DiriPark Parking Guidance System Milestone Presentation Red Team — CS 410 Spring 2009 April 9, 2009
Who We Are April 9, 20092DiriPark — Milestone Presentation Mark Bullard Project Lead, Marketing Administrative Steven Murray Risk Mitigation Garnett Wilson Financial Specialist Technical Dominic Eldridge Software Developer Gabor Eszes Web Developer Thomas Suiter Hardware Specialist
Outline Parking Problem Characteristics Solution Proposal Technical Features Phase Breakdown Business Model Risks and Mitigation Evaluation Plan Appendices April 9, 20093DiriPark — Milestone Presentation
Available parking spaces are difficult to locate in a parking garage April 9, 20094DiriPark — Milestone Presentation
According to the US Department of Transportation Drivers slow down, circle around Creates congestion, wastes time Results in frustration, loss of revenue April 9, 20095DiriPark — Milestone Presentation Source: [1] US Department of Transportation
April 9, 2009DiriPark — Milestone Presentation6
Problem Effects Facility operators and local businesses lose $ 3 to $ 5 per vehicle on hourly rates $ 10 per day $ 150 per shopper April 9, 20097DiriPark — Milestone Presentation Source: [2] Reuters
Affected Enterprises Airports Dining Hospitals Sport stadiums April 9, 20098DiriPark — Milestone Presentation Convention centers Entertainment venues Retail Universities Highly trafficked parking facilities High congestion Time-constrained settings
U.S. Parking Establishments Grand Total: 15,280 facilities April 9, 2009DiriPark — Milestone Presentation9 Source: [3] IBISWorld
Our Goal Provide a space availability system that is: – Flexible – Intuitive – Real-time April 9, 2009DiriPark — Milestone Presentation10
Solution Technical Objectives Establish a sensor array that collects real-time information about space availability Calculate ideal zones for parking based on sensor input and optional historical data Convey zone recommendations to patrons via display devices April 9, 2009DiriPark — Milestone Presentation11
DiriPark Parking Guidance System April 9, 2009DiriPark — Milestone Presentation12 Locate Predict Display
Solution Characteristics 1.Patron enters garage 2.System locates empty spaces 3.System predicts short-term availability 4.System displays top choices on screen 5.Patron is directed to spot and parks April 9, DiriPark — Milestone Presentation
April 9, 2009DiriPark — Milestone Presentation14
April 9, 2009DiriPark — Milestone Presentation15 DiriPark
April 9, DiriPark — Milestone Presentation
Prototype Design April 9, 2009DiriPark — Milestone Presentation17
Benefits For Customer Increased business Enhanced marketability Less garage congestion Reduced illegal parking For End User Faster parking Less frustration Expectations satisfied April 9, 2009DiriPark — Milestone Presentation18
Drawbacks Patron unfamiliarity Periodic maintenance April 9, DiriPark — Milestone Presentation
Objectives Outside of Scope No enforcement of recommendations No reservations No remote access April 9, DiriPark — Milestone Presentation
April 9, 2009DiriPark — Milestone Presentation21 Phase 0 CS 410
Conception – Determine Team Members – Define Project – Conduct Project Research – Determine Solution Requirements Analysis – Conceptualize Project Solution Presentations April 9, 2009DiriPark — Milestone Presentation22 Phase 0 Milestones
Feasibility Presentation – Market Analysis – Financial – Hardware Capability Research – Algorithm Design – Risk Mitigation Milestone Presentation – Documentation Final Presentation – Create SBIR April 9, 2009DiriPark — Milestone Presentation23 Phase 0 Presentations
Red Team Experts April 9, DiriPark — Milestone Presentation Mark Bullard Project Lead, Marketing Administrative Steven Murray Risk Mitigation Garnett Wilson Financial Specialist Technical Dominic Eldridge Software Developer Gabor Eszes Web Developer Thomas Suiter Hardware Specialist Kevin Gallagher Parking Department City of Hampton Kevin Gallagher Parking Department City of Hampton James Long Parking Services Old Dominion University James Long Parking Services Old Dominion University Phase 0 – Staffing
Online Discussion Board Weekly Team Meetings April 9, 2009DiriPark — Milestone Presentation25 Phase 0 Communication
Resources CS Server Rapid prototyping – Mockups – Simulated data Costs N/A April 9, 2009DiriPark — Milestone Presentation26 Phase 0 Resources and Costs
Phase 1 CS 411 April 9, 2009DiriPark — Milestone Presentation27
Prototype Development –Product WBS –Prototype Product Specification –Prototype Test Plan/Procedures Prototype Demonstration –Prototype Presentation 1 –Final Prototype Demonstration Documentation Website April 9, 2009DiriPark — Milestone Presentation28 Phase 1 Milestones
Hardware – Server – Sensors – Vehicle Counter – Display Method Software – Database – Algorithm April 9, 2009DiriPark — Milestone Presentation29 Phase 1 Prototype Design
Red Team Experts Phase 1 – Staffing April 9, DiriPark — Milestone Presentation Mark Bullard Project Lead, Marketing Administrative Steven Murray Risk Mitigation Garnett Wilson Financial Specialist Technical Dominic Eldridge Software Developer Gabor Eszes Web Developer Thomas Suiter Hardware Specialist Kevin Gallagher Parking Department City of Hampton Kevin Gallagher Parking Department City of Hampton James Long Parking Services Old Dominion University James Long Parking Services Old Dominion University Hussein Abdel-Wahab Systems Programming Expert Old Dominion University Hussein Abdel-Wahab Systems Programming Expert Old Dominion University Irwin Levinstein Database Consultant Old Dominion University Irwin Levinstein Database Consultant Old Dominion University
Resources – Database license – Custom developed software – Purchased sensor hardware – CS Server – Test harness Costs – Employee wage $ 15 / hour April 9, 2009DiriPark — Milestone Presentation31 Phase 1 Resources and Costs
Phase 2 Critical Design April 9, 2009DiriPark — Milestone Presentation32
Phase 2 Milestones Hardware – Server – Sensors – Vehicle Counter – Display Method Software – Database – Algorithm April 9, 2009DiriPark — Milestone Presentation33
Red Team Experts Phase 2 – Staffing April 9, DiriPark — Milestone Presentation Mark Bullard Project Lead Administrative Steven Murray Marketing Specialist Garnett Wilson Financial Specialist Technical Dominic Eldridge Software Developer Gabor Eszes Web Developer Thomas Suiter Hardware Specialist Software DeveloperSystem Administrator Kevin Gallagher Parking Department City of Hampton Kevin Gallagher Parking Department City of Hampton James Long Parking Services Old Dominion University James Long Parking Services Old Dominion University Hussein Abdel-Wahab Systems Programming Expert Old Dominion University Hussein Abdel-Wahab Systems Programming Expert Old Dominion University Irwin Levinstein Database Consultant Old Dominion University Irwin Levinstein Database Consultant Old Dominion University
Resources – TBD Costs – Software Developer $ 75,000 – Project Lead $ 100,000 – Web Developer $ 60,000 – Financial Specialist $ 62,000 – Marketing Specialist $ 62,000 – System Administrator $ 75,000 April 9, 2009DiriPark — Milestone Presentation35 Phase 2 Resources and Costs
Phase 3 Production Out-years April 9, 2009DiriPark — Milestone Presentation36
Phase 3 Production Out-years Finalize First Sale Collect Customer Feedback Continue Targeted Marketing Provide Product Support April 9, 2009DiriPark — Milestone Presentation37
Phase 3 – Staffing April 9, DiriPark — Milestone Presentation Project Lead Administrative Customer Service Representative Financial Specialist Marketing Professional Technical On-site Hardware Support Software Developer System Administrator
Resources – TBD Costs System Administrator $ 75,000 Software Developer $ 75,000 Financial Specialist $ 62,000 Customer Service Rep $ 42,000 Project Lead $ 100,000 April 9, 2009DiriPark — Milestone Presentation39 Phase 3 Resources and Costs
Price Point for garage of 500 spaces ItemQuantityCost Sensors500 $ 150,000 Wireless Access Point10 $ 4,000 Network Switch1 $ 3,500 OS LicenseFree & Open Source Database LicenseFree & Open Source Server1 $ 6,500 Display Board5 $ 25,000 Vehicle Counter2 $ 600 Custom-developed Software $ 120,000 Total $ 309,600 Approximate Cost per Space $ 620 April 9, 2009DiriPark — Milestone Presentation40
Installed On-site Software Database System Software April 9, 2009DiriPark — Milestone Presentation41 Hardware Application Server Display Boards Network Infrastructure –Switching Equipment –Wireless Access Points Sensor Array Vehicle Counter
Business model On-site installation Multiple support packages – Tailored to customers needs April 9, 2009DiriPark — Milestone Presentation42
Funding Plan Phase 1 – SBIR Funding Agency – National Science Foundation – $ 100,000 Phase 2 – SBIR Funding Agency – $ 750,000 Phase 3 – Small Business Loan – Investors April 9, 2009DiriPark — Milestone Presentation43
April 9, 2009DiriPark — Milestone Presentation44 Marketing Risks M1. Lack of customer interest M2. Not realizing project benefits M3. Poor target branding Technical Risks T1.Inaccurate predictive analysis T2.Inefficient display of data
April 9, 2009DiriPark — Milestone Presentation45 M1. Lack of customer interest M2. Not realizing project benefits M3. Poor target branding T1.Inaccurate predictive analysis T2.Inefficient display of data Selective marketing (M1, M3) Prototyping trials (T1, T2) Historical data for predictive analysis (T1) Intuitive display (T2) Risk Mitigation
Evaluation Plan Phase 0 – Idea developed – Project website developed Phase 2 – Product design – Software module development – Software module testing – Integration testing – Finished product Phase 1 –Prototype design –Working prototype –Initial customer demonstration Phase 3 –First sale completed –Product released –Marketing plan developed –Successful marketing –New contracts acquired April 9, DiriPark — Milestone Presentation
References #SourceSlide of Appearance 1US Department of TransportationUS Department of Transportation, January ReutersReuters, December 9, IBISWorldIBISWorld, March 20, April 9, 2009DiriPark — Milestone Presentation47
Who We Are April 9, DiriPark — Milestone Presentation Mark Bullard Project Lead, Marketing Administrative Steven Murray Risk Mitigation Garnett Wilson Financial Specialist Technical Dominic Eldridge Software Developer Gabor Eszes Web Developer Thomas Suiter Hardware Specialist