REQD FUTURE POWER SYSTEM CHANGES  Following additional work is required to be performed to restore full capability of the machine: 1. Provide power feed.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

XP 1157 Increasing the CHI start-up current magnitude in NSTX B.A. Nelson et al. 1.
E951 POWER SUPPLY 5/13/02 IOANNIS MARNERIS Brookhaven National Labs.
AIMS TF Upgrade Update 6/18/14. Breaker & Contactor Control & Status 6 Pulse Dual Converter with Lockout Controls (and Shoot-through Protection) Auto-Crowbar.
Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)
Interrupts (contd..) Multiple I/O devices may be connected to the processor and the memory via a bus. Some or all of these devices may be capable of generating.
E951 POWER SUPPLY SAFETY REVIEW 9/06/02 IOANNIS MARNERIS Brookhaven National Labs.
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Shipboard Electrical Distribution …“Shifting the Electric Plant to a Normal Full Power Lineup.”
Chapter 8 Output Modules.
Control & Monitoring of DC-DC Buck Converters Satish Dhawan Yale University Power Distribution Working Group Meeting- Tuesday 24 February 2009 ATLAS Upgrade.
Electric Circuits  To calculate the size of a current from the charge flow and time taken Thursday, August 06, 2015.
Electrical Engineering. A circuit is a combination of different components that allow electricity to flow through them. Each component serves its own.
Noadswood Science, 2012 Electrical Safety. Electricity Safety To be able identify safety features with electrical components Tuesday, August 11, 2015.
Copyright © 2008 Rockwell Automation, Inc. All rights reserved. Direct-to-Drive Technology Product Feature Overview.
TF Joint Voltage Drop Instrumentation Robert Marsala (609) Hans Schneider (609) Engineering Operations August 7, 2003 TF_JOINT_Final_Design_Review.ppt.
Programmable logic control Data Processing Computer System Key Board Light Pen Mouse PLC a Process Control Computer System Motion Sensor Sound Sensor.
NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) NCSX PWR System PROTECTION – REVIEW February 22.
1 RWM P OWER FEED TO EACH COIL S. Ramakrishnan. 01/29/20102 RWM COILS Existing Status The Six RWM coils are grouped in pairs Each Pair is fed from one.
VGD-33 single unit upgrade to parallel system All single units must work properly Installation of the external cables and power cords: all should be connected.
Inner PF Coil Design Updated C Neumeyer 2/2/10. Changes Since Prior Version Added electrical insulation – Account for 3-wire system ground fault – Account.
NSTX_U Design Point Study Active H2O Cooling Pulse Length 60 sec C Neumeyer 5/19/6.
TF FLAG JOINT HIGH CURRENT TEST FIXTURE INSTALLATION TO BE IN THE NSTX TRANSITION AREA Features Assembled Components: Flag and Mating Section of TF Center.
December 15-16, 2009 NSTX Upgrade Project - Office of Science ReviewNSTXU Scope Overview 1 February, NSTX Supported by College W&M Colorado Sch.
NCSX NCSX CDR May S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX CDR May
All rights reserved MV SWITCHGEAR.
NSTX Center Stack Upgrade Workshop Requirements & Design Point C Neumeyer Jan 22, 2009.
Electricity. What is electricity? Electric current – flow of electrons through a _______ Current (I) is measured by how many __________pass a given point.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
Failure of Original TF Inner Leg Assembly C Neumeyer 4/10/3.
LARP CM15 Magnet Testing Working Group SLAC, November 2 nd 2010.
PF1A upgrade physics review Presented by D. A. Gates With input from J.E. Menard and C.E. Kessel 10/27/04.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
NSTX NSTX Center Stack Upgrade Ensure fatigue resistant Welds: minimum # of locations shown, could be more. Various Weld Reinforcements & Hardware Replacement.
Queensland University of Technology CRICOS No J Protection of distributed generation connected networks with coordination of overcurrent relays.
SC Project Review of NCSX, April 8-10, 2008 S. Ramakrishnan - 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PWR System April
Penn ESE370 Fall DeHon 1 ESE370: Circuit-Level Modeling, Design, and Optimization for Digital Systems Day 36: December 6, 2010 Transmission Lines.
10.3 Electric Potential. Electric Potential Electric potential refers to the amount of energy that electrons possess in a circuit.
Design Point Studies for next step device National High-heat-flux Advanced Torus Experiment NHTX C Neumeyer 6/8/6.
NCSX NCSX Trim Coil Peer Review 11/6/07 1 Tom Brown Art Brooks Raki Ramakrishnan Mike Kalish NCSX Trim Coil Peer Review.
A Training Presentation On 220 KV GSS CHOMU,JAIPUR
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
NSTX-Upgrade Magnetics And Related Diagnostics SPG NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu.
issues 40 min. rep. rate Fabrication of flex sections –Water jet cut copper –Copper flat cable –Others – electroform brazed straps –Shape –OOP support.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
Design Point Studies for Next Step Device National High-power Advanced Torus Experiment NHTX C Neumeyer 7/25/06.
REQUIREMENTS & ASSUMPTIONS C Neumeyer 4/10/3. FIELD AND CURRENT Base GRD requirement: 3kG at R 0 =0.854m with 4.5 sec flat top, once every 300s
NSTX Supported by NSTX Centerstack Upgrade Project Meeting P. Titus March F.
Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
Switches and Over Current Protective Devices Class Instructor ALPHER E. DE VERA, uap.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
SOLID STATE RELAYS are used to produce reliable signal and to avoid expensive relay replacement.
Electric Circuits Chapter 14, Section 4. Circuits consist of an energy source, a load, wires, and in some cases, a switch.
TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) Engineering Operations April.
Dry cell 1-carbon cell. carbon cell 1-The electrolyte is a moist paste inside the cell. 2-The outside case of the battery is usually made of zinc case.
S A Griffiths CM42 June 2015 Electrical & Control.
TRANSFORMERS  A power station produces an AC pd of ~25 kV  This AC pd is stepped up to ~132 kV so that it can transport through cables without losing.
Considerations from machine protection and the ELQA teams
Introducing Current Electricity
MQXFS1e – PH-to-Coil hipot tests
Hardware Commissioning
Warm-up Is it possible to create a circuit with wires, but no battery or other electrical power supply?
Presentation transcript:

REQD FUTURE POWER SYSTEM CHANGES  Following additional work is required to be performed to restore full capability of the machine: 1. Provide power feed to a) PF1bU, b) PF1cU, c) PF1cL coils.  This involves designing the power loop and providing Power Supplies, CLRs, Disconnect & Ground Switches, DCCTs, Protective relaying etc. 2. Upgrade PF5 feed such that PF5 coil can be injected up to 34kA  This would require an additional branch to the existing power supply. Note that PF5 is powered up to 24kA in the current set up. 3. Upgrade TF feed such that TF can be pulsed every 20 minutes. (Note that we can with appropriate controls, pulse with a period < 40 / 20 minutes based on the I^2*t imposed on the coil system.)  In the current scope the TF can be pulsed only once in 40 minutes. This requires additional power cabling from the Transition area to the NSTX Test Cell, additional changes in the PCTS, enhancing the feed from PCTS to coil terminals.  We can also consider providing a water cooled bus in the NSTX Test Cell Basement from the place the power cables are terminated. 1raki

POWER SYSTEM CHANGES CONTD. 4. Make changes as needed to operate CHI from 2kV to 4kV.  In order to address this requirement we must plan right now to choose the appropriate insulation for the CHI leads and the Inner vessel. Note that the Inner Vessel to Outer Vessel will require to be hipotted at 9kV instead of 5kV as at present. 5. Convert PF1a circuit from a 3- Wire scheme to a 2 - Wire scheme.  This is required to upgrade CHI from 2kV to 4kV. The work involves additional cabling. 6. Change DCCT positions such that these measure the coil currents directly. At the present time the DCCTs are above the SDS in some circuits *7. Repair MG2 weld to restore normal rating  At present MG2 can be used only at about 15% of the full energy rating *8. Repair MG1 Welds so that it can be an effective standby.  This also increases the life of the MGs by alternating usage of the sets  Following tasks are being performed at present. Part of this task was originally included in the NSTX upgrade scope but were transferred to Operations cost.  Change FD/FG for all the suppliies needed to power NSTX. Eliminate the PC link.  Note that we are currently performing this task. In this modification we are changing the FD/FG for active rectifiers which will be used for NSTX. Also a slow PLC I/O will be provided in these rectifiers to interface with the main PLC that will be provided in the Cntrol Boards.) (* MG information from Mounir Awad) 2raki

PWR SUPPLY TABLE (Extracted information from CN design point spreadsheets) 3raki

MG REQUIREMENTS (Extracted from CN design point spreadsheets) raki4

NSTX PRE-UPGRADE CIRCUITS raki 5