ATLAS POH.P, G.D12/5/2009 IBL Update H. Pernegger, G. Darbo (PO 12/5/09) Organization and WG coordinator Schedule Decision Items Organization Tools & Meetings.

Slides:



Advertisements
Similar presentations
3D Sensor Processing - IBL G. Darbo – INFN / Genova Venezia, 4 June 2009 o IBL per Marzio G. Darbo - INFN / Genova Agenda page:
Advertisements

M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
IBL interim-MoU Annexes G. Darbo – INFN / Genova PEIB, 1 March 2010 o IBL interim-MoU Annexes Pixel Extended Institution Board CERN, March 1 st, 2010 NCP.
Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September 2009 o Update on ATLAS insertable B-layer LHCC Upgrade session CERN, September, 22 nd 2009.
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
NSW SG 19 Nov Nov 2014 S. Zimmermann, NSW SG 1.
IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 o IBL Spare Slides Commissione I – 22 Nov 2010 G. Darbo - INFN / Genova.
Towards a TDR for the IBL G. Darbo - INFN / Genova AW, 24 February 2009 o Towards a TDR for the IBL ATLAS Upgrade Week CERN, 24 February 2009 Session:
ALICE ITS Coordination Board 16 July 2013 L. Musa 1.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013.
IBL MoU G. Darbo – INFN / Genova 24 April 2010 o IBL MoU ATLAS Upgrade Week DESY, April 24 th 2010 M. Nordberg, M. Nessi, C. Gößling, H. Pernegger Presented.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
DCS Workshop - L.Jirdén1 ALICE DCS PROJECT ORGANIZATION - a proposal - u Project Goals u Organizational Layout u Technical Layout u Deliverables.
IBL MoU G. Darbo – INFN / Genova 17 April 2010 o IBL MoU Contribution prepared for Marzio’s talk at April RRB G. Darbo - INFN / Genova.
ATLAS Preparations for LHC Phase-I Upgrade G. Darbo – INFN / Genova ATLAS Week, 8 July 2009 o ATLAS Preparations for LHC Phase-I Upgrade ATLAS Week CERN,
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
15/2/2006 LHCC Status Report J. Schukraft General News LHC progress & Schedule  now recent news on schedule  ‘closure of beam on 31 August’, first injected.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September 2009 o Update on ATLAS insertable B-layer LHCC Upgrade session CERN, September, 22 nd 2009.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
Communications G. Darbo – INFN / Genova IBL MB#15, 5 October 2009 o Bump Bonding Selex / INFN Roma, October, 30 th 2009 G. Darbo - INFN / Genova.
Jorgen Christiansen, CERN PH-ESE 1.  Spokes persons and Institute chair elected ◦ SP’s: ATLAS: Maurice Garcia-Sciveres, LBNL CMS: Jorgen Christiansen,
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
July 17, 2013 CERN T. Flick University of Wuppertal.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
IBL - Opening G. Darbo - INFN / Genova AW, 25 February 2009 o IBL Introduction & Project Organization ATLAS Upgrade Week CERN, 25 February 2009 Session:
C. Kiesling, 1st Open Meeting of the SuperKEKB Collaboration, KEK, Dec , The DEPFET-Project: European Collaboration for a Pixel SuperBelle.
October RRB G. Darbo & H. Pernegger RRB – October 2010 o October RRB Slides for Marzio’s RRB talk CERN, October, 11 th 2010 G. Darbo & H. Pernegger.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Local Supports to IDR Discussion ATLAS Upgrade Week November 2014.
IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
AFP – Technical Status 1.Cost estimates 2.Manpower estimates 3.First Actions AFP Kick-Off 03FEB Michael Rijssenbeek.
IBL – UniGe involvements UniGe Team : G. Barbier, F. Cadoux, A. Clark, S. Débieux, D. Ferrère, C. Husi, G. Iacobucci, M. Weber Other member (KEK): Y. Takubo.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
IBL TDR G. Darbo / INFN Genova ATLAS CB – October 2010 o TDR of Insertable B-layer ATLAS CB, October 8 th 2010 G. Darbo / INFN - Genova Indico agenda page:
IBL Progress D. Ferrère for the IBL community LHCC Upgrade Session – June 14 th 2011 Detailed progress was reported at the IBL General meeting, June 8-10.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
Main Linac Technology (MLT) Meeting To be held through WebEx July 13, 2007.
ATLAS Italia – IBL G. Darbo – INFN / Genova CERN, 2 March 2011 o IBL ATLAS Italia / Referee CERN, March 2 nd 2010 G. Darbo – C. Meroni INFN / GE – MI Agenda:
ALICE Upgrade Construction management system Adriana Telesca ALICE MFT Plenary meeting 9 July 2015.
The ATLAS IBL Project – 5 th Trento Workshop G. Darbo – INFN / Genova Manchester, February 2010 o The ATLAS IBL Project The 5 th "Trento" Workshop.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
20/07/ Marzio Nessi Agenda For NIKHEF plans for the ATLAS Upgrade. NIKHEF ATLAS upgrade plans and organization DL/NH Potential.
Upgrade plans for ATLAS. Nigel Hessey (Nikhef) is overall ATLAS upgrade coordinator.
TC activities.
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
FBK / INFN Roma, November , 17th 2009 G. Darbo - INFN / Genova
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
EDR HLRF Work Packages Draft Summary
TK Upgrade report.
Communications Share Point Collaborative WS:
Status of CO2 Cooling tests at CERN for Pixel phase 1
Update on ATLAS insertable B-layer
The WIGOS Pre-Operational Phase
SVT – SuperB Workshop – Frascati Sept. 2010
Perugia SuperB Workshop June 16-19, 2009
Presentation transcript:

ATLAS POH.P, G.D12/5/2009 IBL Update H. Pernegger, G. Darbo (PO 12/5/09) Organization and WG coordinator Schedule Decision Items Organization Tools & Meetings

ATLAS POH.P, G.D12/5/2009 Management board Module WG (2 coordinators) FE-I4 Sensors Bump-Bonding Modules HDI Test & QC Irradiation Module WG (2 coordinators) FE-I4 Sensors Bump-Bonding Modules HDI Test & QC Irradiation Stave WG (1 Phys + 1 Eng.) Staves Loaded Stave Internal Services Test & QC Cooling Design & Stave Thermal management Stave WG (1 Phys + 1 Eng.) Staves Loaded Stave Internal Services Test & QC Cooling Design & Stave Thermal management IBL Integr.-Install. (2 Eng.) Stave Integration Global Sup. Beam Pipe (BP) Ext.services inst. IBL+BP Installation Cooling Plant Test & QC IBL Integr.-Install. (2 Eng.) Stave Integration Global Sup. Beam Pipe (BP) Ext.services inst. IBL+BP Installation Cooling Plant Test & QC Off-detector (1 Phys + 1 E.Eng.) Power DCS ROD Opto-link Ext.serv.design/proc Test Beam System Test Off-detector (1 Phys + 1 E.Eng.) Power DCS ROD Opto-link Ext.serv.design/proc Test Beam System Test IBL Management Board Membership: IBL PL + IBL TC 2 coordinators from each WG Plus “extra” members IBL Management Board Membership: IBL PL + IBL TC 2 coordinators from each WG Plus “extra” members

ATLAS POH.P, G.D12/5/2009 IBL MB Composition PL and TC propose the following IBL (MB) Composition: –IBL Project Leader: G. Darbo (Genova) –IBL Technical Coordinator: H. Pernegger (Cern) –“Module” WG: Maurice Garcia-Sciveres (LBNL) + Fabian Hugging (Bonn) –“Stave” Working Group: Ole Rohne (Oslo) + Danilo Giugni (Milano) –“IBL Assembly & Installation” WG: Neal Hartman (LBNL) + Raphael Vuillermet (Cern) –“Off-detector” WG: Tobias Flick (Wuppertal) + Stephane Debieux (Geneva, tbc) “Extra” members: –Ex officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), Pixel Chair (C. Gößling) –Offline “liaison”: Pixel Off-line coordinator (A. Andreazza) –TDR editor (K. Einsweiler + M. Capeans) Working Group coordinators have been selected in discussion with IBL PL, IBL TC, the candidates and responsible of their home institutes. –Normally WG coordinators are endorsed by Institute Board –We propose to appoint WG coordinators today ad interim and present this proposal for endorsement at the IB kick-off meeting on July 8. –Appointment is for a two years term

ATLAS POH.P, G.D12/5/2009 Institute Board July 8 (Atlas week)

ATLAS POH.P, G.D12/5/2009 Working group mandate WG coordinators will –In design phase: follow interfaces, define tasks, deliverables, study design options and contribute “their” sections to the TDR –In production phase: lead qualification process on prototypes and follow construction deliverables and tasks through the project –Track actions in their area and report them to the MB PL and TC have asked workgroup coordinators now to prepare a “mandate” for each working group which includes: –List of activities for each WG –Update of list of deliverables where applicable –First preliminary estimate of resource needs (manpower!) and schedule for R&D, prototyping and construction –Have already a first draft for 3 WG (see last two MB meetings) This is to be included into the IBL Project Organization Document ATU- ORG-MG-0001 by Giovanni, Heinz, Nigel ready for presentation at the IB kick- off meeting

ATLAS POH.P, G.D12/5/2009 Towards a Schedule: general consideration Assume an installation date of Oct 2013 (obviously we will get more info during the time to come) –The schedule is build by working “backwards” from the installation date –A later date (2014?) may give us more time for RD (FEI4) but needs to be balanced with the need for contingency. –We need to forsee time for commissioning after the installation date. The IBL is small in “number of modules” –Many components are produced with a “single batch” hence our scope to overlap activities and component production is limited This is a first attempt with many assumptions and over the next week(s) we will develop a detailed schedule for each working area –This can then become a first “baseline” schedule –It does not yet include most of the prototyping (except on chips & sensors) Based on this first baseline schedule we need to agree on milestones The schedule will (in some cases) drive the decision making process and timescale for technical decisions (see later)

ATLAS POH.P, G.D12/5/2009 FEI4 drives the schedule for modules -getting the next FEI4 asap is crucial for module qualification - do we need 2 eng. Runs or 2 eng runs + 1 prod run? Service installation happens in shutdowns - need definition & procurement of services (USA15- >PP2) early on to use shutdown time efficiently Stave 0 plays a crucial to qualify the IBL system (staves and off detector electronics)

ATLAS POH.P, G.D12/5/2009 Decision items Goal is to establish –Where do we need studies? –When do we have to decide between options? Need to understand which items need redesign and to develop a complete system layout. This can then be used to update list of deliverables and coordinate the institute’s contributions and provide input to funding requests. The following list is sorted by working area and nothing more than a personal view Module –Sensor technology to be used in IBL (mid 2010) –FEI4 functionality & “IBL” version: based on next prototype and its test results: this drives the schedule for IBL, need to investigate if we can build IBL on 2 engineering runs (present schedule) or need 2 eng. Runs + 1 production run (during module assembly) –Module size (end 2009?) : this drives mech. designs –Bump bonding : only 1 vendor or qualify second for FEI4? Stave –Stave cooling : which type of pipe and coolant? (end 2009?) –Single stave or bi-stave engineering –Fittings/connectors at end of stave or “7m” object? (end 2009) –EoS card: is it passive or does it need active parts (data, power) (end 2009)

ATLAS POH.P, G.D12/5/2009 Decision items cont. Integration and installation –Beam pipe removal feasibility study to be concluded (mid 2008) for tooling design –Exact beam pipe specs for IBL and replacement beam pipe (when?) –Support “strategy” for IBL: on BP or on a “mini” PST (when?) Off-detector –Powering: study for what to do if DC-DC conv. nn FEI4 cannot be used (can start now) –Services inventory and detailed specifications for power,readout,cooling (end 2009?): needed to plan installation and routing –ROD/BOC specs revisited with FEI4 test results (mid 2009?)

ATLAS POH.P, G.D12/5/2009 Meetings & Work spaces Regular meetings –Management board weekly Mo 15h30-17h30 –Module & Off-detector WG bi-weekly Thursday –Stave and Integration/Installation WG bi-weekly Tuesday –Still investigation best possible meeting configuration in ID with Pippa –General meetings : 2 days (next June 25-26) –Currently book rooms for those meetings with help from Atlas secretariat Mailing Lists –Created one per WG + general + Management board Share point: Collaborative work space for WGs and MB – Action list on Share point created –“Track Issue” in MB Share Point EDMS tree created for technical documentation –