Excavation Below Subgrade (EBS)

Slides:



Advertisements
Similar presentations
Pavement Rehabilitation Method
Advertisements

Bentley Systems, Incorporated Chris Collins
CTC-275 Construction Methods
A section has been added regarding Stream Restoration Design Criteria: A. Designs for stream restoration try to mimic natural conditions present in stable.
Summary of Conceptual Design Site 3 Causeway Landfill Culvert Stabilization Marine Corps Recruit Depot Parris Island (CTO JM38) 19 August 2014.
Click to continue…. Railroad Track wetland Image Date: December 2003.
Earthwork Operations & Equipments
Chemical Stabilization of Subgrades Section Engineers ’ Meeting Lake Cumberland State Resort Park March 5-7, 2013.
Spring  Proper Drainage  Safe  Long-lasting  Contractor’s Responsibility  But inspector’s confirm correct installation  Refer to contract.
Chapter 3 Measuring Excavation and Sitework
Trenching and Excavating Safety. Asphyxiation Each time a breath is exhaled the weight of the load restricts inhalation of the next breath. Slow suffocation.
An Introduction to Soil Bryan McElvany Research Coordinator Warnell School of Forest Resources Patrick Davies.
An Introduction to Soil
Project details • New headquarters for HKSB
E4014 Construction Surveying
Soils of Wisconsin Topic C. Soil Uncemented aggregate of mineral grains and decayed organic matter with liquid and gas in the empty spaces between the.
Foundation Engineering CE 483
MAINTENANCE PART 2. Inlet free of obstructions Inlet free of obstructions Adequate scour protection provided.
Foundations and Soil types
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
Foundation Fundamentals GSD 6204 Building Technology Harvard Graduate School of Design.
Estimating Site work. Major Components Erosion & Sediment Control Fencing Clearing and grubbing Excavation Backfill Grading Trucking.
Preparation before placing concrete Chapter 3. Chapter Topics Subgrade preparation Compaction around buried pipes and excavations Establishing grades.
 Embankment Construction – LOTs  What is the maximum length of a LOT? Mainline pavement lanes, turn lanes, ramps, parking lots, concrete box.
Introduction Transportation System Objectives : Military; Knit together the inhabitants of a territory by providing mutual access and communication; Economic.
Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.
Earthwork: Use of Fine Grained & Granular Material.
Street and Local Roads Inspection and Acceptance of Alternative Pavements.
2013 Section Engineer’s Meeting.  Correct Type, Gauge, and Coating (Standard Drawings)  Based on Pipe Diameter, Fill Height & Soil pH  Obtain copy.
Foundation Engineering CE 483
Erosion Control/Damage Topic H. Erosion & Sentiment Control Defined by: – Environmental Regulations – State and federal laws – Standard specifications,
Golf Course Construction Site Preparation TRF 250 Golf/Sports Field Construction.
The sand filter has to be moved from this location. The embankment cross section used in the slope stability analysis did not include the sand filter.
EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement.
Wes Marshall, P.E. University of Connecticut March 2007
Topic B2 Sub-structure groundworks
EnE 301: ENVIRONMENTAL ENGINEERING
Pavement Analysis and Design
Residential Construction Unit 2- Site Work and Concrete Mr. Todzia.
Surface Drainage Crown (flat A shape) c Dirt & Gravel: 1/2” - 3/4” per foot (4 - 6 inches in 10 feet)
Planning for Earthwork Construction
E4014 Construction Surveying Pavement Setout. Road Construction Consists of a number of sequential steps –clearing –earthworks –drainage works –pavement.
Soil and Earth Works Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lecture 3 - Week 2 2 nd Semester 2008/2009 UP Copyrights.
Soil Compaction Topic I Topic I.
Highway Subgrade (1) Introduction
Site Work.
Construction Technology: Substructure DW57 34 Outcome 2 Methods of groundwater control.
CIVIL ENGINEERING. Civil engineering work includes: dams embankments motorways bridges buildings cuttings quarries tunnels mines All these need to take.
FRAMING SEMINARS 2012 PRESENTED BY KW ENGINEERING 1.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
1 Common Issues on Site Re-certification Training For Level IA Fundamentals Certified Personnel Issued May 2009.
What are we going to learn…  Soil-Why is it important? Why is it important?  What is soil?  Sand, Silt and Clay  What’s a soil profile?  Horizons?
SOIL PROFILE A vertical strip of soil stretching from the surface down to the bedrock and including all of the successive soil horizons.
Factors to Consider in Foundation Design Chapter # 02
BUILDING CONSTRUCTION
Track Drainage CE2303 Railway Engineering. Drainage-General Drainage is the natural or artificial removal of surface and sub-surface water from an area.
SOIL MECHANICS AND FOUNDATION ENGINEERING-III (CE 434)
Construction Inspection for FO Activities - Soils and Earthwork
Soil mechanics and foundation engineering-III (CE-434)
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
GEOLOGY RECOMMENDATION SHEET GEOLOGY NOTESGEOLOGY RECOMMENDATIONS WYOMING DEPARTMENT OF TRANSPORTATION MATERIALS TESTING LABORATORY PROJECT __________________________________.
An Introduction to Soil
An Introduction to Soil
4th Annual Construction Law Summit
SUBGRADE HOW TO DEAL WITH SOFT SPOTS
Growing Media.
Lecture 7 Excavators TSP-308 MPK Ferdinand Fassa.
ACEC Designer Training
Presentation transcript:

Excavation Below Subgrade (EBS) Topic G Topic G

EBS QC/QV personnel do not determine/direct EBS operations. Engineer ultimately determines the need for EBS. Topic G

EBS Remove objectionable materials. Resulting excavation is then back filled with soil. Figure 3.1 Topic G

Figure 3.1: Intercepting Embankment Topic G

Predicting EBS Areas Groundwater levels = 3 feet or less. Silty “B” horizon. Topsoil depths exceed 12 inches. Moisture levels above plastic limit. Depositional characteristics (alluvial, lacustrine). Topic G

Predicting EBS Areas Roadway constructed prior to 1940. Extensive filling. Roadway is distressed. Highly variable soil conditions exist. Subgrade is within 2 ft. of original surface. Topic G

Figure 3.2: Detail of EBS Topic G

EBS Remove uncertain soil. Note the diagonal rutting= unstable silt. In addition to excavation. Topic G

Figure 3.3: EBS Topic G

Topic I

Rutting of Unstable Material Transition from cut to fill are important. Inspect before the subbase or base. Rutting of unstable material shown. Topic G

Figure 3.4: Rutting of Unstable Material Topic G

EBS Yielding water-bearing silt. Rock truck-hauling material away. Backhoe-Loading EBS material out. Dozer-Pushing material to backhoe. Topic G

Figure 3.5: EBS Topic G

Backfilling EBS EBS has to be measured. Original section is template in the cross. Final section How much was excavated. Topic G

Figure 3.6: Backfilling EBS Topic G

EBS Do not do EBS when rain is imminent. Do not leave EBS excavation open over night. Topic G

Topic I

Figure 3.7: EBS Topic G

Figure 3.8: Loading Unstable Material Topic G

Backfilling EBS Careful placement and compact backfill. Use similar materials in area. Topic G

Figure 3.9: Backfilling EBS Topic G

Organic & Silty Soils Have foundation support for equipment. Topic G

Figure 3.10: Organic & Silty Soils Topic G

Seepage in a Cut Must correct area like this. Ditches may work. Riprapping Underdrains Vegetation will not grow. Topic G

Figure 3.11: Seepage in a Cut Topic G

Dust Abatement Required to minimize dust. Use water or dust control materials. Topic G

Figure 3.12: Dust Abatement Topic G

Stone Piles & Fences Large rocks outside the shoulder point. Topic G

Figure 3.13: Stone Piles & Fences Topic G

Marsh Excavation Picture 2: Excavated marsh either cast out or loaded into marsh. Used for deeper marshes. Dragline works slower then backhoe. Topic G

Figure 3.14: Marsh Excavation 1 Topic G

Figure 3.15: Marsh Excavation 2 Topic G