HIE-ISOLDE Project: Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January 2013 Yacine Kadi.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Henrik Loos LCLS FAC Meeting 27 October RF Gun Status LCLS Facility Advisory Committee Meeting October 26, 2005 Mechanical.
L. Tavian, TE/CRG, Page 2 12 th September 2013 Accelerator Consolidation Workshop L. Tavian, TE-CRG.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning and Operation of the Horizontal Test Apparatus at SNS Presented at: CEC/ICMC.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
201 MHz NC RF Cavity R&D for Muon Cooling Channels
HIE-ISOLDE contribution packages M. Pasini BE/RF.
1 Nb Sputtered Cu QWR: a 20 years experience from an idea to the routine beam acceleration A.M. Porcellato S. Stark V. Palmieri F. Stivanello.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team 49th INTC Meeting CERN, 11 February 2015.
Status of crab crossing studies Presented by NAKANISHI Kota (KEK) 2008/1/25.
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
HIE-ISOLDE Project Status Report
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Revised SPL-study work-plan W. Weingarten 3 May 20101SPL Cavity WG Meeting.
HIE-ISOLDE Project Y. Kadi (EN-STI) On behalf of the HIE-ISOLDE Coordination team.
HIE-ISOLDE Project Status Report
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
HIE-ISOLDE Project Status Report Y. Kadi for the HIE-ISOLDE Project Team HIE-ISOLDE Physics Coordination WG Meeting CERN, 16 February 2015.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
October, 2009 Cost of SRF Components Gary McIntyre October, 2009 Internal Review.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
HIE-ISOLDE Project Status Report 52nd ISOLDE & nTOF Technical Committee meeting February 3rd 2016 Y. Kadi On behalf of the HIE-ISOLDE Project Team.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
HIE-ISOLDE Project Status Report 50th ISOLDE & nTOF Technical Committee meeting July 1st 2015 Y. Kadi.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
TE-CRG Activities D. Delikaris, TE-CRG.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
7th SRF Materials Workshop FRIB SRF Cavities 7/16/12 Chris Compton.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
HIE-ISOLDE Status Report Yacine Kadi on behalf of HIE-ISOLDE project team ISOLDE Annual Workshop, 5 December 2011.
R. Bonomi - SLHiPP2, Catania 3-4/5/20121 SPL Thermal Studies R. Bonomi Superconducting linacs for high power proton beams - Catania, 2012.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
WP1: Superconducting Cavity Developments and Tests Walter Venturini Delsolaro Mid Term Review Meeting, 26 September 2012 CATHI Marie Curie Initial Training.
Guillaume Olry on behalf the IPN Orsay SPIRAL2 team TTC Meeting – Milan, 28 Feb-3 March 2011.
HIE ISOLDE Linac Short Technical Description W. Venturini Delsolaro Material from: L. Alberty, J. Bauche, Y. Leclerq, R. Mompo, D. Valuch, D. Voulot, P.
CERN – Zanon discussions
WP5 Elliptical cavities
ILC-SCRF Test Facilities considerations
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
HFM Test Station Main Cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
THE HIE-ISOLDE SUPERCONDUCTING CAVITIES:
Update on HW commissioning
ILC Cryogenic Systems Draft EDR Plan
HIE-ISOLDE Status Report
UK RFD Pre-Series cryomodule
HIE-ISOLDE Project: Planning & Resources
HIE-LINAC status report
HIE-ISOLDE Project: Status Report
Report on HIE-ISOLDE Status
CERN’s MidTermPlan and the consequences for HIE-ISOLDE
HIE-ISOLDE contribution packages
Cryomodules Challenges for PERLE
Prototype cryomodule development
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

HIE-ISOLDE Project: Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January 2013 Yacine Kadi

Phase 1 Updated Schedule Initially planned to start in May 2015, the Physics Program at 5.5 MeV/u is now expected to start in October The above schedule is could be affected by unforeseen emergency activities that could arise during LS1. Reprioritization of phase 2 and 3 is unavoidable JFMAMJJASONDJFMAMJJASONDJFMAMJJASOND LS1 & shutdowns Refurbishment of the old ALEPH Cryo-Plant Compressor installation and commissioning Cryo-plant installation (cold box and transfer line) Cryo-plant commissioning HIE-ISOLDE SC Linac Cryomodule 1 Tests (SM18) Cryomodule 2 Tests (SM18) Cryomodule 1&2 installation (ISOLDE) Cryomodule 1&2 Commissioning (ISOLDE) HIE-ISOLDE High-Energy Beam Transfer Lines Power converters installation & Commissioning Magnet installation & Commissioning BI installation & Commissioning (HW) Vacuum installation & Commissioning Beam commissioning (phase1) Start of the Physics at 5.5 MeV/u JFMAMJJASONDJFMAMJJASONDJFMAMJJASOND LS2 & shutdowns Physics at 5.5 MeV/u

Cost: External Funding Phase 1 The missing income of 0.7 MCHF should be covered through new applications:  Belgian Big Science Project #2 through K.U. Leuven => Phase-2  Local funds from Sweden through U. Lund  COSA EU-FP7-ITN Innovative Doctoral Program 24 man x years 3 (*) to be considered additional expenses on salaries of 6.0 MCHF ( ) already covered by EU-FP7-ITN Marie-Curie program: CATHI

CERN Extra Costs Phase 1 4 (*) re-use of ALEPH cryo-plant

Missing Resources for Phase 1 5 For the CRYOMODULE: HR needs (8 man years) All of these needs (the 5 man years listed above) have been filled by redeploying personnel from other projects. However, a short-term (3 year LD contract) position is requested to ensure the continuation of the experienced Mechanical Engineer currently assigned to the HIE-ISOLDE project beyond July 2013.

Missing Resources for Phase 1 6 For the CRYOGENIC PLANT: HR Needs (2.3 man years)  HR needs are estimated to a total of 8.3 man years for the period ( ). The need is for Engineers and technicians to be involved in “Cold box reinstallation” and “Compressor station reinstallation” mainly in the activities of: Project engineer, Mechanics/drawing, Process control, Instrumentation and Commissioning.  All of these needs but, 2.3 man years, have been secured for the project. For the Beam Instrumentation: HR Needs (2 man years)  HR needs are estimated to a total of 2 man years during the period ( ). Two electronic engineers are needed for a period of 12 months to develop: (i) the front-end analogue electronics for the Faraday Cup (in intensity and profile measurement modes) and the Silicon detector and (ii) the motion control for the beam diagnostic boxes.  All of these needs will be filled by redeploying personnel from other projects.

CRYOMODULE: Status 7 DoneIn progressPending Active componentsMechanical & cryogenics interfaces Assembly procedures redaction, current leads Quench protection system, RF interfaces AlignmentConcept and proceduresAdjustment mechanism design Jacks procurement Detailed design, drawings of supporting frame assembly VacuumConcept, interfaces, instru. and product identification Interfaces drawings Vacuum vessel drawings Procurement and contract follow-up CryogenicsConcept, procedures, reservoir drawings, instrumentation list Aleph fridge compatibility study Thermal shield specifications redaction Response to cryogenics stop scenario. Thermal shield drawings SurveyConcept, interfacesTargets definitionDetailed design of supports AssemblyConcept, general assembly sequence Clean room procurement Detailed procedure redaction Tooling detailed design InstrumentationRequirements-Selection, procurement, installation SafetyRisk identification, calculationsProducts selectionProcurement, installation Contracts follow-up-Adjustment mechanism, helium reservoir Vacuum vessel, thermal shield, supporting frame, bellows, instrumentation, tooling  General  Conceptual design 100%  Detailed design 60%  Detailed drawings 20%  Priorities  Start procurement processes for components requiring long delays  Validate last active components solutions  Instrumentation consideration

Cavity development work in 2012

Parameter/feature HIE ISOLDE cavity CERN ALPI cavity INFN-LNL Substrate treatment SUBUTumbling, EP then SUBU Rinsing water pressure 5-6 bar100 bar Bake out temperature 670ᵒC (~ sputtering T) 600ᵒC (>sputtering T) Sputtering temperature 450ᵒC  690ᵒC300  500 ᵒC Sputtering pressure mbar mbar Number of layers layers Power 2 kW  11 kW 5 kW (for 2.5 times smaller surface) Cathode voltage1 kV Bias voltage-80 V-120 V Total electrical energy 46 kWh15 kWh Auxiliary electrode 2 cm diameter, bias potential 4 cm diameter (2/3 of inner conductor), rounded, bias potential Film minimum thickness To be measured2 µm Sputtering gasArgon Venting gasN2N2 N2N2 vacuum jointVitonCF Cavity Test Results

Comparison of HIE ISOLDE and ALPI QWRs Data from Legnaro vertical test courtesy of Anna Porcellato The slope of our best cavities is independent on Q 0 and close to the best ALPI cavities (rounded substrates) Q2_7 ranks 9th out of 13 in terms of Q 0 and initial slope Looks as if we were entering the distribution of the LNL cavities from below

Summary 11 Most recommendations of the previous cavity review were implemented:  Reconsidered mechanical tolerances  4 prototypes available since summer 2012  Focused on dc bias sputtering  Dummy copper cavity available and used for sample studies in autumn 2012  Increasing cavity turnaround up to 2 weeks  Setting up a backup test place in Orsay  Continuing work on cavity ancillaries (tuning plate, coupler, RF line) Cavity performance improved significantly in one year:  1 10 W in September 2011  5 10 W in October 2012 Remaining issues for cavity performance  Film thinness on cavity top (high current region)  Bad film quality on tip of the inner conductor (peak E  field emission)  Stability  Statistics

12