Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Slides:



Advertisements
Similar presentations
DESIGN LAYOUT OF DISTRIBUTION SYSTEMS
Advertisements

Theme – Rural Infrastructure and Development Case study - Addressing the issue of drinking water & water pollution Team Members Parth Gupta Shruti Ohja.
4/26/2006 – Nicaragua, Matagalpa: Elder Hogar Improvement Project Team: Nick Carey, Gita Dombrowski, Jeremiah Hess, Chris Lastomirsky Engineers Without.
Washington State Department of Health Division of Environmental HealthOffice of Drinking Water Mike Dexel Water Resources Policy Lead Municipal Water Law.
Allegany-Limestone Central Schools Department Budget Presentation: Drafting our Plan for the Future To the Allegany-Limestone Board of Education February,
Green Roof Action Project 綠頂行動 Our scheme is not just about physical implementation of green features on top of school buildings, it is about the knowledge.
ISLA POPA II, PANAMA WATER SUPPLY PROJECT July 10 th 2014.
EWF- Rural Water Supply Proposal
Monroe L. Weber-Shirk S chool of Civil and Environmental Engineering WFP Slideshow Photos from Water For People Projects Courtesy of Jody Camp Photos from.
Presentation on City of Westminster Water System Pressures May 1, 2013.
CE HYDRAULICS ENGINEERING
Engineers Without Borders Princeton University Amanda Li ‘16, Corrie Kavanaugh ‘17, Hana Ku ‘17, Josh Umanky-Castro ‘17, Kasturi Shah ‘16, William Guiracoche.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2012 Updated: 2/12/2012.
Logistics: How to Set up and Manage a Project. Logistics The aspects of an operation that deal with the procurement, distribution, maintenance, and replacement.
Monroe L. Weber-Shirk S chool of Civil and Environmental Engineering Water Supply Engineers without Frontiers.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2012 Update: 2/2/2012.
Las Delicias, El Salvador Water Supply Project Implementation Proposal Phase I Trip Dates: May 2012 Presented to TAC: March 7, 2012.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2011.
Session Objectives To introduce the Micro-Hydro Project Scope & Plan
Future Vision Plan Update Rotary Foundation Grants and Sustainability.
EWB-MAP Water Tank Project Construction Progress June 5-12, 2012.
FHM TRAINING TOOLS This training presentation is part of FHM’s commitment to creating and keeping safe workplaces. Be sure to check out all the training.
ENGINEERS WITHOUT BORDERS – NORTHEASTERN UNIVERSITY CHAPTER MENTOR: TIMOTHY J. MCGRATH, PH.D., P.E. Water Storage and Distribution Bbanda, Uganda.
Who We Are Mission:Working with developing communities to improve their quality of life through sustainable engineering projects Part of a national.
RESPIRATORY PROTECTION STANDARD FEDERAL REGISTER 1/8/98 29 CFR Revised Other OSHA Standards That Incorporated By Reference.
Experiences from the Field: Building a Water Distribution System in Rural Honduras Ethan LaRochelle Northeastern University Engineers Without Borders Building.
Water for Life Project Apatut, La Union, Philippines
Implementation Trip for Date of TAC Presentation: April 14 th, 2009 Project Location: El Chaguite, Yoro District, Honduras Project Risk Level: 2 Northeastern.
Lecture 1 Water Distribution Systems
EWB-NCSU Bolivia Water Supply Project. Why Do They Need Additional Water Supplies? School Students Add to Population Rainfall – Avg. 8.5 in/yr – 0.7 in/month.
H umanitarian R esponse in S indh Update as of: 9 March 2011.
Public Hearing August 30, 2014 Drive-Way Ordinance Please Sign in…
REGIONAL DISTRIBUTION CENTRE CEDI PARTNERS Noah Chapman, Rob Campbell and Kyla Hanson LAC SEUL FIRST NATIONS.
12, 2916 – 5 th Avenue Calgary, Alberta, T2A 6K4, Canada Phone: + 1 (403) , Fax: + 1 (403) Website:
Pipeline Crossing Suncallo, Bolivia Mountain TAC Presentation October 4 th, 2010 Engineers in Action.
WSNTG Annual Conference 8 th September 2005 WSNTG 9 th Annual Conference “Water Services Strategic Plans – Fact or Fiction”
Western Regional Gas Conference August 24, 2010 Distribution Integrity Management Programs (DIMP) Rule.
MUS pilot project in Honduras Testing guidelines for planning and implementation of multiple use services.
Best for the Buck: Using Asset Management for Project Design at Highline Water District Matthew J. Maring, P.E. April 30, 2008.
Washington’s Water Use Efficiency Rule May Require Increased Coordination for Many Utilities Dan Sander, P.E. Senior Engineer.
BASICS IN IRRIGATION ENGINEERING 2.1. Planning Irrigation systems 2.2. soil-plant-water relation – over view 2.3. Crop water requirement 2.4. Base, delta.
Short and Long Range Water Supply Planning and Aquifer Performance Test (APT)
Network Appurtenances Major operations within a water transport and distribution systems are: 1. Transmission. 2. Storage. 3. Pumping.
EWB-USA Principles of Development. Our Mission EWB-USA supports community-driven development programs worldwide by collaborating with local partners to.
Circuit Rider Training Program (CRTP) Circuit Rider Professional Association Annual General Meeting and Conference August 30, 2012.
Engineers Without Borders-USA Mid-Atlantic Professionals Chapter Water for Life Project Apatut, La Union, Philippines Amanda Jacobs Project Lead.
Pipeline Safety: How the Mayor’s Council On Pipeline Safety Can Help Presentation to: Mayor’s Council on Pipeline Safety Conference Name: Christopher A.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Withlacoochee Regional Water Supply Authority Withlacoochee Master Regional Water Supply Planning and Implementation Program (WMRWSPIP) Technical Review.
Rugerero, Rwanda A village tap is located in the center of the village Housing units have been equipped with rainwater catchment systems.
CE 3372 WATER SYSTEMS DESIGN Lecture 09: Report writing and cost estimating.
Josiah Dobson Brett Nicholson Travis Befus Team 11.
Existing System The system originally operated with everyone having 24-hour availability. The village then created a 3-day rotation which improved the.
Steve Bonk Kevin Dischino Joseph Moore
Components of Water Networks Eng. Mona Al-Gharbawi Eng. Ayman Al-Afifi
Pressure and Flow Analysis Through EPANET Open source software package for hydraulic simulation of water distribution networks Used to determine impact.
1 Global Water is an international, non-profit, humanitarian organization focused on providing safe water supplies, sanitation & hygiene facilities for.
Sanitary Sewer Fee Study March 4, Summary Sausalito’s 75-year-old sewer system is old and deteriorated. While the current rates have allowed the.
Timing (minutes) Learning ObjectiveMain tasks / ProcessResources / tools 5TitleStandard Operating Procedures for Power Press Machine Slide 1 5Index 
1 Highland Water District CAPITAL IMPROVEMENT PLAN.
RESIDENTIAL RAINWATER HARVESTING PROJECT ALTITUDE ENGINEERING, INC. PRESENTERS: HAYLIE BREWER, ERICA KIESOW,& BRETT HIGHTOWER DATE: APRIL 28 TH,
EWB-USA Hartford Professional Chapter Sabhung, Nepal Water Supply Project Project Background o The Sabhung Village Development Committee (VDC) is part.
Grey Owl Municipal Water feasibility study
Fort Stanwix National Monument Energy Audit Contract
Metropolitan Airports Commission
Shyamaghat Rainwater Model Project
Engineers Without Borders
City of Roundup, Montana
Water Distribution Networks Under Intermittent Pumping: Development of a hydraulic model and Assessment of water losses Prepared by Mohammad Jihad Abdo.
Department of Teaching & Learning
Presentation transcript:

Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System

2

3

4

Guides Project: El Chaguite Water System5

El Tecuan Project: El Chaguite Water System6

Los Planes Project: El Chaguite Water System7

Project Schedule Project: El Chaguite Water System8 Dates of TravelPurposeDescription December 2007Los Planes Implementation & El Chaguite Assessment Complete Transmission Main in Los Planes, Visit El Chaguite April – May 2008El Chaguite Assess.Water Quality, Hydraulic Investigations, Existing System Inspections, Topographic Survey, Health Survey December 14- December 29, 2008 El Chaguite Phase 1 Implementation Construct Transmission Main/ Begin Distribution System April – May 2010(proposed) El Chaguite Phase 2 Implementation Storage Tank/ Finish Distribution System

El Chaguite Existing System 9Project: El Chaguite Water System

Existing Conditions Project: El Chaguite Water System10 Sufficient, clean water source Limited service Unusable distribution system Damaged main line Diverse topography Hurricane damage Fire damage

11Project: El Chaguite Water System

Current and Future Conditions Project: El Chaguite Water System12 Chaguite now:Chaguite in 25 years: 60homes87homes 333people483people 68students99students Conditions now:Conditions in 25 years Total Average Available Flow (GPD) 22,349 Total Average Available Flow (GPD) 22,349 Total Average Demand for People (GPD) 8,797 Total Average Demand for People (GPD) 12,755 Total Average Demand for Irrigation (GPD) 3,000 Total Average Demand for Irrigation (GPD) 4,350 Total Demand (GPD)11,797Total Demand (GPD)17,105

Design Details Feasibility Transmission Main Distribution Network Float Valve Tank Sustainability Project: El Chaguite Water System13

El Chaguite Population: 333 people Project: El Chaguite Water System14

Overall Feasibility Project: El Chaguite Water System15 Water Source : gpm (22,348 gallons/day) 25 year projected demand: 12,755 gpd +4,350 gpd (Irrigation use) 17,105 gpd Diurnal Demand Cycle Conclusion: Feasible with water storage tank

Design Process Project: El Chaguite Water System16 Excel water flow model WaterGEMS flow model Multi-phase implementation Phase 1 (COMPLETE) –Construct Transmission Main –Instruct villagers on construction of distribution system –Build break pressure tank (float-valve tank) Phase 2 –Water storage tank –Inspect village-constructed distribution system

Transmission Main Project: El Chaguite Water System17 Source Proposed Tank Site Existing Tank Site

Transmission Main Project: El Chaguite Water System18

Float Valve Tank Project: El Chaguite Water System19

Alternatives Considered Project: El Chaguite Water System20 North Water Storage TankEast Water Storage Tank

Distribution System Model Project: El Chaguite Water System21

El Chaguite Project: El Chaguite Water System22

Transmission Main Project: El Chaguite Water System23

Trench Detail Project: El Chaguite Water System24

Trench Examples Project: El Chaguite Water System25

Tank Design

Trip Schedule Project: El Chaguite Water System27 Jun-11 Fly to San Pedro Sula Get Supplies Order Materials Visit Rigo Jun-12 Buy Groceries Order Rest of Supplies Research Pumps for Carrizalito Project Jun-13 Drive To Rosario Meet with Village and Present Design Lay out Tank Site Jun-14 Dig Tank Site Transport Bricks, Cement, Rebar, etc. Jun-15 Train Villagers our process for concrete Jun-16 Layout casting of Foundation Jun-17 Cast Foundation Jun-18 Inspect Distribution System - Day 1 Install Services - Day 1 Jun-19 Start Walls of Tank Inspect Distribution System - Day 2 Install Services - Day 2 Jun-20 Visit Los Planes Visit El Tecuan Jun-21 Survey Carrizalito Take a trip to Yoro Jun-22 Cut GI pipe for tank Visit El Rosario School Jun-23 Visit El Chaguite School Jun-24 Final Meeting With El Chaguite Jun-25 Drive to San Pedro Sula Jun-26 Fly back to Boston

Budget Project: El Chaguite Water System28 El Chaguite Phase 2 Estimated Budget Travel Airfare $ 4,800 Exit Fees $ 210 Truck Rental $ 1,300 Gas $ 120 Ground Hotel $ 300 Food $ 600 Labor Guides $ 240 Laundress $ 100 Cooks $ 240 Materials PVC Fittings/Valves $ 180 GI Pipes & Fittings $ 281 Tools $ 164 Tank Materials $ 1,365 Contingency $ 928 Total $ 10,827

Building Materials Project: El Chaguite Water System29 ItemsQuantityUnitsUnit Price ($)Total Price ($) PipesGI2 Inch80ft $ 2.50 $ Fittings/Valves TapsPVC 1/2 Inch60ea $ 3.00 $ CouplingGI 2 Inch6ea $ 1.73 $ Elbows (45 or 90)PVC 1/2 Inch120ea $ 0.40 $ Valves PVC 1/2 Inch60ea $ 3.05 $ GI Gate Valve 2 Inch3ea $ $ GI Globe Valve 2 Inch1ea $ Tools Pliers4ea $ $ Trowel4ea $ $ Plasterer's Float4ea $ $ Bucket12ea $ 4.00 $ Level2ea $ $ Tank Materials Cement60bags $ 5.10 $ Sand9cy $ $ Gravel7cy $ $ Brick3000brick $ 0.13 $ #3 Rebar2000ft $ 0.16 $ #4 Rebar800ft $ 0.16 $ Barb Wire1000ft $ 0.02 $ Staples3lb $ 0.68 $ 2.05 Nails3lb $ 0.68 $ 2.05

Sustainability Extra materials supplied for maintenance and replacement. Locals will be educated on water conservation and proper system maintenance. Water Board will collect usage tax to fund future repairs. Simple design and construction Project: El Chaguite Water System30

Community Ownership & Education Project: El Chaguite Water System31 What kind of help will the community be providing? –Labor (digging trench, laying pipe, mixing cement, transporting materials). –We will coordinate a schedule of construction with El Chaguite’s Water Board. Who will own the project once it’s completed? –El Chaguite will own the water system upon completion of the project. The El Chaguite Water Board will manage the communally used infrastructure.

Community Ownership & Education Project: El Chaguite Water System32 Who will be overseeing maintenance once the team leaves and how will repairs be paid for? –El Chaguite’s Water Board will be overseeing the maintenance of the system. We will leave extra materials with the villagers to take care of any immediate necessary repairs. Hopefully, with improved health, the villagers will be able to establish community funds and pay for repairs further in the future. What education will be provided to the community? –The community will be educated on the maintenance of the system, and we also plan to provide information about health and sanitation. In order for this to be a successful effort we will be working with the community Water Board and local organizations to ensure that the people understand the situation and are well informed about health and sanitation issues.

Project Lead Sign-Off Project: El Chaguite Water System33 I, Daniel P. Saulnier, P.E., as the Professional Mentor of this project, have reviewed the technical and logistical contents of this project, and approve of the proposed design. I will also comply with TAC recommended changes and make suggested changes before traveling on the implementation trip. Daniel P. Saulnier October 8, 2008 [signed]