Jon KleinISEProject Manager Nguyen VuMETechnical Lead Kyle MengesMETechnical Lead Christine LowryMEDesign Engineer Chris SteinMEDesign Engineer Priya NarasimhanEEElectrical.

Slides:



Advertisements
Similar presentations
Composite Filament Winding Machine: P09226 Shijo George Christofer Brayton Alex Sandy Tiago Santos Daniel Weimann Project Manager Electrical Engineer Chief.
Advertisements

Justin Akerman (CE) Chris Hoerbelt (ME) Hersh Anand (EE) Anthony Poli (ME) Greg Mucks (ME) Jon Notaro (EE) Eric Tripp (EE) Customer: Stan Rickel.
Physiological Simulator
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall.
HEMODYNAMIC SIMULATOR Project Background The objective of this project is to design and build a Hemodynamic Simulator. Hemodynamic Simulator is a modular.
P08026: Modular Hemodynamic Flow Simulator Jason Brown Mechanical Engineering Amanda Clark Mechanical Engineering Matthew Hicks Electrical Engineering.
P11462: Thermoelectric and Fan System for Cook Stove Jared RuggProject Manager (ME) Brad SawyerLead Engineer (ME) Jeff BirdMechanical Engineer Tom GorevskiElectrical.
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall Week 3:  Progress Update  Specifications 
Introduction to Hydraulics ClassAct SRS enabled. In this presentation you will: identify the fundamental parts of a hydraulic system and safety issues.
LFTB Proprietary Information 1 Fuser test bed ™ R I T MSD1 Project Review February 22, 2007 Fuser Test Bed P07501 IE TEAM Justin McMillan – Project Lead.
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall Week 4 Presentation:  Selected Concepts  Engineering.
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall Week 2 Presentation:  Work Breakdown Structure.
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall Week 4 End of Day Presentation:  Design Review.
P08456-LED Lighting for an Underwater ROV Jeremy Schiele-Project Manager Jonathan Lent-Mechanical Engineer Ryan Seeber-Computer Engineer Justin VanSlyke-Mechanical.
Risk Scoring Parameters Severity (choose most severe) Risk Ranking Likelihood ProductProjectInjury 3 Highly Likely > 50% Complete product failure, does.
Dennis Prentice – Project Manager (ME) Anthony Culotta – Mechanical Engineer Jason Nichols – Mechanical Engineer Belinda Segui – Electrical Engineer Sponsor/Advisor:
Reservoir LVAD PVS / Booster Physiological Simulator Valve Automated Resistance Valve Three Loops Blood Extraction Standard Pressure Sensor Temperature.
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall Week 2 – End Of Day:  Progress Update  Concept.
Ventricle Chamber Valve Imaging Chamber ECG Machine Aortic Compliance Chamber Buffer Chamber Secondary Compliance Chamber Flow Meter Pressure Sensors DAQ.
Jon Klein Project Manager Kyle Menges Technical Lead Priya Narasimhan Electrical Engineer Julie Coggshal Industrial and Systems Engineer Christine Lowry.
Classification of Instruments :
Chemical Engineering 3P04 Process Control Tutorial # 2 Learning goals 1.The feedback cause-effect principle 2. Key element in the loop: The control valve.
Giannis Combe Danilo Delgado Sara Patino FIU DEPARTMENT OF MECHANICAL ENGINEERING Miami, FL.
© ABB Group August 13, 2015 | Slide 1 Power Generation Service Life Cycle Management for Power Plants Daniel Looser, Power Gen Europe in Amsterdam, June.
CSE 425: Industrial Process Control 1. About the course Lect.TuLabTotal Semester work 80Final 125Total Grading Scheme Course webpage:
Muhajir Ab. Rahim School of Mechatronic Engineering
Lease Automatic Custody Transfer
HVAC523 Basic Subsystems.
Team: James Mazza, Andre Berwin, Peter Dunning, Nathan Fulcher, Andrew Watson, Travis Bardsley, Anthony Parker April 5, 2013.
TEAM 12: Low-Cost, Portable, Off-Grid Biodiesel Production Plant Team Members: James Black Sam Dresser Joey Kilmer Matt Mills Faculty Advisor: Dr. Dave.
21/01/02 - ECAL Cooling - Arnaud Hormiere ST/CV 1 Development of ECAL COOLING PLANT Application to a Super Module.
Component Environmental Test Chamber Jeff Hughes 1, Peter Adam 1, Thong Vo 2 and Phong Ngo 2 1. Department of Mechanical and Material Engineering, 2. Department.
1 Agricultural Power Systems Identifying Engine Systems and Their Components.
through Introduction  Particle Imaging Velocimetry (PIV) uses a sheet laser beam to illuminate particles that cross the sheet.  The particles.
Control Theory Control System Objectives  Establish a final condition  Provide safe operation  Eliminate the human element  Assure economical operation.
Jon KleinISEProject Manager Nguyen VuMETechnical Lead (MSD1) Kyle MengesMETechnical Lead Christine LowryMEDesign Engineer Chris SteinMEDesign Engineer.
1 LBT Q Engineering Review PLMG: Plumbing, includes IC system, chiller systems, instrument lab cooling, and LUCIFER cryo-compressor cooling.
Team Members: Jon Klein Nguyen Vu Kyle Menges Christine Lowry Chris Stein Priya Narasimhan Julie Coggshall.
P16081: SYSTEMIC CIRCULATION MODEL Jacob Zaremski – Lead Engineer Mallory Lennon – Project Manager John Ray – Communications Manager Fabian Perez – Purchasing.
Nanofluidic Characterization David Sharp David West Justin Davis.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
P16680: AATech Universal Oil and Bag System System Design Review 9/29/15.
Esbe Rotary Motorized valves The ESBE Rotary Motorized valves (mixing valves and actuators) are used to control heating and cooling in buildings. We offer.
SYSTEM LEVEL DESIGN REVIEW P16318 Gaseous Mass Flow Rate Controller Luke McKean, Lianna Dicke, Selden Porter, Schuyler Witschi ?
BASIC AUTOMATIC CONTROLS UNIT 16 ADVANCED AUTOMATIC CONTROLS
Proportional and Servo Valves
Date of download: 6/7/2016 Copyright © ASME. All rights reserved. From: Mock Circulatory Loop Compliance Chamber Employing a Novel Real-Time Control Process.
Ventricular Assist Device Test Loop Client: Minnetronix, Inc. Advisor: Kristyn Masters Team: Joe Bothwell, Dan Carlson, Kayla Ericson, and David Ugai.
P10203 LV1 MOTOR CONTROLLER FINAL REVIEW MAY 14, 2010 Electrical: Kory Williams, Adam Gillon, Oladipo Tokunboh Mechanical: Louis Shogry, Andrew Krall.
Joseph Ferrara Team Lead (ME) Joseph ChurchDesign Engineer (ME) Joshua Van Hook LabView Engineer (EE) Jamie Jackson Electronics (EE) Joelle Kirsch Project.
Author: Nurul Azyyati Sabri
EEN-E1040 Measurement and Control of Energy Systems Control II: Controlled devices, control in energy technology, complex systems Nov 7th 2016.
HYDRAULIC AND PNUEMATIC ACTUATION SYSTEMS
Midpoint Project Review P10454 VAD Test Loop
GOVERNMENT ENGINEERING COLLEGE DAHOD
Date of download: 10/9/2017 Copyright © ASME. All rights reserved.
Control System Instrumentation
Turbomachinery Flow Visualization P08453
P07203 Dynamometry Laboratory Infrastructure
Date of download: 11/15/2017 Copyright © ASME. All rights reserved.
Introduction to process control
AUTOMATIC SHIFT CONTROLS FOR ATV SPONSOR: POLARIS INDUSTRIES
EEN-E1040 Measurement and Control of Energy Systems Control II: Controlled devices, control in energy technology, complex systems Nov 2nd 2017.
HEMODYNAMIC SIMULATOR II P09026
HEMODYNAMIC SIMULATOR II P09026
Heart Pump and Circulatory System
Project Review P07442: Thermoelectric Demonstration Test Bed
Introduction to process control
Heart Pump and the Circulatory System P17080
Light Vehicle Diesel Engines
Presentation transcript:

Jon KleinISEProject Manager Nguyen VuMETechnical Lead Kyle MengesMETechnical Lead Christine LowryMEDesign Engineer Chris SteinMEDesign Engineer Priya NarasimhanEEElectrical Engineer Julie CoggshallISESystems Engineer

Customer Needs Top 10 Specifications Blood Sub-System Physiological Sub-System LVAD Test Loop System Architecture Risks and Mitigation Design Reviews Summary Budget Current State of Design Senior Design II Schedule

Design and build a test loop to help in LVAD development by characterizing the pressures and flows associated with the device as well as its impact on blood. 1.Generate pressure and flow curves for static system (automatically adjusted) 2.Extracting fluids while running to determine damage to blood 3.Process data to generate pressure and flow curve for dynamic system (scaled model of the physiological circulatory system working with a PVS)

Engr Spec #MetricUnitsIdeal Value Lower Limit Upper Limit ES1System Leakage# leak locations002 ES6Portabilityminutes45160 ES9CostU.S. Dollars ES13Pressuremm Hg ES14Pressure Accuracymm Hg ES15Flow Rateliters/minute6010 ES16Flow Rate Accuracyliters/minute ES17Temperaturedegrees C (F)37 (98.6)21 (70)49 (120) ES18Temperature Accuracydegrees F ES22System LxWxHinches48x36x3036x12x1260x48x36

Principle Schema B-Automated resistance A-LVAD D- Temperature controlled bath C-Reservoir /Blood extraction D C A B Differential pressure sensor Flow sensor

Blood reservoir/ Water bath B A C Heating Element (A) Blood reservoir: fill the system, air removal, blood extraction (B) Circulation Pump (C) Water bath: maintain the temperature of the blood (D) D

Glycerin mix (A) Arterial Compliance tank (B) Pressure regulator (C) Resistance (D) PVS (E) LVAD (F) A B C D E F

Valved quick-connect Drainage Points

DAQ Mechanical System Test loop with LVAD and PVS Mechanical System Test loop with LVAD and PVS Stepper motor Pressure sensor Flow sensor Thermocouple Computer: Labview used to monitor temperature and plot flow and pressure curves Pressure of liquid Flow rate of liquid Temperature of liquid Variable resistance

Risk AreaRisk ItemDescription/CommentMitigation Activity Measurement Inaccurate measurements Pressure and flow measurements are inaccurate Use proper instrumentation and verify proper placement. Discuss with experts prior to purchasing. DAQ Error Instrumentation and DAQ not communicating properly, DAQ does not collect or output data properly Debug software, document procedure for DAQ operation and troubleshooting. Discuss with experts prior to purchasing.

Risk AreaRisk ItemDescription/CommentMitigation Activity Physiological Simulation Compliance Tank Desired compliance value not achieved Early milestone in test plan to ensure enough time to fix the problem Temperature System temperature is not maintained Monitor fluid and VAD temperature, implement temperature control system Viscosity Viscosity variation does not simulate human blood properties Research and verify the proper mixture of water/glycerin is used, control/maintain temperature

Risk AreaRisk ItemDescription/CommentMitigation Activity Design Leaks System or components leak causing error in measurement and/or contamination Early milestone in test plan to ensure enough time to fix the problem Air bubbles Air bubbles cannot be removed from system – tank sizes do not allow for bubbles to escape, or there are low points in the system Early milestone in test plan to ensure enough time to fix the problem. Use alternative fill method to reduce bubble formation Blood Damage Valves, sensors, connectors damage blood Early milestone in test plan to ensure enough time to fix the problem. Put in separate, simplified loop Resistance Flow restriction does not function properly Design for the implementation of a back-up, manually controlled resistance method

Risk AreaRisk ItemDescription/CommentMitigation Activity Cost Pressure Sensors Desired sensor accuracy not within budget Find suitable DAQ to achieve accuracy DAQ Dedicated DAQ system not within budget Investigate costs, potential for sharing existing DAQ system

DR1  Compliance: Developed electrical equivalent model  Sensors: Use existing flow sensors  System Architecture: Modular, quick-connect design DR2  Simplify Design: Reduce system to a single tank that functions as both a compliance tank and reservoir Use a pressure-cuff to pressurize compliance chamber in place of expensive gauge and regulator  Need to establish more refined electrical specifications

ComponentDescriptionTotal Price General Components Tubing, Connectors, Fittings, Tank, Cart $ Measurement & Data Collection Sensors (Pressure, Thermocouples, Ultrasonic Flowmeter), DAQ $1, Blood Loop Components Water Bath, Heating Element, Pump, Tank Fittings $ Physiological Loop Components Pressure Cuff & Gauge, Fittings (for Tank) $32.27 Automated Resistance Linear Actuator & Stepper Motor, Stand $97.73 Testing Supplies Glycerin, De-Ionized Water, Saline $ TOTAL$3,170.28

Design meets all customer needs Design exceeds upper budget limit by ~ 6% Data collection and control specifications are not finalized Schedule: 1 week behind on electronic component selection Mitigations: Elimination of venous compliance tank → pending approval Budget: Need approval or reduction in specification limits Finalize design by end of week 11 to order parts

Date(Week)Mechanical SystemData Collection and Control Mar 13(Week 1)Closure of MSD I A.I.’s, All Parts from BOM Ordered Mar 20 (Week 2)All Parts Received Apr 3 (Week 4)Loop Components AssembledConnection with PVS and LVAD established Apr 5 (Week5)Final Test Plan complete Apr 24 (Week 6)Compliance ConfirmedConnection with Sensors established May 3 (Week 8)Final Device BuiltLab View Program debugged May 8 (Week 9)Testing Complete & Documented, Poster Complete May 15 (Week 10)Field Demo, Technical Paper, User Manual May 18 (Week 11)Final Documentation

Heating Element Blood Extraction Resistance Female - Valved Male - Valved Female Male Fluid Fill LVAD PVS