Calculations On completion of this unit the Learner should be able to demonstrate an understanding of: The formula used to calculate: Areas Volumes Ratios Volumes into weight perimeters Mean, Mode, Median and range
Calculations Areas of Rectangles, irregular shapes, circles. Perimeter calculations. Centreline method used to calculate volumes of concrete. Volume for calculating quantities of concrete. Converting volume into tonnage. Mean = average (find the total and divide by the number youy have Mode= most commonly occurring number Median= put the numbers in order and find the middle number Range= difference between highest and lowest number
Surface areas Calculating areas of brickwork and blockwork we are in fact calculating the surface area. Surface areas in construction are calculated to determine quantities of materials required to cover that area. Examples of this are bricks, blocks, floor tiles and block paving. To calculate for these quantities the following procedures should be followed: Calculate the total area to be covered ( m2) Calculate the area of one unit (a brick,block,tile etc). Divide the total area by the area one unit. D) Add percentage to compensate for waste.
Calculate the following areas Formula required to do this is:- Area = L x H = M2 Calculate the area of a wall 7.5m long x 4.5m high with a window opening of 1.200m x 1.050m Answer Formula L x H 7.5m x 4.5m = 33.75m2 – area of window 1.200m x 1.050m = 1.260m2 33.75m2 – 1.260m2 = 32.49m2
Example 1 Calculate the total of 0.100m x 0.200m paving block required to cover the drive area shown below, allow 5% for cutting/waste 8 m 4 m Area = 8 x 4 = 32m2 Area of one paving block = 0.100m x 0.200m = 0.02m2 Total blocks required = 32m2 divided by 0.02m2 = 1600 blocks add 5% for cutting/waste 1600 x 105% = 1680 blocks 100 You will be expected to complete the following calculations. Keep them simple and use the same method each time, ensuring neatness. Complete your calculations using the same method each time.
Answer the following questions Calculate the total 0.3m x 0.3m tiles required to cover the floor area shown below and allow 6% for waste. 6 m 4 m Area = 6 x 4 = 24 m2 Area of one tile = 0.3m x 0.3m = 0.09m2 Total tiles required = 24m2 divided by 0.09m2 = 266.6 tiles add 6% for cutting/waste 266.6 x 106% = 282.596 tiles (round up to 283 tiles) 100
Area of one block = 0.225m x 0.450m = 0.10m2 Calculate the total 0.225m x 0.450m air-rated blocks are required to cover the wall area shown below and allow 8% for waste. 18 m 9 m Area = 18 x 9 = 162 m2 Area of one block = 0.225m x 0.450m = 0.10m2 Total blocks required = 162m2 divided by 0.10m2 =1620 blocks = 1620 blocks + 8% for cutting/waste 1620 x 108% = 1749.6 blocks 100
(A calculator can be used, but show all your workings.) Calculate the area of insulation required for a cavity wall 4.725M long x 2.475M high in which there is a window 1.810M wide x 1.2M high, and allow 5% for wastage. (A calculator can be used, but show all your workings.) Area of wall 4.725m x 2.475m = 11.694m2 Area of window opening 1.810m x 1.2m = 2.172m2 Area of wall – area of window = 11.694m2 – 2.172m2 = 9.522m2 5% allowed for wastage = 9.522m2 x 105% = 9.9981m2 100 Total area of insulation required = 9.9981m2
Calculating the area of irregular shapes 5m Area = Length x Width Length = average of two sides 8 + 5 divided by 2 = 6.5m Length = 6.5m width = 4m 6.5 x 4 = 26m2 4m 8m
Answer the following questions 6.5m 12m 8m 5m 7m 4m Length = average of two sides 7 + 6.5 divided by 2 = 6.75m Length = 6.75m width = 5m 6.75 x 5 = 33.75m2 Length = average of two sides 4 + 12 divided by 2 = 8m Length = 8m width = 8m 8 x 8 = 64m2
10m 4m 3m 7m 8m 2m Length = average of two sides 10 + 2 divided by 2 = 6m Length = 6m width = 7m 6 x 7 = 42m2 Length = average of two sides 8 + 4 divided by 2 = 6m Length = 6m width = 3m 6 x 3 = 18m2
Calculating the volume of concrete. When taking off quantities of brickwork, excavation and concrete for a building, it is essential to calculate the perimeter of the structure. The formula for this differs depending if the internal or external measurements are being used. Here is an alternative method to calculate the volume of concrete required. This is known as the centreline method Using the external measurements The mean perimeter = (2 x L) + ( 2 x W ) Less 4 x Thickness of foundations Using the internal measurements The mean perimeter = (2 x L) + ( 2 x W ) plus 4 x Thickness of foundations
Fig. 1 shows a foundation trench for a building. The trench in fig 1 is 1.2m deep. Calculate the volume of material to be excavated. A Formula when using External dimensions is: (2 x L) + ( 2 x W ) Less 4 x foundation width. Volume = L X W x D = m3 C D 0.75m 8.0m B 10.00m Materials such as concrete will have to be ordered on a weekly basis. When ordering concrete we will have to quote the volume required in this example we would order 29.7 cubic metres of concrete to complete the foundations. Length 2 x 10 = 20 Width 2 x 8 = 16 36m (less 4 x 0.75m) 36m – 3m = 33m 33 x 0.75 x 1.2 = 29.7 m3 of concrete required for this foundation
Fig. 2 shows a foundation trench for a building. Centre-line calculations Fig. 2 shows a foundation trench for a building. The trench in fig 2 is 1.5m deep. Calculate the volume of material to be excavated. A B Formula when using External dimensions is: (2 x L) + ( 2 x W ) Less 4 x foundation width. Volume = L X W x D = m3 C D 3.3m 0.60m A 16.5m Length 2 x 16.5 = 33 Width 2 x 3.3 = 6.6 39.6m (less 4 x 0.60m) 39.6m – 2.4m = 37.2m 37.2 x 0.60 x 1.5 = 33.48m3 of concrete required for this foundation
Centre-line calculations Depth of foundation 0.50m 0.65 4m 10m Formula when using Internal dimensions is: (2 x L) + ( 2 x W ) plus 4 x foundation width. Volume = L X W x D = m3 Length 2 x 10 = 20 Width 2 x 4 = 8 28m (plus 4 x 0.65m) 28m + 2.6m = 30.6m 30.6 x 0.65 x 0.50 = 9.945m3 of concrete required for this foundation. If we calculated the amount of concrete required by the external measurements we would end up with too much concrete this is why we use centre line calculations.
Centre-line calculations 10m 3m The trench is 0.65m wide and 0.50min depth. Calculate the volume of concrete required 7m 4m 6m 4m The formula makes calculating volumes of irregular shaped foundations easier. Length 2 x 10 = 20 Width 2 x 7 = 14 34m (less 4 x 0.65m) = 31.4m 34m – 2.6m = 31.4m 31.4 x 0.65 x 0.5 = 10.205m3 of concrete required for this foundation
Answer the following questions Calculate the quantity of concrete required for this foundation. N.B Width 0.60m depth 0.45m 18m 3m 12m Length 2 x 18= 36 Width 2 x 3 = 6 42m (plus 4 x 0.60m) 42m + 2.4m = 44.4m 44.4 x 0.60 x 0.45 = 11.988m3 of concrete required for this foundation
Answer the following questions Calculate (using the centre line method how many bricks would be required to build the one brick thick inspection chamber. (assume 120 bricks per square metre) depth of brickwork is 0.90m 0.7m 0.91m 12m Length 2 x 0.91m = 1.82m Width 2 x 0.7m = 1.4m 3.22m (plus 4 x 0.225m) 3.22m + 0.9m = 4.12m L D B/M2 4.12 x 0.90 x 120 = 444.96 bricks required to build the inspection chamber
Material which are ordered by weight such as hardcore (per tonne) Material which are ordered by weight such as hardcore (per tonne). To calculate the quantity required we use the following formula. 1. calculate the volume as we do for concrete 2. Use the density method (volume x density) Example An area is to be filled with hardcore. The area is 8.5m long by 4.2m wide. The average depth is 0.15m Calculate the amount of hardcore required Volume = 8.5 x 4.2 x 0.15 = 5.36m3 (2 decimal places) Total amount = Volume x density = tonnage 5.36 x 2.000kg/m3 = 10.72 Tonnes (we would order 11 tonne)
Answer the following questions An area is to be filled with hardcore. The area is 6.70 long by 5.50m wide, with an average depth of concrete of 0.20m Calculate the quantity of hardcore required. (Density = 2.000kg/m3) Total cost of the hardcore at £18 per tonne Remember Volume x density = tonnage Volume = 6.70 x 5.50 x 0.20 = 7.37m3 ( 2 decimal places only) 7.37 x 2.000kg/m3 = 14.74 tonne we would order 15 tonne. 2. Cost 15 x £18 = £270.00
An area is to be filled with hardcore. The area is 8. 5m long by 4 An area is to be filled with hardcore. The area is 8.5m long by 4.2m wide. The average depth is 0.15m Calculate the amount of hardcore required (Density = 2.000kg/m3) Remember Volume x density = tonnage Volume = 8.5 x 4.2 x 0.15 = 5.36m3 ( 2 decimal places only) = 5.36 x 2.000kg/m3 = 10.72 Tonnes we would order = 11 Tonne.
An area is to be filled with concrete. The area is 10. 5m long by 6 An area is to be filled with concrete. The area is 10.5m long by 6.1m wide. The average depth is 0.55m Calculate the amount of concrete required (Density = 2.400kg/m3) Remember Volume x density = tonnage Volume = 10.5 x 6.1 x 0.55 = 35.22m3 ( 2 decimal places only) = 35.22 x 2.400kg/m3 = 84.52Tonnes we would order = 85 Tonne.
Ratios of materials Material such as concrete as mixed together in ratios. A typical mix for concrete would be a 1:3:6 mix this means that 1 Portion of cement is required 3 portions of fine aggregate (sharp sand) 6 portions of course aggregate To produce the required specified mix of concrete. It is relatively easy to work out volume of concrete Volume = (L x W x D). From the volume we would then need to break this down into the proportions of material required to complete the concrete structure.
Example 1 Total portions is 1: 3: 6 = 10 Average density of concrete is 2400 kg/m3 (2.4 tonne of aggregate to produce a cubic meter of concrete) Divide 2400 by 10 = 240kg therefore 1 portion of cement = 1 x 240 = 240kg 3 portions of fine aggregate = 3 x 240 = 720kg 6 portions of course aggregate = 6 x 240 = 1440kg Are required to produce 1m3
Example 2 N.B Ratio of facings to commons (that is 3 facings to every 1 common) Flemish bond is specified by the customer to construct a wall 23.6 long by 1.36 in height. Calculate the amount of facings and commons that would be required to complete this. Area of wall 23.6 x 1.36 = 32.095m2 Total no of bricks required = 32.095 x 120 = 3851.52 bricks (120 bricks per m2 in any one brick wall) Add together 3 and 1 together = 4 Therefore divide 3851.52 by 4 = 962.88 (is equal to one portion) Commons 1 x 962.88 = 962.88 bricks Facings 3 x 962.88 = 2888.64 bricks check = 3851.52 total
Flemish bond is specified by the customer to construct a wall 15m long by 2m in height. Calculate the amount of facings and commons that would be required to complete this. Area of wall 15m x 2m = 30m2 Total no of bricks required = 30 x 120 = 3600 bricks (120 bricks per m2 in any one brick wall) Add together 3 and 1 together = 4 Therefore divide 3600 by 4 = 900 (is equal to one portion) Commons 1 x 900 = 900 bricks Facings 3 x 900 = 2700 bricks check = 3600 total
Calculating diagonals Remember the formula for working out diagonal dimensions is: A2 + B2 Dimension C = ? Dimension B = 8m Being able to calculate the dimension of diagonals is a useful tool for most trades persons. Bricklayers can use this to check of a corner has been set out correctly (square) for example during the setting out of a building onto foundations. Using a builders square and string lines is not a particularly accurate method. A = 10 x 10 = 100 B = 8 x 8 = 64 100 + 64 = 164 square root of 164 √164 = 12.8m length of dimension C = 12.8 m Dimension A = 10m
Calculating diagonals Remember the formula for working out diagonal dimensions is: A2 + B2 Dimension C = ? Dimension B = 7m Being able to calculate the dimension of diagonals is a useful tool for most trades persons. Bricklayers can use this to check of a corner has been set out correctly (square) for example during the setting out of a building onto foundations. Using a builders square and string lines is not a particularly accurate method. A = 12 x 12 = 144 B = 7 x 7 = 49 144 + 49 = 193 square root of 193 √193 = 13.89m length of dimension C = 13.89m Dimension A = 12m
The diagram shows a section through a roof. (Note rafter AB = AC2 + BC2) A Rise of roof 2.100m Calculation AC2 = 2.100 x 2.100 = 4.41m2 BC2 = 2.500 x 2. 500 = 6.25m2 AC2 + BC2 = 4.41 + 6.25 = 10.66 √ 10.66 3.26m is the length of rafter AB B C This is a useful formula as we can use it when setting out to check if a building is square or as in this case to find the length of materials. 2.500m Half of total roof span
√ 58 = 7.61m is the length of the diagonal X The diagram below shows a foundation of a building in the process of being set out. Calculate the length of X mathematically to ensure that the conservatory is square to the rear elevation of the building. A (Note length of X = √ AC2 + BC2) X 7m conservatory 3m 900 B C Calculation AC2 = 7m x 7m = 49m2 BC2= 3m x 3m = 9m2 AC2 + BC2 = 49 + 9 = 58 √ 58 = 7.61m is the length of the diagonal X The main building is always set-out first and the porch or other projecting part of the building is set-out from this. Using this formula a bricklayer can check the position of the corner of the porch by calculating the length of the diagonal X.
Calculating areas of triangles The formula required to do this is :- Area = ½ Base dimension x Height = m2 Tradespersons need to be competent at calculating materials in order to submit accurate estimates. If we were to submit estimates by guessing quantities this would lead us to either not getting the job in the first place (overpriced estimate) or having to order extra materials which may lead to having no money left for wages. The most successful builders among us will be able to accurately estimate projects. A triangular is a common shape that we construct. For example we would use this formula when calculating materials required to construct a gable end. 10m Base 8 ÷ 2 = 4 4 x 10 = 40m2 8m
Calculate the areas of triangles below 8m 12.3m 19.5m 7m 12m 37.7m Now that we are able to work out the area it is simple to then multiply this number by the amount of bricks or blocks that is required to build a m2 We know that a half brick wall consists of 60 bricks per m2. Therefore if triangle A ) was a brick gable all we need do is multiply the area of the triangle by 60 this would provide us with the bricks required for construction of the gable. 28 x 60 = 1680 bricks A) Base = 7 ÷ 2 = 3.5m 3.5 x 8 = 28m2 B) Base = 12 ÷ 2 = 6m 6 x 12.3 = 73.8m2 C) Base = 37.7 ÷ 2 = 18.85m 18.85 x 19.5 = 367.5m2
Calculating the area of a circle The distance around a circle is called its circumference. circumference The distance across a circle is called its diameter. diameter The distance of half the diameter is called the radius. Radius For any size of circle, if you divide the circumference by its diameter, the value of 3.14 will be the answer. This is called (Pi). There are many reasons that a bricklayer may need to work out areas of circles. You may be asked to tender for jobs that have circular windows within the structure or other circular features. Depending on the information that we are supplied with will change the formula we use. The following examples will help you to complete the set questions. R = 3in Example 1. The radius of a circle is 3 in. What is its area ? Area of circle = (Pi) x R x R = 3.14 (Pi) x 3 x 3 = 28.26 inch 2
Calculate of the areas of the circles below. R = 10cm Area of circle = (Pi) x R x R (Pi) = 3.14 x 10 x 10 = 314cm 2 Area of circle = (Pi) x R x R (Pi) = 3.14 x 4 x 4 = 50.24m 2 R = 4.0m
Example 2. The diameter of a circle is 8 cm. What is its area ? Solution D = 8 R = D divided by 2 = 4cm Area = (Pi) 3.14 x 4 x 4 = 50.24 cm2 D = 8 cm Basic rule is to use the radius to calculate the area of a circle, therefore if a question only has the diameter size then dividing by 2 supplies us with the radius size.
Calculate of the areas of the circles below. D = 15m R = D divided by 2 = 7.5m Area = (Pi) 3.14 x 7.5 x 7.5 = 176.625m2 D = 15m D = 300mm R = D divided by 2 = 150mm Area = (Pi) 3.14 x 150 x 150 = 70650mm2 D = 300mm
The diameter of a circle is 12 in. What is its area ? The radius of a circle is 9cm. What is its area ? R= 9cm Area of circle = (Pi) x R x R 3.14 x 9 x 9 = 254.34 cm2 The diameter of a circle is 12 in. What is its area ? D = 12 in Area of circle = D divided by 2 = radius (Pi) x R x R 3.14 x 6 x 6 = 113.04 in2 The radius of a circular pool is 4ft. What is its area ? R= 4ft Area of circle = (Pi) x R x R 3.14 x 4 x 4 = 50.24 ft2
Example 3. The area of a circle is 78.5m2. What is its radius ? Solution Area divided by (Pi) = R x R 78.5m2 ÷ 3.14 = 25 25 = R x R Therefore the square root of 25 will give us size of the radius. We now need to find the square root of 25. Finding the square root of a number is the inverse operation of squaring that number. Remember, the square of a number is that number times itself. I.e the square root of 10 is 10 x 10 which = 100 We can do this with the aid of a calculator by simply pressing the symbol after entering the square number. So the answer for the sum above is : 25 = 5
The figure opposite shows a plan view of a timber floor. The floor area is 64.28m2 86.13m2 100.28m2 158.14m2 R =3m 6m Area of rectangle = L x H = m2 12 x 6 = 72m2 + area of circle Area of circle = (Pi) x R x R 3.14 x 3 x 3 = 28.26 m2 Answer = 72 + 14.13 = 86.13 m2 This is a typical exam question. They are trying to catch you out! We need to divide the area of the circle in half as we have already calculated half of it as it is incorporated in the rectangle. 12m
Example 1 Calculate the total cost of the materials below from the prices given. Allow 17.5% VAT 1500 Facing bricks are required to construct a wall @ £230/ 1000 calculate the cost of 1500 bricks Calculate cost of bricks + vat 1. Cost of bricks = 1500 x £230 = £345.00 1000 2. VAT= 345 x 117.5% = £405.375 (cost of bricks including vat) 100
Example 2 Calculate the total cost of materials using the prices given, allowing 17.5% VAT 400 concrete blocks are required to construct a wall @ £6.50/ 10 calculate the cost of 400 blocks Calculate cost of blocks + vat 100mm Concrete blocks required @ £6.50/ 10 Cost of blocks = 400 x £6.50 = £260.00 10 VAT = 260 x 117.5% = £305.50 (cost of blocks including vat) 100
Calculate the total cost of materials using the prices given, allowing 17.5% VAT A) 2100 Facing Bricks required @ £247/ 1000 Cost of bricks = 2100 x £247 = £518.70 1000 VAT 518.70 x 117.5 = £609.47 (total cost of bricks including vat) 100
Calculate the total cost of materials using the prices given, allowing 17.5% VAT B) 650 100mm Concrete Blocks required @ £4.95/ 10 Cost of blocks = 650 x £4.95 = £321.75 10 VAT 321.75 x 117.5 = £378.05 (total cost of blocks including vat) 100
Calculate the total cost of materials using the prices given, allowing 17.5% VAT C) 3.5 Tonne Building Sand required @ £18/ Tonne Cost of sand = 3.5 x £18 = £63.00 VAT 63.00 x 117.5 = £74.02 (total cost of sand including vat) 100
Calculate the total cost of materials using the prices given, allowing 17.5% VAT D) 250 Wall Ties required @ £17.00/ 100 Cost of wall ties = 250 x £17.00 = £42.50 100 VAT 42.50 x 117.5 = £49.93 (total cost of wall ties including vat)
Assessment questions Question 1 Calculate the total number of bricks required to build the ½ B wall shown, allowing 5% waste. Main area – door and window 1) 12.00m x 3.00m = 36m2 Door = 2.00m x 1.00m = 2m2 Window = 2.00m x 1.50m = 3m2 36m2 – 5m2 = 31m2 2) 31 x 60 = 1860 bricks 1860 x 105 = 1953 bricks including waste 100
Question 2 The uppermost part of a gable wall forms the shape of a triangle. Calculate the total number of bricks required to build the ½ B gable wall shown, add 3 ½% for waste. Area of a triangle = half base x height 9 divided by 2 = 4.5m x 2.0m = 9 m2 9 x 60 = 540 bricks + 3.5 % waste 540 x 103.5 = 558.9 bricks (round up to 559) 100
Question 3 An area is to be filled with hardcore. The area is 6.70m long by 5.50m wide. The average depth of hardcore is 0.20m. 1) Calculate the amount of hardcore required. (Density = 2.000kg/m3) 2) Total cost of the hardcore at £30 per tonne, including VAT at 17 ½ % Area to be filled with hardcore = 6.70 x 5.50 x 0.20 = 7.37m3 Volume x density = tonnage 7.37m3 x 2.000 = 14.74 tonnes (round up to 15 tonnes) 15 x £30 = £450.00 450 x 17.5 = 78.75 100 total cost = 450 + 78.75 = £528.75
Question 4 An area is to be filled with hardcore. The area is 7.00 long by 5.50m wide, with an average depth of 0.20m 1. Calculate the quantity of hardcore required. (Density = 2000kg/m3) 2. 2. Total cost of the hardcore at £27 per tonne Area to be filled with hardcore = 7.00m x 5.50m x 0.20m = 7.7m3 Volume x density = tonnage 7.7m3 x 2.000 = 15.4 tonnes (round up to 16 tonne) 16 x £27= £432
Question 5 Calculate the area of the circle which has a radius of 9m. Area of circle = (Pi) x R x R = m2 3.14 x 9 x 9 = 254.34m2
Question 6 1750 Facing bricks are required to construct a wall @ £320/ 1000 1. calculate the cost of 1750 bricks 2. Calculate cost of bricks + 17.5 % vat 1750 x 320 = £560 1000 560 x 117.5 = £658 100
Formula when using External dimensions is: (2 x L) + ( 2 x W ) Less 4 x foundation width. Volume = L X W x D = m3 Question 7 Calculate the concrete required for the foundation shown below, given that the trench width is 0.4m and the concrete is to be 0.5m deep. N.B all measurements are external 6 x 2 = 12m 4 x 2 = 8m Less 4 x width of foundation 4 x 0.4m = 1.6m 12m + 8m = 20m – 1.6m = 18.4m Volume 18.4 x 0.4 x 0.5 = 3.68m3
Question 8 Calculate the area of the circle which has a diameter of 29m. Diameter divided by 2 = radius Area of circle = (pi) x R x R 3.14 x 14.5 x 14.5 = 660.18 m3 Question 9 Add the following dimensions together 1240mm + 1.2m + 2m +1537mm 1.240 1.200 2.000 1.537 5.977m or 5977mm
Question 10 An area which has a length of 16m and width of 9m requires tiling. 1) Calculate the number of 0.100m x 0.200m tiles required to cover the area. 2) Add 13% for waste Area to be tiled = 16m x 9m = 144m2 Area of one tile = 0.100m x 0.200 = 0.02m2 144m2 divided by area of one tile = 144 divided by 0.02 = 7200 Add 13% for waste 7200 x 113 = 8136 tiles required 100