Question 25: Delineate the R&D program remaining before a technical design review (TDR) and full cost estimate can be prepared. What are the major projects.

Slides:



Advertisements
Similar presentations
February 7, 2007-Beijing (Zisman-DR) Global Design Effort 1 Damping Ring EDR Plans Michael S. Zisman, Jie Gao, Susanna Guiducci, Andy Wolski DR Area System.
Advertisements

Q20: The X-band collider has much tighter requirements for the alignment of the beam orbit with the structure axis, yet the basic instrumental precision.
Page 1 Collider Review Retreat February 24, 2010 Mike Spata February 24, 2010 Collider Review Retreat International Linear Collider.
SuperB and the ILC Damping Rings Andy Wolski University of Liverpool/Cockcroft Institute 27 April, 2006.
Industry and the ILC B Barish 16-Aug May-05ILC Consultations - Washington DC2 Why e + e - Collisions? elementary particles well-defined –energy,
Baseline Configuration - Highlights Barry Barish ILCSC 9-Feb-06.
Damping Rings Baseline Lattice Choice ILC DR Technical Baseline Review Frascati, July 7, 2011 Mark Palmer Cornell University.
Linear Collider Machine Protection Issues M. Palmer Injection System Injector Damping Rings Bunch Compressor and Transfer Sections Main LINAC Beam Delivery.
3-March-06ILCSC Technical Highights1 ILC Technical Highlights Superconducting RF Main Linac.
European Design Study Towards a TeV Linear Collider WP 2 : Beam Delivery System Co-ordinator: Deepa Angal-Kalinin CCLRC, Daresbury Laboratory.
SLAC ILC Accelerator: Luminosity Production Peter Tenenbaum HEP Program Review June 15, 2005.
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
2011 Damping Rings Lattice Evaluation Mark Palmer Cornell University March 8, 2011.
Gek 16/6/041 ITRP Comments on Question 19 GEK 9/06/04 19) For the X-band (warm) technology, detail the status of the tests of the full rf delivery system.
Main Linac Integration Work Packages Chris Adolphsen Dec 11, 2007 High Priority Items in Red.
TTF-II Status & Prospectives Nick Walker DESY 5 th ITRP Meeting – CALTECH.
1.Energy reach  High power klystrons and modulators for X-band still need development and industrialization, and thus brings risk. But klystrons of similar.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
International Linear Collider The ILC is the worldwide consensus for the next major new facility. One year ago, the choice was made between the two alternate.
Summary of WG1 K. Kubo, D. Schulte, P. Tenenbaum.
IR summary M. Sullivan Nov. 3, 2011 JLAB MEIC IR workshop.
Beam dynamics on damping rings and beam-beam interaction Dec 포항 가속기 연구소 김 은 산.
Nick Walker Marc Ross Akira Yamamoto 2010 (and beyond) Plans & Milestones.
1Matthias LiepeAugust 2, 2007 LLRF for the ERL Matthias Liepe.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
A general comment first: The questions ITRP has posed to the proponents focus largely upon technical issues for the linear collider. These are important.
CesrTA Experimental Plan M. Palmer for the CesrTA Collaboration November 17, 2008.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
NLC Status and Milestones D. L. Burke ISG9 KEK December 10-13, 2002.
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
Report of 2 nd ILC Workshop (Snowmass) Working Group Kiyoshi KUBO references: Slides of the plenary talks in the workshop by P.Tenembaum and.
Summary of TDR Cost Reviews at KILC-12 G. Dugan KILC-12 4/26/12.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
Global design effort DOE meeting 8/10/06 Global design effort Americas 1 FY07 DOE ILC Budget recommendations G. Dugan ILC-GDE/Cornell University GDE Americas.
Meeting of the European Global Design Effort Report from INFN non EU-funded R&D Carlo Pagani University of Milano and INFN DESY, 10 May 2006.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
International Linear Collider Technology: Status and Challenges Steve Holmes Fermilab Wine & Cheese Seminar September 24, 2004.
Beam Dynamics WG K. Kubo, N. Solyak, D. Schulte. Presentations –N. Solyak Coupler kick simulations update –N. Solyak CLIC BPM –A. Latina: Update on the.
13 September 2006 Global Design Effort 1 ML (x.7) Goals and Scope of Work to end FY09 Nikolay Solyak Fermilab Peter Tenenbaum SLAC.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Low Emittance Generation and Preservation K. Yokoya, D. Schulte.
NLC - The Next Linear Collider Project Tor Raubenheimer Beam Delivery System Design Differences American Linear Collider Physics Meeting SLAC January 8.
General remarks: I am impressed with the quantity and quality of the work presented here and the functioning of the organization. I thank ILC and FNAL.
ILC R&D at KEK Beam Control Technology –ATF –ATF2 Acceleration Technology –High-gradient Cavities L-band R&D Stand –Linac System  STF –Construction of.
24-July-10 ICHEP-10 Paris Global Design Effort 1 Barry Barish Paris ICHEP 24-July-10 ILC Global Design Effort.
Beam losses in the CLIC drive beam: specification of acceptable level and how to handle them ACE Michael Jonker.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Round Table discussion Norbert Holtkamp SNS Oak Ridge National Laboratory August 11, 2004.
1 Comments concerning DESY and TESLA Albrecht Wagner Comments for the 5th meeting of the ITRP at Caltech 28 June 2004 DESY and the LC What could DESY contribute.
ILC R&D Activities at KEK Superconducting Linac Development Beam-handling Technology Development.
CTC Work Packages ver 2.1 HS for CTC. CTC-001SC wigglers Cooling design, hor. or ver. Racetrack coil Nb3Sn or NbTi cable Prototypes construction Experimental.
Tests on production cryomodules Bob Kephart Sept 30, 2006.
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
1 DR 10 Hz Repetition Rate S. Guiducci (LNF) AD&I webex, 23 June 2010.
The Engineering Test Facility for nLC
ILC - Upgrades Nick Walker – 100th meeting
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Chris Adolphsen Sergei Nagaitsev
R&D Topics for FOA Funding Proposals
High Gradient Cavities: Cost and Operational Considerations
Measurements, ideas, curiosities
XFEL Project (accelerator) Overview and recent developments
Electron Source Configuration
Accelerator R&D Results from the B-factory
CLIC damping rings working plan towards the CDR
ATF project meeting, Feb KEK, Junji Urakawa Contents :
Status of CTC activities for the Damping rings
Barry Barish Paris ICHEP 24-July-10
Summary of the maximum SCRF voltage in XFEL
Crab Crossing Named #1 common technical risk (p. 6 of the report)
Presentation transcript:

Question 25: Delineate the R&D program remaining before a technical design review (TDR) and full cost estimate can be prepared. What are the major projects and approximate cost of the technical system R&D needed to validate the design? Analysis: 1.Summarize the proponent responses 2.Use the TRC issues (R1-R3) to guide understanding of needed R&D 3.Some evaluative comments Paul Grannis June 2004

TESLA response: “all basic R&D for innovative components were done by end of 2000, and all tested in TTF; thus cost estimate is done.” But they do identify remaining major component R&D:  Demonstration of operable 35MV/m cryomodule  Long operation of RF power system at maximum loads, including modulator, HC pulse cable, klystron, rf power delivery  Optimization of electropolish facility and process procedures  System and value engineering for all large quantity components. TESLA identifies 77M€ (92M$) for R&D in (no salaries), of which 43M€ are associated with the XFEL, which serves as a TESLA testbed.

Further R&D noted:  Fast kicker for damping ring  Reliability studies  Accelerator physics studies  Full LC simulation (including ion instability, electron cloud, alignment tolerances) “Full cost estimate can be done in less than 1 year after site selection.”

What remains according to TRC (2003)? TESLA specific: R1: 35 MV/m cryomodule test (partially satisfied for components, not module) ‡ R2: several cryomodules in correct environment, with proposed power systems, beam, HOM couplers, alignment systems. Evaluate operational quench and breakdown rates. Both for 500 and 800 GeV. ‡ R2: development of damping ring kicker ‡ R2: simulation for damping ring particle loss, systematic and random multipole errors, wiggler errors; dynamic aperture of DR optimization ‡ R2: DR alignment tolerance for 500 → 800 GeV; suppression of e-cloud and ion instabilities ‡ R2: review of head on collisions and implication for extraction line design; possible redesign for crossing angle. R2: evaluate reliability and operability analysis for single tunnel. ‡ = noted in TESLA response

My comments on TESLA:  The damping ring for cold LC is not noted as major R&D item, but the range of issues here (vacuum, e-cloud, kicker, emittance control, operability constraints) make me believe that this will remain a necessary high priority area for R&D.  The high dark current seen on one cavity at 25 MV/m (not electropolished, non-standard assembly sequence) is a worry, and sufficient R&D to demonstrate that this is not a limitation for SC acceleration will be needed. Long term cryomodule tests at full gradient remain crucial.  Further evaluation of the e + production system and the impact of using full energy e  beam on commissioning will take effort  Ability of all components (not just cavities) to sustain higher rf power for 35 MV/m should be demonstrated.  If 0 o crossing, demonstration needed of electrostatic separators in radiation field, radiation effects on final doublet, masking, beam losses

X-band response: “baseline technologies are in hand and tested. Main R&D needed is for value engineering, industrialization, reliability, serviceability. Some R&D remaining for specialized components, and for seeking improvements to baseline design.” Many remaining issues are site specific (ESH, site preparation etc.) Final engineering and design will need to be done by GDO. Identified remaining R&D needs:  Life tests of X-band klystrons  Continued study of high gradient structures  Longer pulses length rf for klystrons, and DLDS studies  Positron production target lifetime and serviceability  Damping ring vacuum systems; chamber coatings to control e-cloud  Collimator materials and design  Optimization of IR design and detector interface  Instrumentation and controls

 Major effort will be industrialization; value engineering done by vendors. High volume components (modulators, klystrons) tested in stand-alone test stands.  Test component interfaces with NLCTA and GLCTA, expanded to 5-10 times number of sections as currently available (combined). Will include bunch compressor, full beam loading tests. About 1% of full LC. Upgraded NLCTA/GLCTA will be used to test interfaces of systems, integration and operations issues. Will also be used to support high-power processing of structures during initial industrialization phase.  Development of instrumentation for emittance control (BPMs, girder, quad movers etc.) will be tested at NLCTA/GLCTA and ASSET. Final demonstration of control of emittance growth requires a linac of about 50 GeV; this much of X-band LC would be available 1-2 years before LC completion.

DLDS offers 15% improvement of power efficiency over SLED II; operation at longer pulse time (  s) allows 14% improvement of modulator efficiency; longer pulses allows reduction of number of klystrons by factor 2 and reduction in number of modulators, low level rf R&D required includes demonstration that higher stored energy can be managed (can do with SLED II systems); Tests at 600MW (can do with SLED II; have run briefly at 580 MW; need time after solidifying baseline SLED II) Demonstrate that rf power sources can operate at 3.2  s R&D plan: 1.Verify baseline with SLED II; high power tests of SLED II 2.Test klystrons and modulators at 3.2 ms as they can find time 3.Potential demonstration DLDS system at NLCTA/GLCTA : decide if DLDS or SLED II

NLC estimates 111M$ for materials and supplies for , including costs of systems engineering (20M$). Manpower estimate – 782 FTE units (1800 hrs=1 working year). Further costs after site selection estimated to be 145M$ and 527 FTE units. GLC estimates 88 Oku ¥ for (80M$) including systems engineering and khrs manpower (370 FTE units). Added cost after site selection is 27.5 Oku ¥ (25M$) and 222 khrs manpower (123 FTE units). GLC estimates did not include NLCTA upgrade. Neither includes contingency, operations costs for test facilities, bid to host costs.

What remains according to TRC (2003)? R1: validate 65 MV/m structures with design detuning, irises (claim satisfied) ‡ R1: demonstrate full power full length pulse klystron/SLED-II operation (claim satisfied) ‡ R2: full test of PPM klystron at Hz and develop alternate prototype ‡ R2: test klystron with IGBT modulator at full specs. ‡ ‡ = noted in X-band response

My comments on X-band:  Although studies and tests of the method for controlling wakefields and emittance growth in X-band have been done, the small tolerances and centering techniques required suggest that further R&D with expanded sets of test structures will be needed.  Positron target needs more R&D  Extraction losses are too high, background mitigation at IR requires more study

TRC R&D issues – common to both technologies: R2: simulation of damping ring electron cloud suppression R2: fast ion instability studies R2: damping ring kicker stability (10 -3 needed) R2: simulations of emittance growth in DRs R2: static tuning studies for full low emittance transport sections R2: beam instrumentation; intra-train luminosity, laser-wire profile detector, etc. R2: prototype of main linac girder/cryomodule mechanical; vibration studies R2: subsystem reliability study to verify needed redundancy/ MTBF’s R2: beam based tuning demonstration for magnet, structure alignment in realistic operation.

My comments on common issues:  R&D on undulator positron source needed  Electron cloud effects are still worrisome, and more R&D will be needed to be sure these do not limit emittance.  Final doublet stabilization scheme needs study  Damping ring impedence budget must be verified  Collimator wakefield studies  Availability analysis – MTBF/MTTR  Study of failure modes and machine protection system needs work

Comments: 1.To date, there has been more attention to R&D on those features of a design that distinguish warm from cold than on the common problems. This is less true for X-band where more work on alignment, reliability, low level rf etc. seems to have been done. 2.Since the design will be re-evaluated by GDI after technology choice, there will be some added R&D to verify modified designs, thus lengthening the R&D phase and adding some cost. 3.Site specific issues will force some additional R&D once site is selected. 4.System and value engineering and reliability analysis will be a major theme up until start of construction; warm and cold need this equally. Budget for X-band R&D included this; L-band had less. If R&D does not converge rapidly, industrialization costs will escalate. 5.Costs of R&D effort for next three years looks comparable; excluding system engineering/industrialization, estimate materials and supplies funds of 64 M€ (77M$) [TESLA], 91M$ [NLC], 81 Oku¥ (74M$) [GLC] in three regional estimates. GLC and TESLA estimate has less for systems engineering (~$10M) than NLC (~$20M).

Comments: 6.The R&D effort in the coming years will focus increasingly on  industrialization,  reliability of components,  tests for many specific, ‘non-headline’ components (kickers, vacuum systems, mechanical supports, beam instrumentation etc. etc.),  full simulations of full LC emittance growth, electron cloud effects,  IR instrumentation,  Fault analysis and machine protection etc. The breadth of these activities, and the interplay between this R&D and LC design, will make it difficult for the R&D phase to be completed in the three years envisioned. 7.It is hard to distinguish between the remaining R&D costs for warm or cold machine. 8.Both technologies retain risks that require further R&D

Evaluation: A great deal of R&D is needed to provide a truly integrated overall LC design, for either technology. It will be a big challenge to complete the final design and this R&D in a timely fashion. This R&D will be conducted under a new organizational structure that will struggle to become efficient rapidly. Since much of the remaining R&D concerns issues other than SC rf, structure breakdown, klystrons etc. that make the primary differences between machines, it is likely that the remaining R&D time is comparable for the two machines. X-band has studied a fuller range of issues than SC; some of this work (IRs, bunch compressors, reliability and availability, sources, BPMs etc) could however be transferred to cold if chosen. R&D costs for the two technologies are comparable; both have probably underestimated the time needed for R&D and thus total R&D cost.  I do not see that the R&D needs distinguish significantly between the cold and warm LC choices.