Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Slides:



Advertisements
Similar presentations
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Advertisements

Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Tom Kubicki.  Booster HLRF System to be upgraded using 1kW Solid State Driver (SSD) Amplifiers.  Used to drive the 200kW Power Amplifier  Eliminates.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
1 Electron Cloud Measurements at the Fermilab Main Injector Bob Zwaska Fermilab ECloud07 Workshop April 9, 2007.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
Proton Plans at Fermilab Robert Zwaska - Fermilab Science and Engineering at Henderson- DUSEL Capstone Workshop Stony Brook University May 5, 2006 Outline.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Getting Beam to NuMI (It’s a worry!) Peter Kasper.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
Injector PP Setup Plan and Status November 18, 2008 Haixin Huang.
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
Proton Study Meeting 4/19/05 Eric Prebys 1 Proton Plan Stage I Eric Prebys.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Booster Issues for NuMI Eric Prebys FNAL Beams Division.
F Proton Plan Eric Prebys and Ioanis Kourbanis, FNAL Accelerator Division.
MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Accelerator Status and Plans
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003.
Proton Planning – Major Projects, Schedule, Decisions, and Projections Eric Prebys FNAL Accelerator Division.
Doug Michael Sep. 16, GeV protons 1.9 second cycle time 4x10 13 protons/pulse 0.4 MW! Single turn extraction (10  s) 4x10 20 protons/year 700.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
Proton Plan Expectations Eric Prebys AD/Proton Source.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status January 2006 Pushpa Bhat.
AGS Run-9 Preparations, Status and Plans Dec. 16, 2008 Haixin Huang.
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
Proton Plan PMG 5/25/06 David Harding Booster Correctors Status and CR David Harding.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Answers to Questions Director’s Review August 2006 Eric Prebys.
Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Source July 21, 2006 E Prebys 1 Proton Plan Meeting Agenda:  Review of parameter list: Prebys, Kourbanis  Status of writing assignments Prebys,
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
PAC Meeting, December 12, Prebys 1 The Problem.
Intensity Dependent Quad Ramps We know that in order to get the most intensity, the quad ramps must be tuned for a particular intensity. The way this is.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
MI/RR Operation Status Ioanis Kourbanis August 21, 2014.
Proton Plan 1/10/07 E Prebys 1 Proton Plan Meeting Agenda:  Project/campaign reorganization: Prebys  Status updates: all  Booster Water Proposal: Cooper.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Proton Economics Eric Prebys FNAL Accelerator Division.
Booster Corrector Review, Oct. 10 th, 2006 E. Prebys Introduction/Specifications Eric Prebys Proton Plan Manager.
Oversight Board Meeting October 3, 2017 Rob Michnoff
Presentation transcript:

Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys

Proton Plan PMG 3/22/07 E Prebys 2 Shutdown Preparations and Schedule – Prebys/Mau Operations – Prebys Technical Progress - Prebys Cost/Schedule Report – Baller Agenda Covered under shutdown prep.

Proton Plan PMG 3/22/07 E Prebys 3 Proton Plan Shutdown Projects Linac  Low Level RF Upgrade  Complications NTF Running MTA beamline (not part of Proton Plan) Booster  Long straight correctors Huge project  Water supply upgrade Main Injector  Ring Collimation System Two primary and four secondary collimators Requires rerouting of power bus and water  RF upgrade Transformer upgrade Comb filter

Proton Plan PMG 3/22/07 E Prebys 4 Linac LLRF Status Have design Waiting on FPGA Board prototype Will not drive shutdown

Proton Plan PMG 3/22/07 E Prebys 5 Booster Corrector Status Magnets:  Two Prototypes built and tested Look good Second prototype will be put in Booster tunnel ~April  Vendor Deliveries Cores: over half delivered Coils: lots of start up problems, but now first couple of magnets’ worth delivered  Assembly Beginning assembly of first magnet from vendor-supplied components Power supplies  5 (4x40A + 1x65A) of the six power supply types in procurement  Remaining PS (2.5A skew quad) straightforward

Proton Plan PMG 3/22/07 E Prebys 6 Corrector Schedule

Proton Plan PMG 3/22/07 E Prebys 7 Power Supply Schedule

Proton Plan PMG 3/22/07 E Prebys 8 Booster Water Upgrade Current system will not handle 15 Hz operation  Already operating outside of specificiations Beginning staged upgrade this shutdown  Will upgrade West gallery return from 2” to 4” and 6”.  New manifolding.  Will still tie into existing return via tunnel Estimate 4-6 weeks. Preparing fixed price contract bid package. We will not allow this project to drive shutdown.

Proton Plan PMG 3/22/07 E Prebys 9 Main Injector Collimator Status

Proton Plan PMG 3/22/07 E Prebys 10 MI RF Upgrade Projects Solid state power supplies  Ordered: ~4-8 weeks delivery  Installation will take about 10 days Install spare anode transformer at MI Center Will modify all three anode power supply transformer slabs for new transformers, compatible with NOvA operation. Procuring new transformer for south anode power supply  Will not be ready for shutdown

Proton Plan PMG 3/22/07 E Prebys 11 Linac LLRF  Could be ready for July 1 shutdown  Can be installed arount NTF schedule (total of ~2 days/station x 5)  Will not be allowed to drive shutdown Booster  Water Can be ready for July 1 st shutown 4-6 weeks installation Will not drive shutdown  Correctors Can not be ready until an August 1 st shutdown at the earliest 8 weeks installation, assuming no interference Main Injector  Collimation Can be ready for a July 1 st shutdown Currently 16 weeks installation. Hope to shorten to 12. Summary Start date driver Length driver

Proton Plan PMG 3/22/07 E Prebys 12 Worries and Caveats Correctors  Production of cores and coils is proceeding, but we have not yet built a production magnet from vendor-supplied parts.  We do not yet have a single vendor-supplied power supply  Installation schedule does not yet allow for interference with other projects, resource leveling, and does not include commissioning time (would ideally like two full weeks dedicated time). Main Injector Collimators  Utility rerouting scheme still very preliminary  No detailed installation plan Present time estimate (conservative) WAG

Proton Plan PMG 3/22/07 E Prebys 13 Operations

Proton Plan PMG 3/22/07 E Prebys 14 Operational Highlights MiniBooNE  Still off  All plates lowered without incident  Waiting for stainless steel rods to lift back into out position  Scheduled to come back on ~mid April. NuMI  No significant down time since last PMG Overall uptime since Feb. 1 = 94%!! –Design: 80% –Base: 70% Helps compensate for unrealistic cycle time  Continue to push batch intensity  Slip stacking studies continue Reached 4.05E13 protons to NuMI in tests  Continue to work to reduce cycle time from 2.4->2.2 seconds

Proton Plan PMG 3/22/07 E Prebys 15 Review: NuMI Cycle Time Issues Because pBar and NuMI batches are accelerated together, the NuMI cycle time is locked to the pBar production cycle time. Original assumption:  NuMI and pBar would run at 2 second cycle times during 2+5 operation (limited by minimum pBar rep. rate)  Cycle time would change to 2.2 seconds for 2+9 operation (limited by MI loading time) In fact:  pBar has problems running below 2.4 seconds, significantly reducing beam to NuMI  The effect was originally largely cancelled by NuMI only cycles (during shot setup and “interleaved” mode when the accumulator had large stacks)  Now with fast transfers to Recycler, there are very limited NuMI-only cycles Present status:  Working to optimize pBar for 2.2 cycle time  Will lock complex to that time through end of collider program  Not yet accounted for in this year’s projections

Proton Plan PMG 3/22/07 E Prebys 16 NuMI/pBar Cycle Time Progress

Proton Plan PMG 3/22/07 E Prebys 17 NuMI Dotted lines are 2.4 second rep rate

Proton Plan PMG 3/22/07 E Prebys 18 MiniBooNE MiniBooNE still off Will cross blue line ~May 1 Scheduled to come back on in mid-April

Proton Plan PMG 3/22/07 E Prebys 19 Total Booster Output Mostly reflects loss of MiniBooNE