Houston Area Dynamic Reactive Project March 11, 2011 1.

Slides:



Advertisements
Similar presentations
Houston Region Import Capacity Project Planning for Reliable Power.
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Regional Planning Group Project
ERCOT VRT Study, Phase I ERCOT ROS Meeting December 10, 2009.
Challenge of Large Scale Wind Power Integration - Introduction to the Workshop Pradeep Perera Principal Energy Specialist Asian Development Bank.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Arrowhead  Weston Transmission Line Project Dave Van House Minnesota Power.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
Technical Advisory Committee December 6, 2010 Summary of the CREZ Reactive Study Warren Lasher Manager, Long-Term Planning and Policy.
System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
California Energy Commission Workshop Nuclear Power Plant Issues
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
“Reactive Power Management and Voltage Stability” Sharma Kolluri, IEEE Fellow Manager of Transmission Planning Entergy Services Inc Presentation at 2012.
ISO Exhibit 13 Federal Energy Regulatory Commission Technical Conference on Connecticut Infrastructure Reliability and Operability Committee Update Hartford,
© New York Independent System Operator, Inc. All Rights Reserved. Michael Swider Manager – Research & Development New York Independent System.
1 Cheng-Ting Hsu Chao-Shun Chen Islanding Operations for the Distribution Systems with Dispersed Generation Systems Department of Electrical Engineering.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
PROJECT NO PUCT STAFF WORKSHOP 11/19/14 Julia Harvey Kristi Denney Kevin Mathis Jasmin Thevaril.
Golden Valley Electric Assoc. Inc © 2012 GVEA. All rights reserved. GVEA BESS Expected and Actual Performance Dan Bishop Golden Valley Electric Assoc Fairbanks,
Lyndonville Electric Department Feasibility Analysis Review December 2,
RPG Meeting Five Year Plan Extension Brad Schwarz.
PRR835 – Reactive Power Capability Requirement
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
CRR Auction Scope John Moseley. To outline aspects of the CRR market process to assure that these proposed CRR market protocols (as interpreted by ERCOT.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
LAREDO RMR EXIT STRATEGY Presentation to Technical Advisory Committee March 4, 2004 Transmission Services Operations.
Long-Term Solution for Negative Generation Entergy Transmission AFC Stakeholder Meeting August 22, 2006.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
ERCOT PUBLIC November RPG Meeting RTP – Study Scope November 20, 2015.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
ERCOT DYNAMICS WORKING GROUP Report to ROS August 16, 2007 Vance Beauregard, American Electric Power.
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Voltage Control Brad Calhoun Consultant, Sr. Trainer Spring 2016.
Houston Import Project – ERCOT Independent Review
Houston Area Constraint Mitigation Project ERCOT Board of Directors March 15, 2005.
Freeport Area Master Plan Project
Freeport Area Master Plan Project -
FACTS Devices for Dynamic Reactive Power Compensation in Wind Farms
Calvert City Power I, L.L.C. (“Calvert”) Purpose of Meeting
CSC DETERMINATION PROCESS
FACTS Devices for Dynamic Reactive Power Compensation in Wind Farms
FACTS BY SVC, FLEXIBLE AC TRANSMISSION
IG BASED WINDFARMS USING STATCOM
Warren Lasher Manager, Long-Term Planning and Policy
Compliance Report to ERCOT TAC February 2007
CIGRE Grid of the Future (GOTF) Symposium
Local Area Planning Update to TRANSAC – March 15, 2017
DEC System Voltage Planning - June 2018
Palo Verde-COI RAS Retirement
FACTS BY SVC, FLEXIBLE AC TRANSMISSION
Palo Verde-COI RAS Retirement
Presentation transcript:

Houston Area Dynamic Reactive Project March 11,

Background  Houston area becomes high import area in 2002  NRG (formally Texas Genco) retires 3800 MW in early 2005  Dynamic reactive support lost  Houston imports 25% or more of load requirement from resources external to the CenterPoint Energy footprint  Local dynamic reactive supply has declined More vulnerable to voltage collapse Houston’s high concentration of residential air conditioning load makes the situation worse Load continues to grow 2

3 With units on-lineWith units off (Voltage Collapse) 3-phase fault with delayed clearing Effect of Retiring 3800MW of Local Generation

Steps Taken to Address Voltage Stability Concerns  Under voltage load shedding (UVLS) scheme at CenterPoint Energy completed in 2005  Participation in EPRI load modeling efforts  More than 1550 MVAR of capacitor banks added to the transmission system since 2005  Houston Area Constraint Mitigation projects  STP – Hillje – WAP circuits  Singleton and Zenith substations  Fayetteville – Zenith circuits  Installed a total of 280 MVAR of dynamic reactive compensation in 2008  TSC’s at Bellaire and Crosby  140 MVAR each 4

Recent and Future system developments  Received Notices of Suspension of Operations for approximately 900 MW of generation (~470 MVAR of total continuous reactive capability) within the past year  2014 maximum Houston import UPLAN dispatched case with recently approved transmission projects shows an additional 1800 MW of local Houston area generation offline.  ERCOT’s December 2010 Long-Term System Assessment Report highlights the need for additional supply of local dynamic reactive power and “will conduct further analysis of these potential reactive needs in cooperation with the transmission service provider for the Houston area” 5

Houston Dynamic Reactive Study  Dynamic analysis is required to determine proper dynamic reactive compensation solution  2013 Summer Peak base case  UPLAN Generation Dispatch provided by ERCOT  Dynamic analysis requirements  Detailed generator models, complex load models including induction motors, UVLS models, and Over-excitation limiter models  Disturbance studied: 3-phase fault cleared by breaker failure relaying taking two elements out of service NERC Category D No more than 1250 MW of UVLS should be lost - Reserve a portion of UVLS as safety net due to modeling uncertainties and avoid over- frequency excursions Transmission system voltages must recover so that no generator terminal voltage remains below 90% of rated voltage for more than 10 seconds. 6

Study methodology  Contingency Screening  Time domain contingency screening to determine worst case event  Contingency #58 proved to be the worst case event leading to Fault- Induced Delayed Voltage Recovery violating both aspects of the performance criteria  Load modeling sensitivities  Various types of load models were considered including large, small, and air conditioning motor models  Load model sensitivity analysis also includes a variation of the motor model parameters  Load Model #1 – represents large and small motors with conventional induction motor models  Provided more reasonable and realistic results  Development research for Load Model #2 is still ongoing 7

Houston Dynamic Reactive Study 8  Load Model # Base Case  Results in 5185 MW of UVLS  Eight local generator terminal voltages do not recover to 90% voltage within 10 seconds

Voltage Recovery Solutions  Dynamic reactive device technologies considered  STATCOM  STATCOM with Overload Capability  SVC  TSC  Additional option to package each technology with an additional Mechanically Switched Fixed Capacitor  Dynamic models of distinct characteristics of each technology were included  Primarily concerned with capacitive compensation to satisfy performance requirements 9

Location Considerations Installations New Proposed Installations Dynamic Reactive Projects ROTHWOOD ZENITH ADDICKS BELLAIRE CROSBY

Required Dynamic Reactive Devices Ratings 11 Type of Dynamic Reactive Device Addicks & RothwoodAddicks & Zenith MVAR capacitive output of each device measured at High side voltage Resulting MW Load Shed MVAR capacitive output of each device measured at High side voltage Resulting MW Load Shed STATCOM OC Short-term rating Continuous rating STATCOM OC w/140 MVAR FC Short-term rating Continuous rating104 STATCOM STATCOM w/140 MVAR FC SVC SVC w/140 MVAR FC TSC

System voltage recovery with SVC Example 12  System voltage response with addition of 518 MVAR SVC  Results in 1148 MW of UVLS  All local generator terminal voltages recover to 90% voltage within 10 seconds

Proposed Schedule  February 2011: Project submitted for RPG comments  March – May 2011: ERCOT Independent Review  June 2011: Bid package and specification released to vendors  February 2012: Award contract to vendor  2 nd Quarter 2014: Complete Commissioning 13

Summary  Houston area in need of dynamic reactive support due to generation retirements, increased imports, and load growth  CenterPoint studies showed a need for 350 – 550 MVAR of dynamic reactive compensation at two sites each in order to satisfy performance criteria  Final amount of reactive compensation will be dependent on technology type and vender bids.  Estimated cost is $125 million  Estimated completion date in 2 nd Quarter