J. Large Binocular Telescope (LBT) Operational Readiness

Slides:



Advertisements
Similar presentations
Subaru AO in future. Outline Overview of AO systems at Mauna Kea and in the world. Ongoing plan of AOS at Subaru and Mauna Kea. What’s in future.
Advertisements

GSMT Control Workshop Tucson, September 11-12, 2001 Pointing Control for a giant segmented mirror telescope Patrick Wallace Rutherford Appleton Laboratory.
1 Keck LGS AO Planning Workshop: Overview, Requirements & Schedule December 5, 2004.
RASC, Victoria, 1/08/06 The Future of Adaptive Optics Instrumentation David Andersen HIA.
“Riding the Hub”: The MMT Adaptive Secondary Douglas Miller University of Arizona The AO System Current Performance of the MMT AO System Ongoing Development.
LBT AO Progress Meeting, Arcetri Walter Seifert (ZAH, LSW) The LBT AO System and LUCIFER 1.Requirements for the commissioning of LUCIFER:
The Project Office Perspective Antonin Bouchez 1GMT AO Workshop, Canberra Nov
AO188/LGS status AO188 development group(Subaru Telescope, NAOJ) (JST)
PILOT: Pathfinder for an International Large Optical Telescope -performance specifications JACARA Science Meeting PILOT Friday March 26 Anglo Australian.
System-wide issues Before we get to the telescope System integration and verification at the telescope Operations Maintenance and support.
MMT AO run Jan Timeline: –Night 1: Install hardware during MMT engineering –Nights 2-4: AO engineering with fast-framing H camera (Indigo) –Nights.
A Short Presentation of Ongoing AO Work at Lund Observatory Mette Owner-Petersen Lund Observatory Workshop for “Forskarskolen i Rymdteknik” Gothenburg.
PALM-3000 Instruments update A. Bouchez Team Meeting #9 22 Oct
NGAO Status R. Dekany January 31, Next Generation AO at Keck Nearing completion of 18 months System Design phase –Science requirements and initial.
Keck Laser Guide Star Adaptive Optics System: 1 st & 2 nd Milestones AOWG Telecon Oct. 17, 2003 A. Bouchez, J. Chin, A. Contos, S. Hartman, E. Johansson,
PALM-3000 Systems Engineering R. Dekany, A. Bouchez 9/22/10 Integration & Testing Review.
WMKO Next Generation Adaptive Optics: Build to Cost Concept Review Peter Wizinowich et al. December 2, 2008 DRAFT.
1 NGAO Science Instrument Reuse Part 1: NIRC2 NGAO IWG December 12, 2006.
Imaging Planets in the Thermal Infrared Phil Hinz University of Arizona Outline: Observations of HR 8799 and Fomalhaut Survey of FGK stars in the thermal.
Release & Deployment ITIL Version 3
1 HST Status Cycle 14 TAC/Panels 14 March Telescope and Instrument Status Telescope and support systems are all working well – no unexpected limitations.
I. Plan to Meet PLRA Threshold Requirements Phil Hinz Principal Investigator.
LBTI ORR Pre-Briefing to the Board April 14,
C. Executive Summary Phil Hinz Principal Investigator.
LBT672 opto-electro-mechanical specification overview Presented by A. Riccardi A. Riccardi, G. Brusa, R. Biasi, D. Gallieni FLAO system external review,
Exoplanet Exploration Program Large Binocular Telescope Interferometer (LBTI) Operational Readiness Review (ORR) PI: Phil Hinz, UA PS: Rafael Millan-Gabet,
1 FRIDA Engineering Status 17/05/07 Engineering Status May 17, 2007 F.J. Fuentes InFraRed Imager and Dissector for Adaptive Optics.
FLAO commissioning with InfraRed Test Camera (IRTC) S. Esposito, G. Brusa, A. Riccardi FLAO system external review, Florence, 30/31 March 2009.
AO4ELT - Paris Giant Magellan Telescope Project Science Drivers & AO Requirements Patrick McCarthy - GMT Director Phil Hinz & Michael Hart - GMT.
Telescope Technologies
LBTI HOSTS Science Operations Plan Draft 0 – Feb
Viewing the Universe through distorted lenses: Adaptive optics in astronomy Steven Beckwith Space Telescope Science Institute & JHU.
AO review meeting, Florence, November FLAO operating Modes Presented by: S. Esposito Osservatorio Astrofisico di Arcetri / INAF.
Characterization and Upgrading of Adaptive Optics Demonstrator Joseph Curamen Maui Community College Mark Hoffman & Mark Ammons MCC & UCSC-CfAO.
L. NExScI Operational Readiness Rafael Millan-Gabet Project Scientist, NExScI & Mihseh Kong, NExScI Software Engineer David Imel, IPAC & NExScI Manager.
FLAO system test plan in solar tower S. Esposito, G. Brusa, L. Busoni FLAO system external review, Florence, 30/31 March 2009.
1 1 st Light AO 4 LBT Pyramid WFS Adaptive Secondary MMT Unit.
B. Review Board Charter and ORR Success Criteria Muthu Jeganathan Project Manager, JPL.
LBTI Program Management Review Phil Hinz S.H. (Hop) Bailey 2 December
LBT Q Eng/SW Review IIF – Instrument Interface Jose Borelli.
ASTR 3010 Lecture 18 Textbook N/A
Strehl Ratio estimation. SR from H band images High Strehl PSF ->fitting with Zernike modes We suppose: No relevant loss of energy due to high modes (Z>36)
AO188/LGS Status and Schedule 1 Yutaka Hayano January 31, 2008.
Status report of AO188+LGS (+future AO) Yutaka Hayano (Subaru Telescope, NAOJ) S. Oya, M. Hattori, Y. Saito, Y. Minowa, M. Ito, H. Terada, T.S. Pyo, H.
Ground Layer AO at ESO’s VLT Claire Max Interim Director UC Observatories September 14, 2014.
N. Summary Phil Hinz Principal Investigator. Performance N-2.
Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.
F. LBTI Current Performance and Compliance with ORR Entrance Criteria Phil Hinz Principal Investigator.
D. Measurement Approach Phil Hinz Principal Investigator.
FLAO_01: FLAO system baseline & goal performance F. Quirós-Pacheco, L. Busoni FLAO system external review, Florence, 30/31 March 2009.
LBT Q Eng/SW Review MCSC – Mount Control System.
March 31, 2000SPIE CONFERENCE 4007, MUNICH1 Principles, Performance and Limitations of Multi-conjugate Adaptive Optics F.Rigaut 1, B.Ellerbroek 1 and R.Flicker.
LBTI Program Management Review Phil Hinz S.H. (Hop) Bailey 9 July
Some Thoughts on Ground Layer Adaptive Optics & Adaptive Secondary Mirrors for Keck P. Wizinowich 9/15/14 1.
LBT Q Eng/SW Review SFWG – Software Group Norm Cushing.
Keck Observatory Overview Peter Wizinowich W. M. Keck Observatory AOSC May 31, 2004.
Opening New Frontiers with the GMT, Seoul, October Giant Magellan Telescope How does an adaptive secondary mirror support the unique qualities of.
Why is the VLT very efficient? Fernando Comerón On behalf of Francesca Primas and Martino Romaniello.
Subaru GLAO Simulation
Robo-AO Overview: System, capabilities, performance Christoph Baranec (PI)
Requirements Management with Use Cases Module 2: Introduction to RMUC Requirements Management with Use Cases Module 2: Introduction to RMUC.
KECK INTERFEROMETER KISWG 10/29/20031 ORR Readiness Mark Colavita & Peter Wizinowich KISWG Pasadena 10/29/2003.
Date of download: 6/21/2016 Copyright © 2016 SPIE. All rights reserved. AO corrected average Strehl ratios at different field positions and Sun elevations.
Page 1 Lecture 16 Extreme Adaptive Optics: Exoplanets and Protoplanetary Disks Claire Max AY 289 March 7, 2016 Based in part on slides from Bruce Macintosh.
LBT Q Eng/SW Review ALPC – Primary Mirror Aluminum Shooting.
Keck Observatory Status
Pyramid sensors for AO and co-phasing
Software and Systems Integration
Adaptive optics Now: Soon: High angular resolution
Laser(s) for Keck Observatory’s Next Generation AO (NGAO) System
Presentation transcript:

J. Large Binocular Telescope (LBT) Operational Readiness Christian Veillet Director, LBT

LBT Compliance This presentation discusses LBTO readiness Relationship to ORR Success Criteria: LBTO plans and procedures are complete and under configuration management; LBTO staffing is in place and trained; LBTO risks are documented and acceptable Concerns: None Liens: None 3. The necessary interferometer operations plans and procedures are complete, documented and in place, and under configuration management Green 5. The necessary staffing is in place and training has taken place 6. Project risks are documented and acceptable

LBT Is Ready to Support LBTI HOSTS Survey All LBT systems have been functioning during LBTI commissioning block Addressed maintenance issues with adaptive optics without impact to LBTI commissioning Worked systems-level issues with LBTI to completion Added engineering nights prior to LBTI runs to demonstrate readiness with margin for corrective action LBT has demonstrated it is ready to support LBTI HOSTS Survey

LBTO Provides (1/2) Power, data communications LBT Instruments LBTI DX SX FLAO/LUCI Power, data communications Telescope and AO command and control

LBTO Provides (2/2) Nighttime telescope operation Prerun checkouts Telescope and AO systems System maintenance Adaptive secondaries and associated AO systems Observing scheduling LBTI run to best fit LBTI HOSTS strategy Systems engineering support to LBTI for vibration suppression Accelerometer system (OVMS)

PLRA LBT Performance Expectation Performance envelope consistent with LBT specifications Adaptive optics performance Strehl ratio >60% at K-band Diffraction-limited at 2 µm wavelength

LBT Seeing Meets LBTI Requirements DIMM seeing measurements for 2014 DIMM is mounted on telescope structure Looks at bright star near target Measures dome and atmosphere seeing Small FWHM limit ~0.5 due to instrument design <r0> ~12 cm (550 nm) ALTA Program for seeing prediction in Q-mode AO operational limit Note: DIMM values blah blah…

Weather Impact on Observing Nights Weather: A-semesters (Feb–Jul) better and more predictable than B-semesters (Sep–Jan)

Adaptive Secondaries SX and DX Key to LBTO operation: Heavily used by the whole partnership with LBTI beyond the HOSTS program Needed for the LUCIs (near-IR imagers/multiobject spectrographs) in GLAO (ARGOS) and AO mode Very important for the smooth operation of the observatory once in Q-mode ARGOS on-off LUCI2-AO – S ~ 75% at K

LBTI AO Imaging Capabilities Good conditions, bright guide stars 990 Hz, DX = 400 modes, SX= 300 modes Maire et al. (2015) Maire et al 2015 present (Some of) the highest contrast L’ data obtained to date. Exceptional sensitivity at small separations is due to high Strehl ratio and PSF stability. On bright stars in good conditions, we can work at 400 spatial modes on DX and 300 on SX. At elevations below 50-60dgr (depending on the seeing) DX is limited to 300 modes. HR 8799 Exoplanet System LEECH Program

LBTI AO Stability Strehl ratio PSF stability during observation set ≥85% at L′ (4 μm) ≥98% at 10 μm PSF stability during observation set For nulling, corrected PSF stability throughout a sequence matters as much as Strehl ratio Each PSF is stable to 50–100 nm Average long-term, low-order wavefront error ≤1E-4 null stability at 10 μm Noncommon-path aberration Improves SR Currently being applied for LUCI2 Analysis in progress for LBTI “Stability” = how much does the PSF change of the course of an observation set as noncommon-path aberrations change? Causes may include flexure with elevation, long-term thermal drift in components. As we improve the non-common path mitigation, this should improve. Strehl ratio should also improve with NCPA, but absolute SR is less important for nulling than the relative stability of the PSFs *relative to each other.*

Adaptive Secondaries SX & DX adaptive secondary mirrors are required for LBTI HOSTS Survey and all other programs ASMs are used for both seeing-limited and AO-corrected observing Monitoring and maintenance The ASMs are designed to be functional when missing some voice coil actuator/magnet control LBT monitors the ASM health to establish maintenance and refurbishment requirements and schedule accordingly Current refurbishment Recoating of the spare thin-shell (the optical component of the ASM) Rebonding detached magnets onto the SX ASM thin shell and system testing

AO Systems Future Plans ASM contacts Program to upgrade the electrical contacts onto the thin shell to improve reliability and robustness of ASMs LBT operation with technical feedback from JPL Maintain a fully operational spare thin shell to be swapped in either SX or DX side when necessary SOUL upgrade All pyramid WFS (PWFS) systems will be upgraded with more sensitive detectors Expect sensitivity gain of 1–2 mags Both FLAO & LBTI systems will have the same hardware and software After upgrade is complete, the LBTI PWFS will be handed over to LBT for operation and maintenance Expected completion ~2017/2018—no impact on SVP

LBT Is Ready to HOSTS