ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.

Slides:



Advertisements
Similar presentations
The Preassembling Installation Survey & Alignment Accelerator Center of IHEP Qu Huamin 2006 / 4 / 27.
Advertisements

LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
Main Injector Gap clearing kickers Phil Adamson (#) AEM 14th March 2011.
ANU Cooling Systems Karl Williams Fermilab Accelerator Division CD-2/3a DOE Review of NO A October 23-25, 2007.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
The Tevatron Decommissioning Plans AEM 10/17/11 Paul C. Czarapata.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
1 LEReC Funded! From: Fedotov, Alexei Sent: Thursday, May 14, :04 PM Subject: LEReC project approved Dear All, FYI. The LEReC project is now formally.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
G 0 Coordinator Update & “To-Do List” Joe Grames William & Mary, June 5-6, 2006  Hall C Beam Line Tasks  Accelerator Preparation Tasks  Beam Halo 
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
TD Help for Shutdown 2012 Preliminary, will be updated April 18, 2012.
All Exp Mtg July 7, 2008 NuMI-MINOS Status Report – Laura Loiacono FAR DETECTOR: FD live time was 95.7% for cosmics last week (ROP7 problems reported at.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
2/17/2016 Recycler -Gattuso Recycler Shut Down Status  Flying Wire Status  Wire Vacuum Certified  Tunnel Bake Prep status Disconnection of BPM, Correctors,
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
AP2-Debuncher Injection Area 2004 Shutdown Work August 2, 2004.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Mike Andrews August 30, Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Maximum Credible Beam Loss in the Main Injector D. Capista January 26, 2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
P1, P2 and AP-1 Aperture Improvements February 5, 2015 J. Morgan 1.
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
MI/RR Status January 3, 2014 D. Capista. MI Preformance.
Mike Andrews August 17, Week 16 NuMI Activities Leak testing of DI bottles & Casks Complete all bottles & casks RAW Impulse line upgrade Finished.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Completion of the MICE-US construction project
NuMI - Shutdown – Week 9 Horn 2 Repair – Successfully Tested the Repaired RAW Leak Drained and Refilled Horn 1 and 2 RAW Systems Changed Horn 2 DI Bottle.
J. Seeman Assistant Director for PPA/LCLS
Presentation transcript:

ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012

NuMI Activities Target Pile dehumidifier repairs & upgrades - 95% complete –Electrical hook ups remain should be complete today or tomorrow Phase 1 of Horn 2 RAW system NoVA/ANU upgrade -100% complete New NoVA/ANU Target Pile fan cooling coil 75% complete –New cools are on order and will arrive in 6-8 weeks Un-forseen problem with existing cools start to leak after system was being refilled. Relocation of TP fan controls and sum box -100% complete –This move was require to open space for Raw water system upgrades Work cell lighting & electrical service installation -90% complete –What remain is some electrical installation for decay pipe De humidifier cooling coil. Facility drain & drip ceiling cleaning-100% complete (will need to be repeated at the end of shut down) –Complete drain cleaning in shaft area –Completed drain cleaning in the Absorber Passageway & Hall

4 NuMI Activities Replaced Pretarget magnets Q113, Q114, & Q % Complete –Vacuum has been restored –Cable pulls are complete Terminations and hook up will occur later this week Pull 6 electrical cables from the shaft to new quad locations -50% complete –Complete cable pulls through the upper labyrinth –Started cables pulls in the Pre-Target area –Installed handrail above emergency walkway –Installed scaffold in PT area Chase to be opened in week 8 (~ 2weeks from now)

Decommissioning MI/RR Stochastic Cooling system – 100 % Complete – Tanks and Stands removed – Tanks and Stands removed Spool piece in place Bake setup underway Bake Schedule for Tuesday afternoon after Service Building power outages R22 Line - 90 % Complete –Vacuum components in line have been harvested –Instrumentation components have been harvested BPM Toroids Multi Wires –Recycler Lambertson at 212 location Waiting on spool piece will be ready this week –MI Lambertson at 221 was removed (class mr/hr)

Decommissioning MI/RR R32 Line - 25 % Complete –Vacuum components in line will need to be harvested –Instrumentation components will need to be harvested BPM –Toroid's –Multi Wires –Lambertson removal MI 321 location- 100 % Complete (was class mr/hr) –Spool piece in its place RR 328 location – Schedule for later this week –Correction elements 100 % Complete Have been harvested Already reassigned to new girders –Mirror magnet MGS-001 Removed and relocated for future installation in the new extraction line

Decommissioning MI/RR August 31, 2010 DOE Review MI-620 Region A150 line Decommissioning % Complete –Two 2Q130 were removed from 902 and 901 location Magnets are being reworked for NuMI beam line spares Required the removal and reinstallation of Q618 –MI 620 Lamberstons Two have been removed and placed in short term storage (MSB) One Lambertson Staged for future installation at the 306 location –MI 620 wide aperture quad has been swopped out with 306 Quad –V901 C-Magnet was removed and put into viable spares pull (TPL) –2 kickers left in the A50 alcove (class 2-3) Replaced of NuMI stub 100 % Complete –Replaced Q111 & Q112 (3Q120 magnets Peter porch) –Reworked Stand for V109 to abate future install problems for mangets in the stub region

MI/RR RF section MI RF system Decommissioning % Complete (Shipped to TPL for storage) –Six 2.5 MHz RF cavities were removed –One 106 MHZ RF cavity were removed –Two Barrier Bucket RF cavities were removed MI RF system Installation/ Maintenance –RF4A cavity installation -100 % Complete –RF15A cavity installation -20% Complete Space for cavity has been made –Cavities determined to need tunnel repairs (1 to 2 weeks/ Cavity) We need to pull RF cavities 8 and 16 to replace bellows and flanges. Water cooling loop work for cavities 7, 12, 13, 15, and 17

Cables Pulls/Misc. Cable Pulls (~450 K feet of cables) –MI-50 House BPM cables 100 % Complete –5 days to complete – re-spooled to length –Historically ~2 week Sextupole cables 100 % Complete –MI-40 House BPM cables –Being staged –Pulls will start Tuesday BPM preamp- ion clearing module removal 100 % Complete –1 55 gallon barrel of circuit boards (mixed wasted) –1 64 cu. ft cube of rad waste August 31, 2010 DOE Review

Injection line Installation Recycler line installation -20% complete (Stand installation/relocation process halted) –Problems encountered Installation drawings slow to materialize Stands placement Interferences between the two beam lines Stands placement issues with respect to beam center line –Verify stake out marker locations –Verifying Lattice files –We have a plan……. MI line relocation –MI Quads and PDD magnets 60% complete MI-14 Fluorinert Piping Installation –Installed the brackets on the wall for the Fluorinert lines in the Q104 region –Relocated the Fluorinert manifold from the Q400 region to the Q104 region. –All the welds, from the penetration to the end of the Fluorinert run, that is, past the gate near the Q104 region, have been completed

Original Schedule

Current Schedule