FLAO Interface Control Document Presented by A. Riccardi S. Esposito, A. Tozzi, A. Riccardi, R. Biasi, D. Gallieni FLAO system external review, Florence, 30/31 March 2009
FLAO system external review, Florence, 30/31 March 2009 ICD structure Described interfaces for W@LBT and LBT672: Mechanical Optical Cooling Electrical power and signals Network Real time communication SW interfaces in a different document FLAO system external review, Florence, 30/31 March 2009
Overview of connections LBT672: M2 unit in Hub LBT672: Spider-arm cabinet W@LBT: AGW unit FLAO system external review, Florence, 30/31 March 2009
Overview of physical connections Cooling lines (from telescope) I/O signals (diagnostic lines) Power lines (120VAC, UPS assisted, from tel.) Fast comm link (optical) Power lines (208VAC, from telescope) Gbit ethernet (optical fiber) Power lines (48VDC, internal) FLAO system external review, Florence, 30/31 March 2009
FLAO system external review, Florence, 30/31 March 2009 W@LBT: structure W@LBT: 264 kg (total AGW: 684 kg) FLAO system external review, Florence, 30/31 March 2009
W@LBT: Mechanical interface 3x2 connection screws (4 M8, 2 M10) FLAO system external review, Florence, 30/31 March 2009
W@LBT: Mechanical interface 6 connection M10 screws 2 connection M6 screws FLAO system external review, Florence, 30/31 March 2009
W@LBT: Cooling interface FLAO system external review, Florence, 30/31 March 2009
LBT672: interface sectioning M2 unit in Hub Mirror unit:303 kg Hexapod: 149 kg Hub: 253 kg Tot: 708 kg 1 2 4 3 Spider-arm cabinet FLAO system external review, Florence, 30/31 March 2009
LBT672: Mechanical interfaces FLAO system external review, Florence, 30/31 March 2009
Electrical/Communication FLAO system external review, Florence, 30/31 March 2009
Electrical/Communication/Cooling Fiber connector (18 fibers) Power and digital flags connector Fluxmeter connector Hub temperature FLAO system external review, Florence, 30/31 March 2009
FLAO system external review, Florence, 30/31 March 2009 End of presentation FLAO system external review, Florence, 30/31 March 2009