Thailand NUCLEAR POWER PROGRAM INFRASTRUCTURE AND STATUS OF IMPLEMENTATION: Regulatory Body Prof. Dr. Chaivat TOSKULKAO Secretary General Office of Atoms.

Slides:



Advertisements
Similar presentations
UNRESTRICTED Infrastructure Assessment as Viewed by Technology Holders IAEA Technical Meeting December 10-12, 2008 R. Godden.
Advertisements

EGYPT NATIONAL STRATEGY FOR NUCLEAR POWER PROGRAME INFRASTRUCTURE AND STATUS OF IMPLEMENTATION “General Information on the Status of the Egyptian Nuclear.
History of Nuclear Safety Legislation in Pakistan
School for drafting regulations Nuclear Safety Decommissioning Vienna, 2-7 December 2012 Tea Bilic Zabric.
INSAG DEVELOPMENT OF A DOCUMENT ON HIGH LEVEL SAFETY RECOMMENDATIONS FOR NUCLEAR POWER Milestone Issues: Group C. Nuclear Safety. A. Alonso (INSAG Member)
Regulatory Body MODIFIED Day 8 – Lecture 3.
Nuclear program of Lithuania Dr. Vidas Paulikas, Radiation Protection Department VATESI Visaginas, 29 June 2009.
IAEA International Atomic Energy Agency Human Resources Development for Nuclear Safety J. Bastos NSNI/RAS.
Technical Meeting on Evaluation Methodology for Nuclear Power Infrastructure Development December, 2008 Nuclear Safety in Infrastructure Building.
IAEA International Atomic Energy Agency How do you know how far you have got? How much you still have to do? Are we nearly there yet? What – Who – When.
Status of Thailand’s Nuclear Program
IAEA International Atomic Energy Agency Overview of legal framework Regional Workshop - School for Drafting Regulations 3-14 November 2014 Abdelmadjid.
RER/9/096 Regional Planning Meeting “Strengthening National Infrastructures for the Control of Radiation Sources” (TSA-1), (Phase II) Country: Kazakhstan.
LEGAL FRAMEWORK & REGULATORY SYSTEM f or introduction of NPP into Vietnam Le Chi Dung (VARANS, Vietnam) Vienna, December 2008.
Tom MAZOUR IAEA, Division of Nuclear Power
08 October 2015 M. Ammar Mehdi Introduction to Human Resource Management & SSG-16 Actions 4 th Steering Committee on Competence of Human.
IAEA Technical Meeting/Workshop on Topical Issues on Infrastructure Development 9-12 February 2010 Mr. Chavalit Pichalai, Deputy Director Nuclear Power.
RER/9/096 Regional Planning Meeting “Strengthening National Infrastructures for the Control of Radiation Sources” (TSA-1), (Phase II) Republic of Moldova.
GROUP 3:Bangladesh, Croatia, Egypt, Jordan, Montenegro, Namibia, Senegal, Syria, Vietnam and Yemen Moderator: Dr. I. Rotaru, IAEA consultant Reporter:
Human Resources Development for Sudan Nuclear Power Programme Presented by Prof. F.I.Habbani Technical Committee For Sudan NPP Ministry of Energy and Mining.
WELCOME MEETING China Guangdong Nuclear Power Holding Co., Ltd. (CGNPC) and CLP Group Tuesday, 5 August 2008 Thailand Institute of Nuclear Technology (TINT)
1 ESTABLISHMENT OF REQUIREMENTS Module “National legislation and licensing” Project BG/04/B/F/PP , Program “Leonardo da Vinci”
RER/9/096 Regional Planning Meeting “Strengthening National Infrastructures for the Control of Radiation Sources” (TSA-1), (Phase II) Country: Bulgaria.
SÄTEILYTURVAKESKUS STRÅLSÄKERHETSCENTRALEN RADIATION AND NUCLEAR SAFETY AUTHORITY Key outcomes of IRRS Mission in Finland Kirsi Alm-Lytz.
TM/WS 9-12 February GROUP 3: Bangladesh, Croatia, Egypt, Jordan, Montenegro, Namibia, Senegal, Syria, Vietnam and Yemen Moderator: Dr. I. Rotaru,
IAEA International Atomic Energy Agency. IAEA Outline Learning Objectives Introduction IRRS review of regulations and guides Relevant safety standards.
Thailand’s Preparation for Starting a Nuclear Power Program Mr. Pricha Karasuddhi Technical Advisor Nuclear Power Program Development Office(NPPDO) Ministry.
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Regulatory Authority.
Maria J Moracho Ramirez Regulatory Activities Section
IAEA International Atomic Energy Agency School of Drafting Regulations – November 2014 Government and Regulatory Body Functions and Responsibilities IAEA.
Technical Meeting on Milestones for nuclear power infrastructure development Radiation Protection Khammar Mrabit Head, Regulatory Infrastructure and Transport.
Algerian nuclear power programme Status, needs and perspectives T/M on development of nuclear infrastructure of NP programme February, ,Vienna.
LEGAL and REGULATORY FRAMEWORK for NUCLEAR and RADIATION SAFETY in BULGARIA General overview Dr. M. Mateeva – Chief Inspector R. Markova-Mihaylova – Chief.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
IAEA International Atomic Energy Agency RER2006 RTC Establishing a Nuclear Safety Infrastructure for a National Nuclear Power Programme Wrap up, Where.
RER/9/096 Regional Planning Meeting “Strengthening National Infrastructures for the Control of Radiation Sources” (TSA-1), (Phase II) Country: Kyrgyz Republic.
4rd Meeting of the Steering Committee on Competence of Human Resources for Regulatory Bodies Vienna, 4-7 December 2012 Current Status of the Human Resources.
RER/9/096 Regional Planning Meeting “Strengthening National Infrastructures for the Control of Radiation Sources” (TSA-1), (Phase II) Country: ROMANIA.
International Atomic Energy Agency School for Drafting Regulations on Radiation Safety RER/9/096 Vienna, 3 May, 2010 Adriana Nicic, Regulatory Activities.
INDONESIA NATIONAL STRATEGY FOR NUCLEAR POWER PROGRAMME INFRASTRUCTURE AND STATUS OF IMPLEMENTATION Dr. A. Sarwiyana Sastratenaya Director, Center for.
Current Status of the National Nuclear Infrastructure and Human Resources Development in the Republic of Belarus TM/WS on Topical Issues on Infrastructure.
JORDAN ATOMIC ENERGY COMMISSION (JAEC) Building of National Safeguards Capabilities in Jordan IAEA’s Technical Meeting/Workshop on National Infrastructure.
Milestones for Nuclear Power Infrastructure Development Establishment of A Regulatory Framework Gustavo Caruso, Section Head, Regulatory Activities Section.
Role of Self-Assessment V.C. Agarwal, Director (HR) NPCIL,INDIA.
DEVELOPMENT OF THE NATIONAL INFRASTRUCTURE FOR NUCLEAR POWER IN VIETNAM DEVELOPMENT OF THE NATIONAL INFRASTRUCTURE FOR NUCLEAR POWER IN VIETNAM Vuong Huu.
IAEA International Atomic Energy Agency Arusha, Tanzania Uganda Dr. Akisophel Kisolo Project Counterpart 2 – 5 December 2013 RAF9038 Final Coordination.
Leading State Inspector Ivan Rovkach Department of Nuclear and Radiation Safety Ministry of Emergency Situations of the Republic of Belarus(GOSATOMNADZOR)
The Egyptian Nuclear & Radiological Regulatory Authority (ENRRA)
International Atomic Energy Agency Workshop on Topical Issues on Infrastructure Development: Managing the Development of a National Infrastructure for.
PHILIPPINES Report: Policies and implementation strategies on HUMAN RESOURCE DEVELOPMENT to introduce NPPs Adopting RAIS 3.2 AS THE NATIONAL REGISTER OF.
Egyptian Nuclear and Radiological Regulatory Authority (ENRRA)
Government Reform in Taiwan
János Krutzler Hungarian Atomic Energy Authority
Office of Legal Affairs
THAILAND Training and Tutoring Feedback
SESSION 3 Policy Framework
MALAYSIA Training and Tutoring Feedback
Nuclear and Treaty Law Section Office of Legal Affairs
Republican Unitary Enterprise “Belarusian Nuclear Power Plant”
Establishing the Infrastructure for Radiation Safety Preparatory Actions and Initial Regulatory Activities.
“LEGISLATIVE AND REGULATORY FRAMEWORK IN PAKISTAN” Application Set
Regulatory Control Training Workshop
Armenia Training and Tutoring Feedback
Nuclear Power in Jordan
Arab Network for Nuclear Regulators ANNuR Abdelmajid Mahjoub Daw Mosbah Arab Atomic Energy Agency Tunis
Legal and Regulatory Framework for Nuclear Installations in IRAN
Mostafa El-Asiry Nuclear Power Plants Authority (NPPA), Cairo, Egypt
بسم الله الرحمن الرحيم Dr. Hany Sallam & Regulatory Activities
Nuclear Energy Programme Implementing Organisation
Regulatory system in Hungary
Presentation transcript:

Thailand NUCLEAR POWER PROGRAM INFRASTRUCTURE AND STATUS OF IMPLEMENTATION: Regulatory Body Prof. Dr. Chaivat TOSKULKAO Secretary General Office of Atoms For Peace International Atomic Energy Agency TM/WS on Topical Issues on Infrastructure Development: Managing the Development of a National Infrastructure for Nuclear Power 9-12 February 2010, Vienna, Austria

Contents The Regulatory work to “support” the Nuclear Power Project in Thailand: 1) Revising Atomic Energy for Peace Act 2) Strengthening staff capability 3) Public awareness

The Infrastructure of Nuclear Regulatory Body in Thailand 14 Sub-Committees (Reactor Safety Subcom.) Ministry of Science & Technology (MOST) Office of Atoms for Peace (OAP) (Secretariat of Thai-AEC) Thai Atomic Energy Commission (Thai-AEC)

Main Responsibilities of OAP Main Responsibilities of OAP Establish rules, regulations and measure for the control and regulation of the use of nuclear energy and waste management. To control and regulate the safety of radiation and nuclear facilities. Control functions (inspections) in general are performed through competent officials appointed by the Minister who takes charge and control of the execution of the Act. Cooperate for nuclear affairs and foreign relations.

Present Framework to Support NPP Prime Minister Ministry of Science and Technology National Energy Policy Committee Ministry of Energy Thai AEC (NPP Regulator) Energy Policy and Planning Office Thailand Institute of Nuclear Technology (Research Reactor) Office of Atoms for Peace Nuclear Power Infrastructure Establishment Coordination Committee Nuclear Power Program Development Office Electricity Generating Authority of Thailand (NPP Operator) Reactor Safety Sub Committee

Goal to catch up milestone 1 (NPP Regulator/OAP) Build up safety culture at each level within organization. Define competence needed to carry out regulatory activities. Provide training for regulatory staff (in-house, abroad and O-J-T) as necessary including studying abroad. Develop HRD plan to cover all areas throughout the lifetime of the NPP.

Legislation and Regulatory Framework Effectively independent regulatory body is established, in addition, “OAP” is regarded as SSAC Drafting new nuclear law: Atomic Energy for Peace Act#3 –To set up new set of nuclear law, regulations, rules, standards and guidelines to comply with international good practice Existing law: –Amendment to cover some issues: authorization process, liability, security and conventions –Drafting safety requirements, criteria and guidelines for each authorization stage –Cooperation with DOE in implementation of Additional Protocol

Draft of Atomic Energy for Peace Act #3 New definition for technical term: radiation/radioactive and nuclear materials etc. Exemption limit Composition of Thai Atomic Energy Commission and clarification of the responsibility of the commission (not to set policy on nuclear energy to produce electricity) Delegation of authorization power to OAP (but not RRx. or NPP) Enforcement ………………………………… AEPA #1 in 1961 #2 in 1965

Draft of Atomic Energy for Peace Act # 3 (cont’d) Licensing process: cover all permitting process –Site permit, construction permit, commissioning permit and decommissioning permit –License fee Empower the Board: –Nuclear reactor –Source material, special nuclear material, radiation sources/generator –Nuclear waste management –Set up national plan for nuclear/radiation emergency preparedness and response …………………………………………… AEPA #1 in 1961; #2 in 1965

Draft of Atomic Energy for Peace Act # 3 (cont’d) Introduce concept in –Nuclear safety and security –Action against terrorism and unauthorized used of radioactive/nuclear materials –Safeguards –Compensation for nuclear damage (insurance and set up fund for compensation) ………………………………… AEPA # 1 in 1961 # 2 in 1965

Safety criteria Set up the Rule and Criteria for NPP regulation: Evaluate the Safety Analysis Report Site evaluation Nuclear safety Radiation Protection Safeguards control Emergency preparedness program EIA (specific for radiation impact) Nuclear fuel cycle Spent fuel and waste management Safety management system in NPP Decommissioning plan Safe operation and control Training course for operator and operator license etc.

Human Resources Development of RB Short term development: –competence analysis and implementation of SAT –In house training –Training under IAEA/ANSN/TA/co-operation Long term development: –Scholarship/Fellowship to study abroad –On the job training

Implementation of SAT 2009 In house training: Regulatory control Law and regulation Safety assessment Site evaluation and licensing process (phase I) Ageing determination and management Quality management for regulatory body 2010 In house training: Site evaluation and licensing process (phase II) Quality management (phase II) Basic professional training course Development of safety assessment tool and system for research reactor Studying abroad: - Nuclear Safety Schools (Korea, etc.)

Conclusion 1.Regulatory document and framework are being “revised” which include Authorization process Review process Inspection and enforcement Development of regulations and guidelines 2. Plan for increasing staff capability is partially implemented. 3. Public concern must be taking into account and clear information must be provide consistently. 4. Assistance are needed in various fields for first establishment of NPP. 5. Education and Industrial framework related to NPP technology need to be improved.

Thank you Thank you for your attention for your attention

Office of Atoms For Peace (OAP) Office of the Secretariat Information Technology Center Engineering Center Bureau of Nuclear Safety Regulation Bureau of Atomic Energy Administration Bureau of Technical Support for Safety Regulation Bureau of Radiation Safety Regulation Organization Technical Administrative Group

1)International Law (Nuclear Law) 8 persons 2)Nuclear Engineer 30 persons 3)Civil Engineer 6 persons 4)Electrical Engineer 8 persons 5)Mechanical Engineer 6 persons 6)Industrial Engineer 6 persons 7)Environmental Engineer 6 persons 8)Chemist/Physicist/Geologist/ Scientist 14 persons …………………………………………………………… Administrative person HR Development of RB in : persons/NPP 1000 MW (IAEA)

GO NUCLEAR Policy Decision Milestone 0.1 (Nuclear power option included in PDP 2007) Milestone 0.2 (To prepare for policy decision) Phase 0.1: Preliminary Phase - NPIPC & 5 SCs appointed - Issues & Milestones considered - NPIEP prepared Phase 1 : Pre-project Activity Phase - approve NPIPC - set up NPPDO - infrastructure work started - survey of potential sites - feasibility study completed - public information & participation Phase 2 : Program Implementation Phase - implement NPIEP Milestones - full NRB established - legislation & international protocols enacted - suitable sites for bid selected - technology /qualified suppliers selected Phase 3 : Construction Phase - NPIEP fully implemented - biding process completed - design & engineering - manufacturing - construction & installation - test runs & inspection - NPP commissioning license Phase 4 :Operation Phase - commercial operation - O & M - planning for expansion - industrial and technology development plan st Milestone Policy Decision (Knowledgeable Commitment) 2nd Milestone Call for Bids (Financial Commitments) 3rd Milestone Start Operation (Commissioning 1st NPP) NPIEP Milestones for Nuclear Power Program Implementation NPI : Nuclear Power Infrastructure NPIEP : NPI Establishment Plan NPPDO : Nuclear Power Program Development Office NPP : Nuclear Power Plan NRB : Nuclear Regulatory Body 24 September Year National Strategy and Strategic Plans for the Development of Infrastructure for Nuclear Power 3 Years Years