Office Metro Goldline East Extension Los Angeles January 19, 2007 ASCE Construction Institute Conference

The MGLEE Project The MGLEE is a six-mile, dual track light rail transit system extending the Pasadena Gold Line from Union Station to East Los Angeles. This $898 million project consists of elevated guide way, at-grade segments, 1.7 miles of twin tunnels, two portals, six at-grade stations and two underground stations. The traditional design-bid-build method of procurement was used for the tunnels and stations/portals excavation, while the design- build method of procurement was used for the at-grade segments, underground stations construction, track work and systems. Integral projects which are done by others are the 101 Freeway Structure (by Caltrans), the First Street Bridge Reconstruction (by City), the property acquisition and construction of New HS No. 1 (by LAUSD) the relocation and reconstruction of Ramona OHS (by LAUSD).

MGLEE ALIGNMENT

MGLEE Time Line The project was initiated in 2001 (environmental and preliminary engineering phase), final design and contract packaging for design-bid-build and design-build was completed in 2003, construction contracts awarded in 2004 and as of this writing, construction is more than 50% complete. The Revenue Operating Date (ROD) is scheduled for December of 2009.

MGLEE Entities  Los Angles County Metropolitan Authority (Metro)  Stakeholders (LADOT, Los Angeles County and City Public Works Agencies, Gas Company, SCE, SBC….  Consultants (Eastside Light Rail Partners: Parsons Brinckerhoff; Jenkins, Gales, Martinez; Barrio Planners)  Regulatory Agencies (CPUC, Caltrans, FTA, EPA)  Contractor: Eastside Light Rail Transit Contractors: Washington Group International; Obayashi Corp.; Shimmick Construction Company  Tunnel Sub-Contractor: Traylor Brothers  Utilities Sub-Contractor: Steiny Company  Design-Build Engineer: DMJM Harris/AECOM

Function/Goals of IPMO  Responsible for the design, construction, and start up of the Metro Gold Line Eastside Extension.  Select and Assign key personnel to the MGLEE Project in lieu of the standard matrix organization basis.  Demonstrate that the IPMO ensures the project is delivered on time and within budget.  Implements the goal to minimize the physical distance between the entities involved in the project by co-location.  Although a cooperative atmosphere is encouraged, it is important that staff of contract members is not subjected to pressure to forgo critical procedural requirements.  Provide QA staff to ensure policies and procedures are followed

Development of the IPMO Based on Lessons Learned from previous projects, Metro Project Management explored and adopted a different management approach on the MGLEE, namely the “Integrated Project Management Office (IPMO).

IPMO Structure  Consists of the following:  Engineering  Construction Management  Safety, QA  Planning  Cost and Schedule  Configuration Management  Public Affairs  Environmental  Third Party (Stakeholders) Coordination

MGLEE IPMO Site Plan Contractor Parking and Lay down Area Contractor Field Engineering Underground Structures Metro Administration Metro Engineering Contractor D/B Engineering QC Contractor Parking and Lay down Area To Downtown To County Area To City Area To101 FWY Bridge & !st St. Bridge

Selection of Key Personnel  Expertise in their respective disciplines  Committed to the Project until completion  Must have the necessary Personality and Flexibility for comingling with others  Must be able to “think out of the box” and be proactive in their daily duties

Advantages of IPMO  Reduced Management costs through elimination of redundant positions  Eliminates re-work of technical submittals and ensure the development of a consistent quality design submittal  Improves communication and coordination  Fosters team spirit and teamwork  Promotes a more conducive atmosphere between the entities  Allows for the elimination of perceived barriers between the entities  Accelerates resolution of issues  Results in more efficient project execution  Ensures the free flow of information between entities

Factors working against an effective IPMO to be overcome  Inability of large design groups to relocate key elements of their staff, such as the D-B design team remained in Downtown L.A., close to its major designer, DMJM Harris, although this office was an integrated office, including Budget, Scheduling, Records Control, Engineering Design ( Civil, Structural, Trackwork, Utilities, Architectural, Electrical, Mechanical ). ( Continued )

Factors, continued  Inability of small, highly specialized design groups to relocate any staff, such as Traffic, Systems (Mechanical, Electrical, Communication, Rail Operations, and Fire Safety ), primarily for the need to keep their designers and computer drafting operations in one cost-effective location. Most of these groups are outside L.A., i.e. Orange County, San Diego, Northern CA, Arizona, NY, and elsewhere.