LHC 30 th and 31 st July 2015 07:10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
LHC 14 & 15 April :22: Ramp to 6.5 TeV lost due to MUFO, resulting in quench 10:30: Access during cryo recovery 16:00: Pre-cycle 17:05: RB.A78 short.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC 23 June :07: Started injection cleaning with B1. 08:13: Fault on MKI B2. –MKI Beam 2 in P8 had a breakdown at 07:49 during the SoftStart process.
R.Giachino / M.Albert Be/op 12 th March 2012 LHC Machine check out 1v1.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC Beam Operation Comitte24. April INJECTION AND TRANSFER LINE STABILITY L.Drøsdal For the injection team.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
LHC report Friday 22 nd June 2016 Coordination: Wolfgang Hofle and Mike Lamont.
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Machine Coordinators: G. Arduini, J. Wenninger
SPS extraction, transfer lines, injection
Saturday :12 Stable beams fill 3351 Initial luminosity
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Monday fill with 1092 bunches (6 h stable beams)
Saturday 30th June - Sunday: Rocky !
Tue :25 Beams dumped due to RF vacuum interlock
Thursday morning – optics correction
Summary of Week 11: 14 – 21 March
Monday – recovery from MKI flashover
Wednesday 31 October: Morning
LHC Injection and Dump Protection
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Scrubbing progress - 09/12/2012
Scrubbing progress - 10/12/2012
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Wednesday 03/11 – The Plan Finish electron-cloud program:
Wednesday 10/5 Cryo recovery until 18:30
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Monday 24 October hours of 25ns MD
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Scrubbing progress - 08/12/2012
IP8 aperture measurements (07:30-10:30)
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Injection Studies: 50 ns ABT/BTP.
Another Immortal Fill….
Monday 27th August & night
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Tuesday
Presentation transcript:

LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09 Cryogenics interlock due to beam screen heating (CS R7 and L3) then vacuum valves in at P2 due to outgassing of beam screen Q6R2  pre-cycle so decided to start to long awaited / postponed injection kicker waveform scan –Missing data in Global Post Mortem 09:30 Start injection kicker MKI Point 8 waveform measurement –Thanks to LHCb for the many resets of the BCM interlock ! –At several occasions missing half the BTV screen data  reboots 16:45 Finished waveform scan: pre-cycle following cryo interlock 17:30 BLM IL thresholds increased by factor 2 on TCLA.B6R7.B1 and QI.8L2.B1 (see presentation 8:30 meeting of yesterday) 19:00 Transfer line steering with adjustment of MKI kick, both beams 21:00 TDI check 21:30 Cryo lost in matching section point 8 (without much beam)  fast precycle 00:15 Injecting 01:48 Dump on losses on long running sum TCTPV.4R2 on injection of 144 b 02:00 SPS problems (mains  RF) until this morning. Back again at 6:45 LHC Morning meeting – MG & JU131/7/2015

Vacuum valves in due to outgassing of beam screen LHC Morning meeting – MG & JU231/7/2015 Beam vacuum > 1e-6 mbar TDI vacuum from MKI waveform

Injection kicker MKI waveform scan Following change of Pulse Forming Network in TS1 to recover fast rise time –Batch spacing 1000 ns  900 ns Measured mostly the "shoulders" to save time, but measurement is very slow due to the LHCb interlock issue Results seem consistent with MKI2: –Rise time roughly 900 ns (within spec, needs precise analysis) –Ripple also within specification –Positioning of first bunch and other more detailed results to be determined after the offline analysis of the measurements Then Etienne to adjust the kicker timings and we can use the closer batch spacing LHC Morning meeting – MG & JU331/7/2015 Linda, Chiara

First results To be further analysed LHC Morning meeting – MG & JU431/7/2015

Injection Steering Further adjust MKI kick setting after BETS window re- centring 2 days ago Steer back to trajectory obtained before TS1, before PFN changes, around which TL collimators are aligned Final MKI voltage settings (BETS window is +/- 1 kv) –MKI.P2: V (BETS centre of V) –MKI.P8: V (BETS centre OF V) Reduces significantly the losses which were recently generated from the TCDIs within the vertical bump The MKI voltage reduced by a bit more than 1 kV, beneficial for reducing the probability of an MKI flashover To be done –Tighten operational limits of the MKI around these values –Update the IQC reference LHC Morning meeting – MG & JU531/7/2015 Chiara, Janet, Linda, Wolfgang

TDI Check Move TDI jaws separately outwards In IP8 stronger effect upper jaw movement There is a mechanism which populates the halo of beam 2 faster than beam 1 (also observed at the primaries) LHC Morning meeting – MG & JU631/7/2015 MB.15R8.B2 not far away … Benoit

The Plan Friday and later: –Continue some 25 ns scrubbing –Switch over to doublets possibly during the weekend or on Monday (t.b.d.) if doublets in the SPS look good and scrubbing with 25 ns standard beams is sufficiently advanced –Scrubbing with doublets As well: –1 hour to deploy and test PM / XPOC fix –Update MKI operational limits and IQC references (parasitic) Outstanding: –Injection cleaning optimisation LHC Morning meeting – MG & JU731/7/2015

Report from scrubbing …. LHC Morning meeting – MG & JU831/7/2015 No scrubbing in the last 24 h