Mike Peckham CAC January 16, 2007 Pickering A Units 2 & 3 Safe Storage Project.

Slides:



Advertisements
Similar presentations
Metrolinx is an agency of the Government of Ontario Planning, Design and Engineering (PDE) Workplan February 20, 2009.
Advertisements

Introduction. What is ISO14001? A documented system of all impacts a company are having on the environment. A detailed strategy to reduce these impacts.
Pickering B Refurbishment and Continued Operation EA Update Presentation to Pickering Community Advisory Council Nuclear Generation Development May 20,
Planning, Budgeting, Acquisition & Management of Capital Assets Capital programming is an integrated process within an agency for planning, budgeting,
FPSC Ten Year Plan Workshop Nuclear Panel Steven Scroggs Senior Director, Project Development Florida Power & Light Company August 15, 2007.
Rivanna Water & Sewer Authority Community Water Supply Plan Update Public Meeting Monticello High School September 21, :00 pm.
Symposium on Private Financing for African Power Infrastructure US Treasury Department Washington, DC October 13, 2008.
1 KRB-A (Grundremmingen, Germany). 2 Type:Boiling Water Reactor Power: 250 MW(e) Started in 1966, shut down in 1977 First commercial power reactor in.
Visaginas, 2008 INPP Decommissioning Strategy, Programme, Licensing.
Northwest Rail Update Nadine Lee, Northwest Rail Project Manager Regional Transportation District March 21, 2012.
Project management Topic 3 Directing a project. Overview of processes Authorise Initiation Authorisation for Initiation Stage Authorise the Project Contract.
Safety and Security Aspects of the Management of High Level Waste and Spent Fuel Ramzi Jammal Executive Vice-President and Chief Regulatory Operations.
The decision box represents key management decisions and serve as the GATES which delineate phases. The decision can be to proceed, exit, or recycle. More.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
ENVIRONMENTAL MANAGEMENT PLAN
Species at Risk in Ottawa 2014 Educational Series February 6, 2014.
Kiggavik Project Final Hearing Presentation
Standard WBS Version 1.0 WBS2-3.pptPage 1 Standard Work Breakdown Structure Legend = Decomposes to lower level WBS elements 4.0 Implementation 4.0 Implementation.
August 10, 2007 CONTROL YOUR DATA CENTER! Tune your Legacy Data Center to improve overall efficiencies.
California Energy Commission James Madigan April 27, 2015.
Group New Projects Related to Decommissioning. 29 th May 2008 KNPP Richard Benbow – Head of Kozloduy PMU.
VERMONT YANKEE Transitioning into SAFSTOR ​SEPTEMBER 2, 2015 Paul Paradis Director Decommissioning.
August 4,  Vermont Yankee Nuclear Power Station (VYNPS) ceased power operations on December 29, 2014 after 633 days of continuous power operation.
Nuclearsafety.gc.ca Joint Congress on Medical Imaging and Radiation Sciences May 28, 2015 e-Doc CNSC Administrative Monetary Penalties Overview.
MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
MODULE “COST ESTIMATION, CALCULATION AND COST CONTROL” SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo da.
Nunavut Impact Review Board Presentation of Technical Submission AREVA Resources Canada Inc. Kiggavik Uranium Mine Project March 2015 Transport Canada.
Planning and Community Development Department Housing Element City Council February 03, 2014.
Toll Road Asset Management and the Linkage to Finance Transportation Innovations, Inc. 10/22/
BIM Bridge Inspection and Maintenance Technical Standards Branch Class B Bridge Inspection Course Inspection Policies and Procedures INSPECTION POLICIES.
MODULE “PROJECT MANAGEMENT AND CONTROL” SAFETY ASSESSMENT DURING DECOMMISSIONING SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
Federal Energy Regulatory Commission The Pre-Filing Process IRWA/AI January 13-14, 2009 IRWA/AI.
Repatriation of Vinča RA Reactor Spent Fuel The 15th International Symposium on the Packaging and Transportation of Radioactive Materials PATRAM
1 ESTABLISHMENT OF REQUIREMENTS Module “ Development of regulatory framework for oversight of decommissioning Project BG/04/B/F/PP , Program “Leonardo.
Project Management Process Transition & Closure Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team.
Ottawa’s Light Rail Transit Project OLRT Update to Finance and Economic Development Committee March 2011.
1 ESTABLISHMENT OF REQUIREMENTS Module “DECOMMISSIONING PROCESS” Project BG/04/B/F/PP , Program “Leonardo da Vinci”
Specific Safety Requirements on Safety Assessment and Safety Cases for Predisposal Management of Radioactive Waste – GSR Part 5.
Embedding Carbon Management within Public Sector Organisations 17 th November 2015.
-1- UNRESTRICTED / ILLIMITÉ Demonstrating the Safety of Long-Term Waste Management Facilities Dave Garrick 2015 September.
Sydney (02) Melbourne (03) Brisbane (07) Carlo Biaro Capital Insight Conference 2013 – Tools and.
Managing the Environmental Impacts of Power Canada Europe Roundtable for Business Toronto, 31 May 2005.
District Improvement Plan
Role of Self-Assessment V.C. Agarwal, Director (HR) NPCIL,INDIA.
DEVELOPMENT OF THE NATIONAL INFRASTRUCTURE FOR NUCLEAR POWER IN VIETNAM DEVELOPMENT OF THE NATIONAL INFRASTRUCTURE FOR NUCLEAR POWER IN VIETNAM Vuong Huu.
Britannia Village Flood Control Project Report Back to RVCA Board of Directors – Dec 16, 2010 after attendance at Community Meeting of November 30, 2010.
Reliability-Must-Run (RMR) Cost Evaluation and Settlement Basis Ino González ERCOT RMR Workshop May 24, 2016.
General Overview of the Romanian Nuclear Utility NUCLEARELECTRICA Dumitru Dina Head of Nuclear Safety Department 1WASHINGTON DC, USTDA , September.
COMPREHENSIVE EVERGLADES RESTORATION PLAN …different cultures -- same Team.
Decommissioning San Onofre
Data Center Stabilization
Assignment 1: Defining a project and its scope.
The report on the IBR-2 modernization
Vermont Yankee Decommissioning Update
ALLPIRG/4 MEETING PARTICIPANTS (Montreal , 8 February 2001)
Janet R. Schlueter Senior Director, Radiation and Materials Safety
Flooding Walkdown Guidance
HSIS S2 Governance HSISG HSIS S2 Bruce Lines Alastair Burt
Presentation Title: View > Header & Footer
PRESENTATION OUTLINE Introduction and Background
Adding Nuclear Power to the Grid
Board of Regents Capital Projects Review & Approval Process
Controlling Project Cost and Schedule
Water & Environmental Affairs
MEMBERSHIP GROWTH.
Phase 1 Statement of Work Preconstruction “Plan The Work”
Q2 Updates on 2019 Board Priorities
Q2 Updates on 2019 Board Priorities
Pacheco Reservoir Expansion
Early Funding (Regulations Section 6010)
Presentation transcript:

Mike Peckham CAC January 16, 2007 Pickering A Units 2 & 3 Safe Storage Project

1 The Decision Environmental Assessment Site Acceptance Construction Commissioning Operation Safe Storage Dismantling Site Restoration OPG Management recommended that the restart of Units 2 and 3 not proceed, based on return on investment analysis. Decision endorsed by Board of Directors and Provincial Government. This decision is final.

2 Safe Storage Stage Overall principles have been identified: Both reactors will be defuelled. Heavy water will be removed from the moderator and heat transport systems. Systems will be de-activated (where possible). Common systems supporting Units 1 and 4 will be moved to a live unit (where possible).

3 Strategy System end states have been developed for each of the 53 groups of systems identified for system performance monitoring. End states are being documented and approved in a Safe Storage Package, which will include: Flowsheets Controlled document lists Master equipment lists Power supply lists Air supply lists Active TCR Applicable predefined

4

5 Engineering Packages Type of Package Unit 2 Unit 3 End State Reports5450 Modifications Cut and Cap New Modifications Regulatory commitments from RTS6637

6 Schedule - Milestones

7 Progress to Date Maintenance of safe, laid-up state Rehabilitation of Unit 2 fueling machines 104 End State Determination Reports Development of project governance Budget quality cost estimate Project Execution Plan Initial contracts for design engineering CNSC staff in Ottawa briefed; no significant concerns raised Commenced defueling Unit 2 August 23 Design changes 69 of 612

8 Licensing Issues The CNSC has approved reactor defuelling and removal of heavy water under the existing operating license. At sometime in the future after the fuel and heavy water have been removed, the license may again be modified to reflect the safe storage conditions.