3 Project Management PowerPoint presentation to accompany

Slides:



Advertisements
Similar presentations
3 Project Management PowerPoint presentation to accompany
Advertisements

WBS: Lowest level OBS: Lowest level
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
1 Project Scheduling CP - Chapter 10 Lecture 3. 2 Project Management  How is it different?  Limited time frame  Narrow focus, specific objectives 
© 2006 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management Chapter 3 – Project Management © 2006 Prentice Hall, Inc. PowerPoint.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
MGMT 483 Week 8 Scheduling.
Chapter 3 (Continued) Outline Recap CPM (continued)  Assign time estimates to each activity  Compute the longest time path through the network.
Project Management Chapter 13
PROJECT MANAGEMENT (N MBA 034)
6. Project Management.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Management Techniques.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations.
Operations Management
Project Management. Introduction What – Project Management Where – Where the success or failure of a project will have major consequences for the company.
Operations Management
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc.,
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations.
Roberta Russell & Bernard W. Taylor, III
To accompany Quantitative Analysis for Management, 8e by Render/Stair/Hanna 13-1 © 2003 by Prentice Hall, Inc. Upper Saddle River, NJ Chapter 13.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Lean Project Management
3 - 1© 2011 Pearson Education 3 3 Managing Projects PowerPoint presentation to accompany Heizer and Render Operations Management, 10e, Global Edition Principles.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall  Complex and temporary task of many related activities. (not ‘business as usual’)  May.
1 Project Management Seminar Project Scheduling. 2 Importance of Project Management Three Components of Project Management Project Evaluation and Review.
3 Project Management PowerPoint presentation to accompany
WEEK 4 Introduction to Project Management. Agenda Phase 2: Planning ◦ Communication Plan ◦ Scheduling Preparation  Build an AON Diagram  Determine Critical.
© 2006 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management Chapter 3 – Project Management © 2006 Prentice Hall, Inc. PowerPoint.
Strategic Importance of Project Management
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Project Management Techniques
To accompany Quantitative Analysis for Management, 7e by Render/Stair 13-1 © 2000 by Prentice Hall, Inc., Upper Saddle River, N.J Quantitative Analysis.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
1 OMGT 3123 Project Management  Project Controlling  Project Management Techniques: PERT And CPM  The Framework Of PERT And CPM  Network Diagrams And.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
OPSM 301 Operations Management Class 18: Project Management: Introduction and CPM Koç University Zeynep Aksin
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
© 2006 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management Chapter 3 – Project Management © 2006 Prentice Hall, Inc. PowerPoint.
Operations Management Project Management Chapter 3.
Prepared by Raida Al-Awamleh 1 Project Management Training Program June 24 th -28 th,2006.
© 2007 Pearson Education Project Management. © 2007 Pearson Education Bechtel Group, INC.  Bechtel is a $16.3 billion-a-year construction contractor.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations.
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Project Management Project Controlling
PROJECT MANAGEMENT.
Project Management: PERT/CPM
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Operations Management
Project Scheduling Network Optimization can be used as an aid in the scheduling of large complex projects that consist of many activities A project is.
Project Planning and Budgeting
3 Project Management PowerPoint presentation to accompany
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Project Management CPM/PERT Professor Ahmadi.
3 Project Management PowerPoint presentation to accompany
Critical Path Method and Assignments for COLL
Presentation transcript:

3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, Eleventh Edition Principles of Operations Management, Ninth Edition PowerPoint slides by Jeff Heyl © 2014 Pearson Education, Inc.

Outline The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Techniques: PERT A Critique of PERT

MANAGEMENT OF PROJECTS

Importance of Project Management Project: unique, one-time operations designed to accomplish a set of objectives in a limited time frame. Building Construction Research Project

Importance of Project Management Planning - goal setting, defining the project, team organization Scheduling - relate people, money, and supplies to specific activities and activities to each other Controlling - monitor resources, costs, quality, and budgets; revise plans and shift resources to meet time and cost demands Planning Scheduling Controlling

Project Planning Establishing objectives Defining project Creating work breakdown structure Determining resources Forming organization

Project Planning Project Organization Often temporary structure Uses specialists from entire company Headed by project manager Coordinates activities Monitors schedule and costs Permanent structure called ‘matrix organization’

Project Planning A Sample Project Organization Project No. 1 Marketing Finance Human Resources Design Quality Mgt Production President Test Engineer Mechanical Project No. 1 Project Manager Technician Technician Project No. 2 Project Manager Electrical Engineer Computer Engineer Figure 3.2

Project Planning Matrix Organization Marketing Operations Engineering Finance Project 1 Project 2 Project 3 Project 4

Project Planning The Role of Project Manager: All necessary activities are finished in order and on time The project comes in within budget The project meets quality goals The people assigned to the project receive motivation, direction, and information

Project Planning The Role of Project Manager: All necessary activities are finished in order and on time The project comes in within budget The project meets quality goals The people assigned to the project receive motivation, direction, and information Project managers should be: Good coaches Good communicators Able to organize activities from a variety of disciplines

Project Planning Work Breakdown Structure Dividing a project into more and more detailed tasks (or activities) Level 1. Project 2. Major tasks in the project 3. Subtasks in the major tasks 4. Activities (or “work packages”) to be completed

Work Breakdown Structure Level 1 Develop Windows 8 Operating System 1.0 Level 2 Software Design Cost Management Plan System Testing 1.1 1.2 1.3 Level 3 Develop GUIs Design Cost Tracking Reports Module Testing Ensure Compatibility with Earlier Versions Develop Cost/Schedule Interface Defect Testing 1.1.1 1.2.2 1.3.2 1.3.1 1.2.1 1.1.2 Level 4 Compatible with Windows 7 Compatible with Windows Vista Compatible with Windows XP 1.1.2.3 1.1.2.2 1.1.2.1 (Work packages) Figure 3.3

Project Scheduling Shows the relationship of each activity to others and to the whole project Identifies the precedence relationships among activities Encourages the setting of realistic time and cost estimates for each activity Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project

Project Scheduling Techniques Gantt chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT)

A Simple Gantt Chart Project : establish a new department Activity Time Activity Sequence Project Duration

Project Controlling Close monitoring of resources, costs, quality, budgets Feedback enables revising the project plan and shift resources Computerized tools produce extensive reports

Project Management Software There are several popular packages for managing projects Primavera MacProject MindView HP Project Fast Track Microsoft Project © 2014 Pearson Education, Inc.

Project Control Reports Detailed cost breakdowns for each task Total program labor curves Cost distribution tables Functional cost and hour summaries Raw materials and expenditure forecasts Variance reports Time analysis reports Work status reports

PROJECT MGMT TECHNIQUES: PERT

PERT and CPM Network techniques Developed in 1950s CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958) Consider precedence relationships and interdependencies Each uses a different estimate of activity times

Six Steps PERT Define the project and prepare the work breakdown structure Develop relationships among the activities - decide which activities must precede and which must follow others Draw the network connecting all of the activities

Six Steps PERT Assign time and/or cost estimates to each activity Compute the longest time path through the network – this is called the critical path Use the network to help plan, schedule, monitor, and control the project

PERT: AON Convention Activity on Activity Node (AON) Meaning (a) A B C A comes before B, which comes before C (a) A B C 3.0 2.5 2.0 A and B must both be completed before C can start (b) A C B 3.0 2.5 2.0

PERT: AON Convention Activity on Activity Node (AON) Meaning (c) B A C B and C cannot begin until A is completed (c) B A C 3.0 2.5 2.0 C and D cannot begin until A and B have both been completed (d) A B C D 3.0 2.5 2.0 3.5

PERT: AON Convention Activity on Activity Node (AON) Meaning (e) A B C C cannot begin until both A and B are completed; D cannot begin until B is completed. (e) A B C D 3.0 2.5 2.0 3.5 B and C cannot begin until A is completed. D cannot begin until both B and C are completed. (f) A C D B 3.0 2.5 3.5 2.0

AON Example Example 3.1: Milwaukee has identified the eight activities that need to be performed in order to install air pollution control equipment in its facility. Activity Description Immediate Predecessors Estimated Time (weeks) A Build internal components — 2 B Modify roof and floor 3 C Construct collection stack D Pour concrete and install frame A, B 4 E Build high-temperature burner F Install pollution control system G Install air pollution device D, E 5 H Inspect and test F, G

Immediate Predecessors Estimated Time (weeks) Activity Immediate Predecessors Estimated Time (weeks) A — 2 B 3 C D A, B 4 E F G D, E 5 H F, G 4 3 2 5 C F H E A B Start D G

EX1 in class Estimated Time Immediate Task (weeks) predecessor Construct a PERT network for this project by using AON convention A 8 — B 6 A C 4 — D 9 C E 11 A F 3 B, E G 1 B, C, E H 5 D, F, G

PERT Important concepts Path: A sequence of activities leading from the beginning node to the ending node of a PERT network. Path length: The sum of the time estimates of the activities on a path. Critical path: The longest path in a PERT network. Critical activities: The activities on the critical path. Project duration (or completion time): The length of the critical path. Path slack: The difference between the length of a path and the project duration.

PERT Analysis Deterministic PERT Analysis Computational Algorithm

Deterministic PERT Analysis Enumeration method Calculate and compare the lengths of all paths Determine the critical path, critical activities, and the path slacks

Deterministic PERT Analysis Example 3.2: Do deterministic PERT analysis. Estimated Time Immediate Task (weeks) predecessor A 8 — B 6 A C 4 — D 9 C E 11 A F 3 B G 1 D, E, F G F B E D A C Start 9 4 6 11 1 8 3 Total 42

Deterministic PERT Analysis G F B E D A C Start 9 4 6 11 1 8 3 (1) What is the critical path? What are the critical activities? (2) What is the duration of the project? Are there any path slacks? If so, how long is each of the slacks? Critical Path Path Length (weeks) Slack Start – A – B – F – G 8+6+3+1=18 2 Start – A – E – G 8+11+1=20 Start – C – D – G 4+9+1=14 6 (1) The critical path is Start – A – E - G. The critical activities are A, E, G. (2) The duration of the project is 20 weeks. Path Start – A – B – F – G has a slack of 2 weeks, and path Start – C – D – G has a slack of 6 weeks.

Deterministic PERT Analysis The critical path is the longest path through the network The critical path is the shortest time in which the project can be completed Any delay in critical path activities delays the project Critical path activities have no slack time

Deterministic PERT Analysis Example 3.3 (1) What is the critical path? What are the critical activities? (2) What is the duration of the project? Are there any path slacks? If so, how long is each of the slacks? Path Length (weeks) Slack Critical Path Start – A – C – F – H 9 6 Start – A – C – E – G – H 15 0 Start – A – D – G – H 13 2 Start – B – D – G – H 14 1 (1) The critical path is Start – A – C – E – G – H. The critical activities are A, C, E, G, H. (2) The duration of the project is 15 weeks. (3) Path Start – A – C – F – H has a slack of 6 weeks, path Start – A – D – G – H has a slack of 2 weeks, and path Start – B – D – G – H has a slack of 1 week.

Immediate Predecessor(s) Estimated Time (weeks) EX2 in class Activity Immediate Predecessor(s) Estimated Time (weeks) J -- 10 K 8 L 6 M 3 N K, M 5 O 7 P L, N Draw the diagram by using the information above, and determine the project duration, critical activity and path slacks

PERT Computational Algorithm Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors have been completed Earliest finish (EF) = earliest time at which an activity can be finished Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project ES EF LS LF

PERT: Forward Pass Begin at starting event and work forward Earliest Start Time Rule: If an activity has only one immediate predecessor, its ES equals the EF of the predecessor If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max (EF of all immediate predecessors)

PERT: Forward Pass Begin at starting event and work forward Earliest Finish Time Rule: The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time

PERT: Forward Pass (Example 3.4) Step 1: Use forward pass to calculate ES and EF ES EF LS LF 2 4 4 7 3 2 2 F C 2 4 8 A 4 2 E H Start 13 15 5 3 4 B D G 3 3 7 8 13

PERT: Backward Pass Begin with the last event and work backwards Latest Finish Time Rule: If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min (LS of all immediate following activities)

PERT: Backward Pass Begin with the last event and work backwards Latest Start Time Rule: The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF – Activity time

PERT: Backward Pass (Example 3.4) Step 2: Use backward pass to calculate LS and LF ES EF LS LF 2 4 4 7 2 4 10 13 3 2 2 F 2 C 2 A 4 8 4 2 4 8 E H Start 13 15 5 3 4 13 15 B D G 3 3 7 8 13 1 4 4 8 8 13

PERT: Slack time & Critical activity After computing the ES, EF, LS, and LF times for all activities, compute the slack time for each activity, and identify the critical activity. Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES = LF – EF Critical activity is an activity with zero slack

PERT: Critical activity & Project duration Noncritical activity is an activity with a positive slack Project duration is the time to finish the whole project. Project duration = LF of ending activity = EF of ending activity

PERT: Critical Activity (Example 3.4) Step 3: Calculate activity slack and decide critical activities & project duration Slack = 0 Slack = 6 2 4 4 7 Slack = 0 2 4 10 13 3 2 2 F C Slack = 0 2 2 A 4 8 4 2 4 8 E H Start Slack = 0 13 15 5 3 4 13 15 B D G Slack = 0 3 3 7 8 13 1 4 4 8 8 13 Slack = 1 Slack = 1 Slack = 0

PERT: Critical Activity (Example 3.4) Critical activities: A, C, E, G, H Slack = 0 Slack = 6 Project duration is 15 weeks. 2 4 4 7 Slack = 0 2 4 10 13 3 2 2 F C Slack = 0 2 2 A 4 8 4 2 4 8 E H Start Slack = 0 13 15 5 3 4 13 15 B D G Slack = 0 3 3 7 8 13 1 4 4 8 8 13 Slack = 1 Slack = 1 Slack = 0

Note Activity slack time: Path slack time: PERT Algorithm Example 3.4 Deterministic PERT Analysis Example 3.3, 3.2

PERT: Computational Algorithm (Example 3.5) (1) Construct a PERT network for this project by using AON convention Activity Immediate Predecessors Estimated Time (weeks) A — 7 B 3 C 9 D A, C 5 E 2 F Dummy Ending Activity Dummy Starting Activity 9 3 2 5 7 A B D E Start End C F

PERT: Example 3.5 Step 1: Use forward pass to calculate ES and EF A D LS LF 7 12 17 17 19 7 5 2 A D E 19 19 Start End 3 9 5 B C F 3 3 12 12 17

PERT: Example 3.5 Step 2: Use backward pass to calculate LS and LF A D EF LS LF 7 12 17 17 19 5 12 12 17 17 19 7 5 2 A D E 19 19 19 19 Start End 3 9 5 B C F 3 3 12 12 17 3 3 12 14 19

PERT: Example 3.5 Step 3: Calculate activity slack and decide critical activities & project duration Slack = 5 Slack = 0 Slack = 0 7 12 17 17 19 Slack = 0 5 12 12 17 17 19 7 5 2 Slack = 0 A D E 19 19 19 19 Start End 3 9 5 B C F 3 3 12 12 17 3 3 12 14 19 Slack = 0 Slack = 0 Slack = 2

PERT: Example 3.5 Critical activities are B, C, D, E. Slack = 5 Slack = 0 Slack = 0 7 12 17 17 19 Slack = 0 5 12 12 17 17 19 7 5 2 Slack = 0 A D E 19 19 19 19 Start End 3 9 5 B C F 3 3 12 12 17 3 3 12 14 19 Slack = 0 Slack = 0 Slack = 2 Critical activities are B, C, D, E. Project duration is 19 weeks.

EX3 in class Use the computational algorithm to determine the critical activities & project duration 10 6 8 J L P 3 5 End M N Start 8 7 K O

Advantages of PERT/CPM Especially useful when scheduling and controlling large projects Straightforward concept and not mathematically complex Graphical networks help highlight relationships among project activities Critical path and slack time analyses help pinpoint activities that need to be closely watched

Advantages of PERT/CPM Project documentation and graphics point out who is responsible for various activities Applicable to a wide variety of projects Useful in monitoring not only schedules but costs as well

Limitations of PERT/CPM Project activities have to be clearly defined, independent, and stable in their relationships Precedence relationships must be specified and networked together Time estimates tend to be subjective and are subject to fudging by managers There is an inherent danger of too much emphasis being placed on the longest, or critical, path