Broadway Street Viaduct Improvement, Pre-Load Testing and Geotech Report Workshop Consultant Presentation Iowa DOT 2 nd April 2007
Workshop Goals Agree on recommended bridge and foundation alternative to be carried forward into preliminary design. Decide if bridge and geotechnical reports will be combined into one final report. Discuss level of effort anticipated in conducting the pre-final design load testing program for the post-grouted drilled shafts
Information from February 2006 PIM
Overview of Bridge Replacement Options Update to bridge options and schedules presented in the June 2006 Draft Bridge Report Three bridge replacement options Three bridge lengthening alternatives Drilled shafts as foundations
Bridge Construction Costs
Summary of Options Option Estimated Construction Cost Estimated Time For Completion 1. Least Cost $ 10.1 million 10 months 2. Shortest Schedule $ 16.5 million 7 months 3. Hybrid $ 10.2 million 9 months Costs do not include approach slabs, demolition and mobilization.
Option 1: Least Cost
Option 2: Shortest Schedule
Option 3: Hybrid Concept
Lengthening the Bridge Construction Cost Implications Soil Remediation and Retaining Wall Implications Lengthening Options
Lengthening the Bridge
Alternate 1 Extend bridge 37’-6” at east end Extend bridge 25’-0” at west end Sloping ground under bridge MSE walls along sides Alternate 2 Extend bridge 100’-0” at east end Provides 9’-0” min. vertical clearance under bridge MSE walls in front of abutments Alternate 3 Extend bridge 200’-0” at west end Extend bridge 250’-0” at east end Provides 2’-0” min. vertical clearance under bridge Soil remediation significantly reduced Cantilevered retaining wall likely used for remaining short fill heights
Lengthening the Bridge
Alternate 1 Alternate 2 Alternate 3 Bridge $ 500,000 $ 500,000 $ 800,000 $ 800,000 $ 3,600,000 $ 3,600,000 Slope Paving $ 45,000 $ 45,000 $ 0 $ 0 MSE Wall ($ 170,000) ($ 117,000) ($ 1,000,000) Soil Remediation ($ 40,000) ($ 75,000) ($ 600,000) Pavement & Barrier ($ 47,000) ($ 75,000) ($ 334,000) Net Cost $ 288,000 $ 288,000 $ 533,000 $ 533,000 $ 1,666,000 $ 1,666,000 Average Net Cost for Additional Bridge Length = $ 4,600 / ft.
Foundation and Soil Remediation Options Post-grouted Drilled Shafts Drilled Shafts Socketed in Bedrock CMC Ground Improvements at Bridge Approaches Lightweight Foamed Concrete Fill at Approaches
Drilled Shaft Load Test Program Expected Schedule Level of Effort Required from CH2M HILL
Bridge Aesthetics Piers, Abutments, Retaining Walls Bridge Railings, Barriers, Beams Coloring textures, Rustications Lighting