NATIONAL GPAR PROGRAMME 2011-2015: INITIATION PLAN PRESENTATION TO LOCAL PROJECT APPRAISAL COMMITTEE June 23, 2011.

Slides:



Advertisements
Similar presentations
Ministry of Public Sector Development Public Sector Development Program Better Government Delivering Better Result.
Advertisements

19-20 September 2013, IBGE, Rio de Janeiro, Brazil
Delivering as One UN Albania October 2009 – Kigali.
Enhanced Integrated Framework for Trade-Related Technical Assistance to Least Developed Countries (EIF) IF Programme Implementation Unit (PIU) World Trade.
IFAD’s regional communication strategy for Western and Central Africa.
1 Aligning the work of the SWGs to support health policy making/reform Experiences from the health sector.
Process and Requirements of the Accreditation of National Implementing Entities for Direct Access under the Adaptation Fund for the Pacific Sub Region.
1 Assessment of Cambodia’s Statistics Capacity Prepared by Zia A. Abbasi IMF Multi-sector Statistics Advisor, Cambodia for the International Conference.
Inita Paulovica Deputy Resident Representative Turkmenistan.
THE NATIONAL FOREST PROGRAMME FACILITY
Introducing Regulatory Impact Analysis into the Turkish Legal Framework Prime Minister’s Office, Better Regulation Group The Project Implementation Team.
MID-TERM REPORT FOR THE UGANDA IAP PROJECT By Telly Eugene Muramira Director; Policy, Planning and Information NATIONAL ENVIRONMENT MANAGEMENT AUTHRORITY.
Lao PDR PAR & Decentralisation in LAO PDR: Problems and Prospects ( Presentation Bratislava Conference, 20 th April 2004) Presentation by: Bikash Ranjan.
System of Environmental-Economic Accounting SEEA Implementation Guide and Diagnostic Tool Alessandra Alfieri UNSD.
Consultant: Mamadou Talla 1. Rationale of the PRTSR Having recognized that: The first-generation Poverty Reduction Strategies (PRSs) did not take into.
System of Environmental-Economic Accounting SEEA Implementation Guide and Diagnostic Tool and Suggested Structure for Assessment United Nations Statistics.
ECP Workshop, Ankara, September 2012 Development of CPF Dinara Rakhmanova Assistant FAO Representative Kyrgyz Republic Priority areas for FAO assistance.
Midterm Review of Economic Reform and Diversification Sector 22 – 23 June 2009, Baghdad.
Project Implementation Plan and Principal Activities
Project Overview, Objectives, Components and Targeted Outcomes
The Project Governance Inception Workshop and the First Steering Committee Meeting of the UNEP/GEF Project “Piloting Integrated Processes and Approaches.
Project Implementation in ECLAC & ESCAP Region Workshop on Informal Employment and Informal Sector Data Collection: Strategy, Tools and Advocacy
Session 13 CPIP Formulation Process Project for Capacity Development for Implementing the Organic Law at the Capital and Provincial Level (PILAC 2)
Joint Programme Enhancing judicial reform in the Eastern Partnership countries Judicial component.
N° 1 Directorate General for Energy and Transport Preparation of the Green Paper on Urban Transport Brussels, June 2007 Marcel Rommerts Clean Transport.
Country Presentation- GEF Operational Focal Point, Sri Lanka GEF Sub-Regional Workshop 2-3 December 2007, Bali, Indonesia Anura Jayatilake Director, Environmental.
Report on the Evaluation Function Evaluation Office.
Food and Agriculture Organization of the United Nations TCP/RER/3402 (D) Assistance to Western Balkan Countries for Improving Compliance to International.
February 21, JAS Consultation between the Government of Tanzania and Development Partners February 21, 2006 Courtyard Hotel, Dar es Salaam.
Experiences in Strategic Statistical Planning – Statistical Institute of Jamaica (STATIN) – The Modernization of STATIN Presented by Annette McKenzie Deputy.
VIETNAM STATISTICAL DEVELOPMET STRATEGY , VISION TO 2030 (VSDS) Presented by: Nguyen Van Doan Director, Institute of Statistical Science GSO December,
Development process / consultation National Water Strategy V A N U A T U.
Preparation of a Strategic Pilot Program for Climate Resilience (PPCR) Project - Phase I (November January 2013) Climate Investment Funds (CIF) Grant.
9-10 December GPAR Luang Prabang ARM 2010 GPAR LP II GPAR Luang Prabang Phase II: Decentralized Participatory Governance and Service Delivery Reform.
CIVILIAN SECRETARIAT FOR POLICE STATUS REPORT ON IMPLEMENTATION OF THE CIVILIAN SECRETARIAT FOR POLICE SERVICE ACT 2 OF 2011 PORTFOLIO COMMITTEE ON POLICE.
1 Preparation of Six-Year ED Sector Programme Cycle and its 1st biennium Advantages -Real alignment of biennial C/5 (within 6-year ED Programme Cycle)
DANIDA’s Experience of Results Managing for Development Results Peter Ellehøj – Quality Assurance Department November 2011.
Bosnia and Herzegovina Ministry of Finance and Treasury Planned Piloting of Sector-Wide Approaches (SWAps) in BiH Dusanka Basta, MoFT and Richard Moreton,
Session 2 Laws and Regulations Project for Capacity Development for Implementing the Organic Law at the Capital and Provincial Level (PILAC 2)
Community Development Workers: Progress Report Report to the Parliamentary Portfolio Committee on Public Service and Administration, 22 June 2005.
MedLiHer Contribution to Implementing the Convention for Safeguarding of the ICH in Mediterranean Countries Phase II Evaluation Meeting Cairo – Egypt 28-30/11/2010.
Eurostat/UNSD Conference on International Outreach and Coordination in National Accounts for Sustainable Development and Growth 6-8 May, Luxembourg These.
Preparatory Stakeholder Workshop - Laos 26 May 2010.
INTERACTIVE TRAINING ON IDP FOR COUNCILLORS ________________________
‘ By Abdou Karim LO Minister of State for Reform and Technical Assistance AfCoP/MfDR Co-Chair.
THE MKUKUTA AND MDGs, IMPLEMENTATION FRAMEWORK AND MONITORING. A Paper presented at the Development Partners Seminar held in Dar es Salaam on 25 th October,
SPC Advisory Committee Training Fall 2015 Institutional Research President’s Office SPC 10/9/20151.
Forum on National Plans and PRSPs IN EAST ASIA Forum on National Plans and PRSPs IN EAST ASIA April 4 - 6, 2006, Vientiane, LAO PDR By Ms. Heang Siek Ly.
Joint Assistance Strategy for Tanzania (JAST) Poverty Policy Week Creative and Hard Work, the Key to Fighting Poverty Presentation by the Ministry of Finance.
Cambodia Export Diversification and Expansion Program (CEDEP) I By: Sylvie Bétemps Cochin, Trade Promotion Officer, ITC Date:13 December 2012 Overview.
Cluster Bankable Programmes, Budget Process and ARTF M Mustafa Mastoor Deputy Minister for Finance.
Highlights Progress & Challenges Priorities for Branch: Climate Change Portfolio Committee Workshop – January 2011.
Strategic approach to national implementation programmes for SEEA by UNSD Sixth Meeting United Nations Committee of Experts on Environmental Economic Accounting.
Ministry of Finance National Strategic Reference Framework Communication Strategy 20 June 2008 Second NSRF Monitoring Committee Zornitsa Arsenieva Advisor.
1 Briefing for Schools and Education Department Lisa Bibby Director Schools and Education 16/ 19 November 2012.
ASSESSING LONG-TERM STRATEGIC DOCUMENTS WITH THE EU PERSPECTIVE Supreme Audit Office Poland Slawomir Grzelak Director, Department of Economy,
Project Debriefing Debriefing meeting on the implementation status of two ADB- JFPR funded projects: (i) Technical Assistance Strengthening Coordination.
Aziz Aaliev, Food security expert, Kyrgyz Republic
IMPLEMENTATION OF THE Agenda 2030 in the Czech Republic
Implementation of the IPS MDTF
Ministry of Planning & Economic Affairs
Open and inclusive budgeting: Working beyond boundaries
Dr. Arounyadeth Rasphone Deputy Director General
United Nations Development Programme
COORDINATION OF FOREIGN ASSISTANCE IN THE REPUBLIC OF MACEDONIA
Gas Regional Initiative
UN Support to SDG implementation in Seychelles.
The role of the Passport Indicators in Monitoring PFM Strategy
Annual Meeting of the Directors of the NSIs of the Mediterranean ENP Countries Updating on the first project of regionally coordinated migration surveys.
Forum on National Plans as Poverty Reduction Strategies in East Asia National Strategic Development Plan (NSDP), & Public Investment Program.
Presentation transcript:

NATIONAL GPAR PROGRAMME : INITIATION PLAN PRESENTATION TO LOCAL PROJECT APPRAISAL COMMITTEE June 23, 2011

Initiation Plan – Local Appraisal  National GPAR Programme : formulation in 2011  Preparatory steps initiated by Govt. through GPAR SBSD  Intensive efforts to complete formulation & launch  UNDP assistance through Initiation Plan project  Initiation Plan project document prepared for review  Initiation Plan project being presented to LPAC

GPAR Programme Background Initiated as support to Prime Minister’s Office in 1994 as small PAR project Expanded to GPAR from 1997, followed by two phases and now GPAR SBSD Provincial projects initiated in 2001, implemented independent from central GPAR, in five provinces Supported government mainly on policy development and piloting e.g ODS, DDF also quality of public services as CRC survey GPAR is one of the largest projects of the Govt. in terms of spread of activities

Key Lessons Learned Need for a programme approach integrating all aspects of governance reform and capacity development Important to scale up successful projects and widely implement the policies that have been improved Integrate new approaches into regular work of government and reduce the use of project modality

Update on Progress in Formulation New Programme concept shared with PSISSWG in 2010 New Programme formulation team organized in second half of 2010 Programme formulation mission in January 2011, and report by March 2011 Internal review of draft programme and alignment with Strategic Plan on Governance as well as PACSA proposals for 7 th NSEDP Internal review and revision by PACSA and initial discussion with key ministries completed Agreement with UNDP to set up Initiation Plan support

Purpose of the NGPAR IP Project GPAR SBSD in final stages: extended to complete strategic outputs with limited remaining resources Fresh resources and intensive effort required to complete formulation and launch of new Programme IP Project during period June to – December 2011 will: support the detailed formulation of projects under the Programme and implementation arrangements support the consultations and dialogue that will accompany the formulation ensure adequate awareness of the new GPAR Programme and related policies and priorities among stakeholders

Outputs of the NGPAR IP Project Four outputs of the NGPAR IP project 1.Operational and management arrangements for the national GPAR Programme 2.Detailed project documents, activity plan and implementation arrangements for the projects 3.Awareness of the Strategic Plan on Governance among stakeholders 4.Governance Sector Working Group reports for Round Table Implementation Meeting 2011

Output 1: Programme Arrangements Output 1: Operational & management arrangements for the national GPAR Programme Action 1: Technical assistance to prepare operational & management arrangements Action 2: Consultations to prepare operational & management arrangements

Output 2: Project Documents Output 2: Detailed project documents, activity plan and implementation arrangements for the projects Action 1: Technical assistance to prepare project documents, activity plans and implementation arrangements Action 2: Consultations to prepare project documents, activity plans and implementation arrangements

Output 3: Awareness Building Output 3: Awareness of the Strategic Plan on Governance among stakeholders Action 1: Publish and disseminate Strategic Plan on Governance Action 2: Dissemination workshops with key stakeholders on the Strategic Plan on Governance

Output 4: Sector Working Group Output 4: Governance Sector Working Group reports for Round Table Implementation Meeting 2011 Action 1: Prepare Sector Working Group reports for RTIM 2011 and work plan for 2011 Action 2: Meetings and workshops of the Governance Sector Working Group reports during 2011

Management Arrangements Project Manager Director General, Civil Service Mgmt., PACSA Project Manager Director General, Civil Service Mgmt., PACSA Project Board Senior Beneficiary Min of Plng. & Inv Min. Of Finance Senior Beneficiary Min of Plng. & Inv Min. Of Finance Executive Vice Chairperson, PACSA Executive Vice Chairperson, PACSA Senior Supplier UNDP SDC Embassy of Luxembourg Senior Supplier UNDP SDC Embassy of Luxembourg Project Assurance Governance Unit, UNDP Project Assurance Governance Unit, UNDP Project Support Technical Advisor Project Support Technical Advisor TEAM A HR Coordinator TEAM A HR Coordinator TEAM C Finance Officer TEAM C Finance Officer TEAM B

IP Project Budget OutputResources allocated Output 1: Programme Arrangements$30,000 Output 2: Project Documents$120,000 Output 3: Awareness Building$22,000 Output 4: Sector Working Group$68,000 TOTAL$240,000

THANK YOU FOR YOUR ATTENTION