G020457-00-R Advanced LIGO Seismic Isolation R&D Dennis Coyne 8 Oct 2002.

Slides:



Advertisements
Similar presentations
LIGO-G M May 17, 2006 Installation (INS) Requirements and Design Breakout Presentation NSF Review of Advanced LIGO Project Dennis Coyne, Caltech.
Advertisements

LIGO-G D Comments: Staged implementation of Advanced LIGO Adv LIGO Systems 17 may02 dhs Nifty idea: a way to soften the shock, spread cost, allow.
LIGO-G D Quiet Hydraulics Board: Purpose, Scope, Charter and Plans Dennis Coyne Kick-off Stanford, 16 Oct 2003.
G R LIGO Laboratory1 Advanced LIGO Research and Development David Shoemaker LHO LSC 11 November 2003.
G R LIGO Advanced System Test Interferometer LIGO Advanced R&D Review M. Zucker 8 October, 2002.
LIGO-G D Evaluation of EPI Approaches Dennis Coyne 18 April 2003 EPI Design Review #2.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G M 1 Conceptual Design Review: Initial LIGO Seismic Isolation System Upgrade Introduction Dennis Coyne April 12, 2002.
LIGO-G0200XX-00-M LIGO Laboratory1 Pre-Isolation Dennis Coyne LIGO Laboratory NSF LIGO Annual Review, at MIT 23 October 2002.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
PALM-3000 Management Update A. Bouchez Team Meeting #9 10/22/2008.
Dennis Coyne Excomm Jan 26, 2004
LIGO-G M LIGO1 Hydraulic External Pre-Isolator (HEPI) Overall Installation Plan/Schedule Dennis Coyne HEPI Installation Readiness Review Feb 11,
G M Advanced R&D1 Seismic Isolation Retrofit Plan for the LIGO Livingston Observatory Dennis Coyne 29 Nov 2001.
LIGO Magnetic External Pre-Isolator Richard Mittleman, David Ottaway & Gregg Harry April 18, 2003.
LIGO-G M LIGO Laboratory1 Pre-Isolation Dennis Coyne LIGO Laboratory NSF LIGO Annual Review, at MIT 23 October 2002.
LIGO-G W LIGO II Pre-stabilized Laser System Design Requirements and Conceptual Design David Ottaway, Todd Rutherford, Rick Savage, Peter Veitch,
LIGO-G M LIGO Laboratory1 Adv. LIGO Seismic Isolation (SEI) Plans, Schedule, Costs, Team Schedule »through R&D, including near-term plans »project.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
Nov ’01, page 1 Current Work on Hydraulics for LIGO 1 and Advanced LIGO Rich Abbott, Graham Allen, Daniel DeBra, Joe Giaime, Giles Hammond, Marcel Hammond,
LIGO-G06xxxx-00-M Technical Progress Planned/Needed in FY07 Advanced LIGO Program Advisory Panel meeting, 30 November – 1 December 2006, MIT Dennis Coyne,
LIGO-G D 1 Requirements Environment and constraints Performance requirements Functional requirements.
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
LIGO-G M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
LIGO-G M 1 Initial LIGO Seismic Isolation System Upgrade Dennis Coyne LIGO Seminar March 29, 2002.
LIGO-G D 1 MEPI electroMagnetic External Pre-Isolator Backup alternative to the Hydraulic actuator approach Goal: maximum commonality with HEPI.
G R PHOTON ACTUATION R&D PROGRAM Michael Smith 8 Oct 02.
Active Seismic Isolation Systems for Enhanced and Advanced LIGO Jeffrey S. Kissel 1 for the LSC 1 Louisiana State University The mechanical system for.
RF Cavity / Coupling Coil Module
LSC Meeting August ‘04 1 LIGO ADVANCED SYSTEMS TEST INTERFEROMETER (LASTI) Program Update: LSC Meeting, Hanford Dave Ottaway for the LASTI team August.
Test Mass Discharging System (TMDS) Design Review 20 Nov 2014 Rich Abbott, Dennis Coyne, Eddie Sanchez, Calum Torrie 1 LIGO-G v1.
4/25/11 G v3 1 Facility Modifications and Preparations (FMP) Technical Status Annual NSF Review of Advanced LIGO Project April , 2011 John.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
LIGO-G M 1 Conceptual Design Review: Initial LIGO Seismic Isolation System Upgrade Development, Implementation Plan & Schedule Dennis Coyne April.
G M 1 Advanced LIGO Update David Shoemaker LSC/Virgo MIT July 2007.
Livingston 16 th August 2006 LIGO-G E HAM SAS Passive Seismic Attenuation System Fabrication, Assembly, Installation Ben Abbott, Valerio Boschi,
G Amaldi Meeting 2015, Gwangju, South Korea1 Status of LIGO June 22, 2015 Daniel Sigg LIGO Hanford Observatory (on behalf of the LIGO Scientific.
E v3 aLIGO SEI Testing and Commissioning Overall Plan
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
G M 1 HAM-SAS CCB information 22 Feb 06 Coyne, Shoemaker, Wilkinson.
Daniel Clark Dan DeBra Victor Herrera Brian Lantz Joe Hansen Jeff Kissel Michael Meyer Brian O’Reilly Celine Ramet & Staff at LLO Anamaria Effler Michael.
G Consideration of HAM SAS for Advanced LIGO David Shoemaker LIGO Excomm 30 April 07.
LIGO-G D LIGO R&D1 Advanced LIGO R&D Review The PSL Peter King & Rich Abbott October 8, 2002.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Update on Activities in Suspensions for Advanced LIGO Norna A Robertson University of Glasgow and Stanford University LSC meeting, Hanford, Aug 20 th 2002.
LSC Meeting March ‘05 1 LIGO ADVANCED SYSTEMS TEST INTERFEROMETER (LASTI) Program Update: LSC Meeting, LLO Dave Ottaway for the LASTI team March 2006 LIGO-G Z.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
LIGO-G M Overview of LIGO R&D and Planning for Advanced LIGO Detectors Gary Sanders NSF R&D Review Caltech, January 29, 2001.
Lasti ISI Update March 2007 On behalf of the SEI Team LIGO-G Z.
G R Interferometer Sensing & Control P Fritschel 8 Oct 02.
G R LIGO R&D1 Advanced LIGO Update David Shoemaker LSC LHO August 2004.
Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014.
LIGO-G M State of the LIGO Laboratory Gary Sanders LIGO/Caltech LSC Meeting, LLO March 16, 2004 State of LIGO.
LIGO- G M LIGO Status Stan Whitcomb Oversight Committee 20 October 2004.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
LIGO LAB R&D PROGRAM TECHNICAL REVIEW, OCT 02
Prospects and plans : LIGO interferometers Michael Landry LIGO Hanford Observatory LSC meeting, MIT Nov 4-5, 2006.
Reaching the Advanced LIGO Detector Design Sensitivity
Lasti Update July 25, 2007 LIGO-G Z
Peer Review Agenda (Suggested).
Stan Whitcomb LSC meeting Livingston 21 March 2005
Management of the Advanced LIGO Seismic Isolation System Development
LIGO Advanced System Test Interferometer
Improving LIGO’s stability and sensitivity: commissioning examples
Daresbury ESS In-Kind Contributions
Advanced R&D Lab Review
Advanced LIGO R&D Review Input Optics
Presentation transcript:

G R Advanced LIGO Seismic Isolation R&D Dennis Coyne 8 Oct 2002

G R 2 Current status (see images in LASTI report) Program has bifurcated into internal & external isolation efforts due to acceleration of the external pre-isolator AdvLIGO SEI: Selected a conceptual design approach April/2001 Held a design requirements review Jan/2001 Completing assembly & beginning test of the Technology Demonstrator (Servo- controls test bed) at the Stanford ETF Preparing an RFP for design and fabrication of the BSC and HAM full-scale prototype structures for LASTI »Contingent on early ETF results PDR is scheduled immediately after LASTI prototype results »Really should have a review of the RFP & ETF results before buying the LASTI prototypes »To avoid further delay, could review in parallel with prototype contract award & before committing to fabrication External Pre-Isolator (EPI): Held a design requirements review April/2002 PEPI is operational at LLO Integrating and evaluating the MEPI and HEPI external pre-isolators at LASTI now PDR for the EPI is scheduled immediately after LASTI prototype results CCB request for EPI production is planned at the time of the PDR

G R 3 Plans for 2003 AdvLIGO SEI: Hold design review for preliminary phase LASTI prototypes Begin servo-controls testing on the ETF Tech Demonstrator Initiate contract for design & fabrication of the LASI HAM and BSC prototypes (1 ea.) EPI: Complete evaluation of the MEPI and HEPI prototypes »Preliminary results by Dec, 2002 »Hold PDR Jan, 2002; select approach for Observatories Fabricate & Assemble EPI »Get CCB approval for production »May need to start long lead procurement before PDR (say ~Dec) »Incremental FDRs on each subsystem/subassembly as required before production orders Install & Stand-alone testing of EPI »Plan to be ready to install at LLO ASAP after S2 (target 4/14; current projection mid-May) »Installation and test will take 4+ months at LLO EPI for LHO? »Per the DRR (T ), the baseline is PEPI on 6 Chambers at LHO (ETM, ITM, MC) »Implementation after LLO iff funds permit in FY03

G R 4 Technical Risks and Opportunities AdvLIGO SEI: Technical Risks and opportunities: what is technically scary? »Limiting effect of tilt-horizontal coupling »Achieving structural resonances well above the control band »Magnetic fields from SEI internal actuators may need considerable shielding to prevent noise injection to the magnets on the SUS assemblies »Heat dissipation of the internal electromagnetic actuators may be difficult »Materials in the electromagnetic actuator need to be vacuum qualified, or replaced with compatible materials (development effort on a commercial unit) »BSC unit may need to be larger (higher) than can readily be integrated into the LASTI facility (complicates installation with SUS) What new ideas not in the plan might we pursue? »None

G R 5 Technical Risks and Opportunities EPI: Technical Risks and opportunities: what is technically scary? »Interaction of structural support modes with the control system may limit gain/bandwidth and performance, or cause us to consider structural modifications/additions, or an entirely different approach. »Modeling is still lagging the hardware development though catching up »Contamination from hydraulic fluid – careful, robust engineering can mitigate; To date engineering has been on more fundamental design trade- offs, not focused on minimization of leak risk What new ideas not in the plan might we pursue? »Structural modifications or additions such as stiffening elements, constrained layer damping, tuned mass damping, etc. (HAM support structure & BSC pier) »As a deep fallback if significant problems are encountered soon in LASTI testing: Drop the ‘stiff’ approach and employ the VIRGO ‘soft’ (pendulum & GAS) approach.

G R 6 Schedule issues Schedule issues: what is going too slowly, what is faster than thought, how are interacts with other activities? AdvLIGO SEI: Far behind original schedule due to acceleration of the EPI system for initial LIGO »Delay is mostly due to diversion of personnel to accelerate the external pre-isolator for initial LIGO »HPD effort was considerably longer than expected as well Need timely ETF results and RFP development to prevent further schedule slip SEI delays virtually all elements of the LASTI program, most particularly SUS Milestones: »ETF results (elastic modes >> control band, low frequency tilt-horiz coupling within limits) by ~11/18 »RFP issued ~11/15 »RFP award Jan, 2003 »Delivery to LASTI for assembly ~Dec, 2003

G R 7 Schedule issues Schedule issues: what is going too slowly, what is faster than thought, how are interacts with other activities? EPI: Schedule (M ) is very aggressive Schedule has slipped many months in the hardware development phase – which is nearly done, so risk of further hardware related delays is low May take longer than scheduled to test the LASTI prototypes Fabrication/assembly schedule is not generous (3 months) Milestones: »Debug & initial results 4 weeks after install (~12/1) »PDR Jan, 2001 »FDRs as needed for drawing releases »Final results in another 4 weeks (~1/7)

G R 8 Cost baseline and issues Cost baseline and issues: what do we expect to expend this year (not a guess, something backed up with a spreadsheet)? anything changed? anything uncertain? AdvLIGO SEI: FY03 Costs cover: »1 engineer at LLO »0.5 PostDoc shared with LSU? (assume that this no longer part of the plan) »Both the BSC and HAM prototypes were originally estimated at $670K total including all instrumentation and electronics and pre-isolation »The HPD contract for the structure alone cost $750K »Already have some (most?) instrumentation for the BSC & HAM adv SEI prototypes »Rough estimate is that the BSC and HAM prototypes will cost ~$750K each »Total rough cost in FY2003 = ~$1.4M (with $0.4M required in FY04 for completion) Changes in baseline: »Mechanical design work: –Originally design work was to be done in the Lab after the ETF Technology demonstrator. Now we will outsource the design; perhaps less cost since the adv. LIGO program schedule is stretching –ETF Technology Demonstrator effort far exceeded the original estimate (estimated $500, actual $750+) Uncertainties: »Price for RFP on mechanical design »Sensor pod sealing costs »Cost of in-vacuum actuator

G R 9 Cost baseline and issues Cost baseline and issues: what do we expect to expend this year (not a guess, something backed up with a spreadsheet)? anything changed? anything uncertain? EPI: FY03 R&D Costs cover: »a hydraulic servo-valve test stand ($10K) »some additional components of the LASTI prototype pump station ($10K) »Distribution plumbing at LASTI ($18K) »Total = ~$40K »N.B.: Most R&D costs for EPI in FY2002 covered under the MIT LASTI facility funds Changes in baseline: »Integrated costs for the EPI R&D far, far exceed the original estimates »Added MEPI »N.B.: PEPI hardware costs covered in operations funds allocation »N.B.: Production costs for EPI will be a CCB request for an operations funding allocation Uncertainties: »If structural modifications or alternative approaches are needed (e.g. 6 dof piezo-electric actuator) then R&UD costs will increase; relatively low risk

G R 10 Staffing baseline and issues Staffing baseline and issues: who is working how much on this effort? enough people? right skills? AdvLIGO SEI: ~¼ Brian Lantz, ~1/8 Joe Giaime, Wensheng Hua, ~¼ Marcel Hammond, 1/10 Rich Abbott, ¼ Larry Jones, 1/10 Gerry Stapfer »Only Marcel’s time is charged to LIGO Lab R&D »Travel for LLO staff is charged to R&D (but not CIT, MIT); non- symmetric Insufficient staffing (people diverted to EPI) Hope to complete EPI development early in FY03 and move some staff back to adv LIGO SEI

G R 11 Staffing baseline and issues Staffing baseline and issues: who is working how much on this effort? enough people? right skills? EPI: ~¾ Brian Lantz, ~¼ Joe Giaime, ~¾ Jonathan Kern, ~¾ Marcel Hammond, Ken Mailand, ¼ Rich Abbott, Ken Mason, ¾ Myron McInnis, ~½ Dave Ottaway, Rich Abbott (plus help from Mike Zucker, Peter Fritschel, Dennis Coyne, Prof. Samir & students,…) = ~6 FTE Barely sufficient staffing »some hardware delays could have been helped by added staffing »Should we add staff to make final design & production schedule more robust? Plan to have all/most useful staff deployed for LASTI testing