Project Control WeekCost ($)Cumulative CostWeek StartingBCWSACWPBCWP 1$6,672.50 5/17/10$6,672.50$4,070.23$4,003.50 2$53,407.33$60,079.835/24/10$60,079.83$51,068.68$17,353.97.

Slides:



Advertisements
Similar presentations
COST CONTROL - EARNED VALUE 1.0. EARNED VALUE - INTRODUCTION
Advertisements

Connoizor Enabling Performance for Businesses through Software Website: Contact:
Presenter: Sohel Akhter, PMP, CCNA,ISMS
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Monitoring and Controlling the Project
N O T E “CLICK” TO CONTINUE… If the slide show is not launched, click on View  Slide Show in the menu bar at the top of the Power Point window. When the.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
Copyright , Dennis J. Frailey CSE7315 – Software Project Management CSE7315 M30 - Version 9.01 SMU CSE 7315 Planning and Managing a Software Project.
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Chapter 41 Chapter 13 ٠ Contract Types ٠ Supplier Management.
Earned Value Management
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Management Methodology Project monitoring and control.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Statistical Process Control of Project Performance Walt Lipke Software Division Tinker AFB, OK SCEA 2002 June Scottsdale, AZ.
Chapter 16 Floor-Plan Layout.
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Construction PROJECT MANAGEMENT Supervisor : E. Barraq Jumaa Prepared by: Ahmad Faqra Amjad Zarour Nidal Haroon.
1 Lecture 4.3b: Earned Value as the Cost and Schedule Metric (SEF Ch 14) Dr. John MacCarthy UMBC CMSC 615 Fall, 2006.
Information Investment Subcommittee Meeting EVM SLIDE ONLY December 20, 2007.
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Team7 Team Assignment 2 Software Measurement and Analysis.
Architectural Design Detailing the Design – The Floor Plan Technological Design TDJ2O1 – Grade 10.
Architectural Terms and Features
PRESENTATION FOR POLO SETTIMO TORINESE PROJECT Nov.25 th.2009.
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
Orthographic Drawings
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
MEASURING AND FORECASTING COMPLETION. PROGRESS BY DISCIPLINE.
CSE SW Project Management / Module 30 - Managing with Earned Value / Measurement Issues Copyright © , Dennis J. Frailey, All Rights Reserved.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
Earned Value Management
Work Packages / Deliverables Completed
EVM 202—Lesson 7 Tools Analysis Case Study
Contract Performance Charts
Progress and Performance Measurement and Evaluation
EVM 202—Lesson 7 Tools Analysis Case Study
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Floor Plan A horizontal section view of a structure taken about 4’ from floor level, It shows all exterior and interior walls, doors, windows, patios,
Project Cost Control.
Project Management Life Cycle
Earned Value $$$.
Presentation transcript:

Project Control WeekCost ($)Cumulative CostWeek StartingBCWSACWPBCWP 1$6, /17/10$6,672.50$4,070.23$4, $53,407.33$60, /24/10$60,079.83$51,068.68$17, $86,606.79$146, /31/10$146,686.62$171,452.12$77, $1,283.95$147, /7/10$147,970.58$173,095.58$129, $1,283.95$149, /14/10$149,254.53$174,880.27$147, $1,283.95$150, /21/10$150,538.48$175,522.25$148, $1,283.95$151, /28/10$151,822.44$177,383.98$150, $1,283.95$153, /5/10$153,106.39$178,205.71$151, $1,283.95$154, /12/10$154,390.34$179,720.78$152, $1,283.95$155, /19/10$155,674.30$181,030.41$154, $1,283.95$156, /26/10$156,958.25$182,275.85$154, $3,586.58$160, /2/10$160,544.83$187,655.72$155, $16,783.89$177, /9/10$177,328.72$208,299.90$156, $29,507.11$206, /16/10$206,835.83$236,036.59$159, $15,599.00$222, /23/10$222,434.83$254,911.38$167, $8,344.50$230, /30/10$230,779.33$265,342.00$183, $7,122.50$237, /6/10$237,901.83$272,820.63$213, $32,548.75$270, /13/10$270,450.58$315,134.00$225, $24,969.75$295, /20/10$295,420.33$346,096.49$235, $20,051.50$315, /27/10$315,471.83$374,168.59$244, $59,750.00$375, /4/10$375,221.83$435,711.09$275, $54,639.20$429, /11/10$429,861.03$501,824.52$290, $6,946.00$436, /18/10$436,807.03$510,645.94$315, $21,260.20$458, /25/10$458,067.23$526,378.49$386, $15,688.60$473, /1/10$473,755.83$545,832.35$432, $10,015.00$483, /8/10$483,770.83$554,946.00$445, $7,978.85$491, /15/10$491,749.68$566,914.27$467, $4,924.62$496, /22/10$496,674.29$572,577.58$475, $4,924.62$501, /29/10$501,598.91$579,275.06$483, $3,548.78$505, /6/10$505,147.69$581,865.67$488, $12,113.14$517, /13/10$517,260.83$592,404.10$495, $18,555.00$535, /20/10$535,815.83$616,896.70$498, $19,719.14$555, /27/10$555,534.98$633,066.40$501, $3,634.86$559, /3/11$559,169.83$637,210.14$505, $514, $528, $539, $559,169.83

Project Control Actual costs and durations were created using a random number generator and a predetermined reasonable range of error for each activity Project is over cost and behind schedule at completion Final Budgeted Cost = $559, Final Actual Cost = $637, Expected Duration = 34 Weeks Actual Duration = 38 Weeks

Project Control

At Week 27 WEEK 27 CPI 0.82 SPI 0.95 CV -$99, SV -$24, EAC $678, VAC -$118, ACWP $566, BCWS $491, BCWP $467,480.39

Procurement Plan ItemShop Drawing Submittal Date Fabrication Lead TimeOrder Date Delivery DateInstall Date RebarDevelop Bar List by May 4th1-2 WeeksMay 18thMay 25thMay 27th Brick 3-4 WeeksOct 13thNov 3rdNov 5th Steel 3-4 WeeksJul 29thAug 19thAug 23rd TrussesAug 11th3-4 WeeksAug 25thSept 15thSept 17th Shingles 1 WeekNov 9thNov 16thNov 18th Windows 4-5 WeeksSept 29thOct 27thOct 29th Exterior/ Interior Doors 5-6 WeeksSept 22ndOct 27thOct 29th Cabinets 3-4 WeeksNov 24thDec 15thDec 17th Plumbing Fixtures 2-4 WeeksDec 2ndDec 16thDec 20th Reilient Floor Tiles 1-2 WeeksDec 14thDec 21stDec 23rd Ceramic Floor Tiles 1-2 WeeksDec 16thDec 23rdDec 27th Manufactured Fireplace 3-4 WeeksNov 24thDec 15thDec 17th