CHEP 97 Berlin, April 97Frédéric Hemmer1/11 Managing Outsourcing Contracts for System Administration Frédéric Hemmer CERN.

Slides:



Advertisements
Similar presentations
STORAGE MANAGEMENT/ GETTING STARTED: Storage Management 101 Everything you always wanted to know about Storage Management (but were afraid to ask) Stephen.
Advertisements

1 Eurostat Unit B1 – IT Systems for Statistical Production IT outsourcing in Eurostat – our experience Georges Pongas, Adam Wroński Meeting on the Management.
SERVICE LEVEL AGREEMENTS The Technical Contract Within the Master Agreement.
Lecture 17 Chapter 9 Managing IT Outsourcing. 2 Final Exam Outline 12 – 3pm, Wednesday June 14 Half short and long answers on theory and principles from.
A CONSTRUCTION SAFETY COMPETENCY FRAMEWORK: DEVELOPMENT, INDUSTRY APPLICATION, AND FUTURE BENEFITS Herbert Biggs PhD.
Contractor Safety Management
Free Powerpoint Templates Page 1 Free Powerpoint Templates Introduction to Project Management What is a Project? Project Life Cycle Project Management.
Audit Considerations of Data Center Consolidation Jon Ingram Audit Manager Information Technology Audits Florida Auditor General 1.
Council in the Cloud Justin Thomas, ICT Manager Noosa Shire Council.
Yale University Information Technology Services Administrative Systems Art Hunt 3/22/04 Software Service Level Agreement with Finance, Procurement and.
Date: 03/05/2007 Vendor Management and Metrics. 2 A.T. Kearney X/mm.yyyy/00000 AT Kearney’s IT/Telecom Vendor Facts IT/Telecom service, software and equipment.
Iterative development and The Unified process
Pertemuan Matakuliah: A0214/Audit Sistem Informasi Tahun: 2007.
Problem Management Overview
1 Walk-in slide. 2 How to Manage a System Upgrade The Good, The Bad and The Ugly of Conversions David Cervelli Managing Consultant April 25, 2006.
Appraisal Process & Paperwork Update Workshop Jackie Skeel 13 March 2014.
Reducing Budget Costs in the Turbulent Waters of PPAC When Outsourcing.
Nagios as a PC Health Monitor Sean
Basel Accord IITRANSITIONSERVICES Business Integration Support FCM Management Limited Paris New York Toronto.
October 23rd, 2009 Visit of CMS Computing Management at CC-IN2P3.
From Olivier to commissioning team plans for the start-up of regular operations of LHCb 30/06 to 4/07 : Global commissioning week, all detectors, full.
By: Muhammad Raza Ali Khan
Managing Offshore Software Development Projects Presented by Orlando Moreno Phone: web:
1 IS 8950 Managing and Leading a Networked IT Organization.
1 COMPASS Common Processes and Shared Services Setting a Direction for IT.
SLA of an Outsource Process - 1 Service Level Agreements (SLAs) of an Outsource Process Michael Day MBA 731 October 29, 2007.
Module CC3002 Post Implementation Issues Lecture for Week 1 AY 2013 Spring.
Business Systems Development SDLC and introduction to the Microsoft Solutions Framework Team and Process Models.
7/2/2003Supervision & Monitoring section1 Supervision & Monitoring Organization and work plan Olof Bärring.
For BCS by Nadine Mouali 21 May The IT Organization Part I.
Deakin Richard Tan Head, Information Technology Services Division DEAKIN UNIVERSITY 14 th October 2003.
ITEC 275 Computer Networks – Switching, Routing, and WANs Week 12 Chapter 14 Robert D’Andrea Some slides provide by Priscilla Oppenheimer and used with.
Lecture 4 1 Introduction to Systems Planning Lecture 4 2 Objectives n Describe the strategic planning process n Explain the purpose of a mission statement.
Strategic Leadership Defined 1 STRATEGIC LEADERSHIP DEFINED.
A Level ICT Unit Implementing CBIS’s. Support Installing a new system is disruptive and the support program will need to be planned well in advance.
© 2008 IBM Corporation Challenges for Infrastructure Outsourcing July 29, 2011 Atul Gupta Vice President, Strategic Outsourcing, IBM.
Texas Nodal Program ERCOT Readiness Update TPTF March 31, 2008.
Change and Patch Management Controls
Northwest ASSIST How to obtain maximum value from consultants 3 rd April 2008 Nadine Fry Julian Todd.
CS 111 – Dec. 3 Lab recap Problem solving approach for systems analysts –8 phases –Just understand the flow/process/sequence of the steps, not specifically.
CERN - European Laboratory for Particle Physics FOCUS - July 1 st, 1999 NICE : Plans for Physics Service Impact of Windows 2000 Frédéric Hemmer.
Status of the LHCb MC production system Andrei Tsaregorodtsev, CPPM, Marseille DataGRID France workshop, Marseille, 24 September 2002.
Service Level Agreements Service Level Statements NO YES The process of negotiating and defining the levels of user service (service levels) required.
Phases of BCP The BCP process can be divided into the following life cycle phases: Creation of a business continuity and disaster recovery policy. Business.
Ian Bird GDB; CERN, 8 th May 2013 March 6, 2013
Example Incident Mgmt Initiation No recording of Incidents Users can approach different departments Solutions of previous incidents are not available.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Production and Cost CH 7, 8. Outline Production Costs Output Decisions Pricing Market Environment and Consumer Demand Firm’s Objectives.
14 th April 1999CERN Site Report, HEPiX RAL. A.Silverman CERN Site Report HEPiX April 1999 RAL Alan Silverman CERN/IT/DIS.
1 LHCC RRB SG 16 Sep P. Vande Vyvre CERN-PH On-line Computing M&O LHCC RRB SG 16 Sep 2004 P. Vande Vyvre CERN/PH for 4 LHC DAQ project leaders.
ST Quality WG I. Béjar Alonso Group Leader’s meeting 6th July.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Outsourcing of Census Operations United Nations Statistics Division UNSD-ESCWA Regional Workshop on Census Data Processing in the ESCWA region: Contemporary.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
Outsourcing of Census Operations United Nations Statistics Division Regional Workshop on the 2010 World Programme on Population and Housing Censuses: International.
More Timely, Credible and Cost Effective Performance Information on Multilateral Partners Presented by: Goberdhan Singh Director of the Evaluation Division.
CERN IT Department CH-1211 Genève 23 Switzerland t Migration from ELFMs to Agile Infrastructure CERN, IT Department.
MANAGED LAN SERVICES How will you benefit? Managed LAN service  Full LAN service (hardware, operation, other services)  Per-port pricing  International.
Practical IT Research that Drives Measurable Results Get Started Bringing Order to Help Desk Request Chaos.
SMB Service Status 111 th ACCU Meeting Tuesday, 8 march 2016.
ITEC 275 Computer Networks – Switching, Routing, and WANs Week 12 Chapter 14 Robert D’Andrea Some slides provide by Priscilla Oppenheimer and used with.
GSA IT Strategic Plan 2009 – 2011 August 2007 US General Services Administration 1.
Service Design.
1 ALICE Summary LHCC Computing Manpower Review September 3, 2003.
ITIL: Service Transition
Employing People.
C Loomis (CNRS/LAL) and V. Floros (GRNET)
CERN openlab for DataGrid applications
Establishing a Strategic Process Roadmap
Presentation transcript:

CHEP 97 Berlin, April 97Frédéric Hemmer1/11 Managing Outsourcing Contracts for System Administration Frédéric Hemmer CERN

CHEP 97 Berlin, April 97Frédéric Hemmer2/11 Capacity explosion Physics Data Processing capacity Benefits Cheaper and more affordable computing cycles Large data stores Services dedicated to experiments Large increase of computer nodes (20 in 1990, 300 now) Over 1000 disks î need for more manpower to perform the system administration (est.) Year CPU Capacity - CERN Units Disk Storage - GigaBytes

CHEP 97 Berlin, April 97Frédéric Hemmer3/11 Manpower evolution Physics Data Processing manpower system administration user support general administration planning etc. Total decreased by 25 % Sys. Admin. decreased by 40 % (est.) Year man-years per year TotalSystems Administration

CHEP 97 Berlin, April 97Frédéric Hemmer4/11 Outsourcing Very wide definition Total outsourcing of a service Total transfer of ownership (equipment, infrastructure and staff) Long term mega-deals Temporary labour contracts Selective sourcing (scope, size and duration) different activities lead to different management attention create constant competition more flexibility to adapt to changes î We try to follow this approach

CHEP 97 Berlin, April 97Frédéric Hemmer5/11 “Best Practices in Information Technology Sourcing” M.C. Lacity, L.P. Wilcocks Executive Research Briefing, Oxford Institute of Information Management, Templeton College, University of Oxford 1996

CHEP 97 Berlin, April 97Frédéric Hemmer6/11 Our approach Short term contracts System administration only CERN retains planning, HW purchase/maintenance, user support, choice of technology and architecture SLA’s defining quality measures At least two contracts (offset in time) î allows for regular retendering (competition)

CHEP 97 Berlin, April 97Frédéric Hemmer7/11 Our experience (1) Initially tried to use temporary labour Difficulty in finding experience candidates CERN policy evolved to service contracts Difficulty to express specifications of sys. admin. Outsourced the task of writing the specifications Long iterative process Vendor and customer have different goals ! Contract covering 28 HP and 27 DEC starting Jan. 96

CHEP 97 Berlin, April 97Frédéric Hemmer8/11 Our experience (2) Documents Service Definition Document (Scope, communication and escalation procedures) Service Level Agreement (responsibilities, tasks and performance metrics) Specific Sys. Admin. documents for each system System Administration tasks installation, configuration changes, reactive and proactive problem management, development of service quality and performance measurements Aggressive timescale 2 months for sys. admin. guides, take over one month later

CHEP 97 Berlin, April 97Frédéric Hemmer9/11 Our experience (3) May review Objectives met No degradation in service Documentation very good Improvements needed Communication needs to be more formal î Mastersoft’s OSM Inventory, SLA, communication, reporting, quality measurement System managers showed reluctance to give away “their” systems (lack of confidence, faster to fix it now). Not solved yet. Decided to expand 24/hours day later expand to all DEC, HP, SUN and SGI equipment

CHEP 97 Berlin, April 97Frédéric Hemmer10/11 Potential Problem areas Call Management System Installed in Autumn, not used before March No PC for our OPS manager Lack of momentum in contract follow-up (increased responsibilities of the team leader, staffing problems) î no quality or performance measures Coverage and end of 96 shutdown Contract excluded this period Period of intense activity as the computers are down î return of control to CERN staff Contractor’s staff stability î unable to test whether procedures and documentation are enough

CHEP 97 Berlin, April 97Frédéric Hemmer11/11 Conclusions Globally positive Procedures well documented Very few problems/mistakes Not too many delays Clear cost attributable to system administration Scaling up no longer limited by CERN staffing level Improvement needed More involvement from CERN needed in contract follow-up The performance metrics need to be gathered and analysed î We hope to assess performance by the summer and be ready for tendering at the end of the year.