Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 1: Portfolio Management Infrastructure Planning:

Slides:



Advertisements
Similar presentations
Asset Management in Integrated Planning and Reporting for Local Governments Troy Daniels, Project Manager Department of Local Government and Communities.
Advertisements

Developing & operating a corporate landlord model
REPUBLIC OF NAMIBIA OFFICE OF THE PRESIDENT NATIONAL PLANNING COMMISSION Overview of Development/ Capital Budget 01 March 2012.
Limpopo Department of Education: Procurement strategy for Education infrastructure 25 March
Implementation of the Government Immovable Asset Management Act, 2007 (GIAMA) National Department of Public Works Presentation to the Select Committee.
Infrastructure Delivery Management Toolkit: 2010 Edition development through partnership 1 Practice Guide 1: Provincial Infrastructure Strategy.
PUBLIC SECTOR ENGINEERING CAPACITY & CAPABILITY A M Peters Pr Eng BSc Eng MBA.
Land & Construction Management III Project Management Leadership Motivation Procurement.
Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Overview 1.
PORTFOLIO COMMITTEE MEETING PRESENTATION ON MTEF BUDGET ALLOCATION FOR THE YEARS 2015/ /18 15 th APRIL 2015.
Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 3: Operations & Maintenance 1.
Formulation of a Government-wide Fixed Asset Management Framework
Operational efficiency 20 November Contents Background –Approach –Context Initiatives Results.
1 PMIG PUBLIC SECTOR PROCUREMENT BEST PRACTICES & LESSONS LEARNED Kevin James Barrie Kroukamp.
IDP Conference 2004 “Developmental Governance in Action” SESSION 7: Integrated Governance: > Provincial-Municipal Engagement - A Provincial Perspective.
New Procurement & Delivery Arrangements for the Schools’ Estate Presentation to Strategic Advisory Group 18 April 2005.
SPACE ADMINISTRATION IN HIGHER EDUCATION INSTITUTIONS – BARRIERS AND OPPORTUNITIES Jean Skene Director: HEMIS Department of Higher Education and Training.
Challenges to purchase/release of Land & Buildings for Sustainable Human Settlements Presentation to the Portfolio Committee on Public Services 10 September.
1 Alignment of the Infrastructure Delivery Cycle with the Budget Cycle and Strategic Planning Cycle Prepared by the Infrastructure Delivery Improvement.
1 RHD Cost Sharing Review Update 2011 UBCM Convention Presented by RHD Cost Sharing Review Implementation Group September 26, 2011.
IN YEAR MONITORING & BUDGET PREPARATION WORKSHOP PREPARED BY BUDGET OFFICE MAY
1 1 BRANCH: CORPORATE AFFAIRS 1. CORPORATE MANAGEMENT SERVICES To provide financial and strategic support services that enhance service delivery by the.
1 Government Immovable Asset Management Bill [GIAMA] National Council of Provinces Select Committee on Public Services Parliament, 09 May 2007.
February 9, 2012  Partner with the community  Provide an effective educational experience  Prepare every student to find success in our complex society.
1 Alignment of the Infrastructure Delivery Cycle with the Budget Cycle and Strategic Planning Cycle Prepared by the Infrastructure Delivery Improvement.
Alignment of the Infrastructure Delivery Cycle with the Budget Cycle (Abridged Version for Prepared by the Infrastructure Delivery Improvement Programme.
ASSOCIATED BENEFITS OF mSCOA IN THE ASSET LIFE CYCLE
1 Department of Public Works Government Immovable Asset Management Bill GIAMA Portfolio Committee on Public Works 28 February
Portfolio Committee on Appropriations Quarter 1 Expenditure and Performance 24 August 2012 The Presidency Department of Performance Monitoring and Evaluation.
1 Department of Public Works Government Immovable Asset Management Bill [B1-2006] Portfolio Committee on Public Works 08 November
PUBLIC–PRIVATE PARTNERSHIP (PPP) FRAMEWORK AND GUIDELINES Syed M. Ali Zaidi, P.Eng. PM(Stanford), Ph.D. Director, Strategic Partnerships Alberta Infrastructure.
Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 2: Project Management 1.
© CT Management Group Pty Ltd 2015 Municipal Association of Victoria Rate Cap Forum 25 th November 2015 Ian Mann CT Management Group
DEPARTMENT OF EDUCATION EDUCATION INFRASTRUCTURE PROGRAMME OF ACTION Portfolio Committee Presentation Cape Town 15 February 2005.
Policy, Budgeting and Oversight: The Role of the Legislature in Uganda Ishmael M Magona Ministry of Finance, Planning and Economic Development.
1 PRESENTATION TO THE PORTFOLIO COMMITTEE OF MINERAL RESOURCES. STATEGIC PLAN 2014/19 DATE: 8 JULY 2014 Programme Financial Administration.
INFRASTRUCTURE EXPANSION IN RELATION TO THE DEPARTMENT OF HOME AFFAIRS (DHA) Presentation to Portfolio Committees of Home Affairs and Public Works 19 September.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES SERVICE LEVEL AGREEMENT 02 June 2010.
PROVINCIAL INFRASTRUCTURE GRANT NCOP 06 March 2006.
Estimates of National Expenditure 2003 NATIONAL TREASURY.
Development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 1: Portfolio Management Introduction Sonny Schmidt.
Alignment of the Infrastructure Delivery Cycle with the Budget Cycle and the Strategic Planning Cycle Version 7: November 2011 (Aligned with the 2010.
Infrastructure Delivery Management Toolkit:
ELECTRICITY DISTRIBUTION INDUSTRY DECISION
Infrastructure Delivery Management Toolkit: 2010 Edition
Infrastructure Delivery Management Toolkit: 2010 Edition
USA Corporate Plan and Budget for the Period
Infrastructure Delivery Management Toolkit: 2010 Edition
Presentation to Portfolio Committee
Budget Vote/Strategic Plan Presentation
Planning Monitoring & Controlling the Maintenance Programme
THE SELECT COMMITTEE ON LOCAL GOVERNMENT AND ADMINISTRATION
ASSET MANAGEMENT.
Infrastructure Delivery Management Toolkit:
What is Capacity? Design capacity Effective capacity Actual output.
Municipal Association of Victoria Rate Cap Forum 25th November 2015
DP1: Portfolio Management
Infrastructure Delivery Management Toolkit: 2010 Edition
Municipal Association of Victoria Rate Cap Forum 25th November 2015
2018/19 ANNUAL PERFORMANCE PLAN FOR MISA
Amending the Performance Framework
Department of Correctional Services
INGONYAMA TRUST BOARD’S ANNUAL PERFORMANCE PLAN
BLOEMFONTEIN SANDF: TEMPE MILITARY BASE: 3 MILITARY HOSPITAL: INFRASTRUCTURE REFURBISHMENT AND MAINTENANCE CHALLENGES Date: SEPTEMBER 2018 BRANCH HEAD:
Financial and IT Services
LIMPOPO DEPARTMENT OF PUBLIC WORKS PRESENTS
Medium-term estimates
IMPLEMENTATION EVALUATION OF THE RESTITUTION PROGRAMME
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
PORTFOLIO COMMITTEE ON HUMAN SETTLEMENT UPDATE ON ACCREDITATION
Presentation transcript:

development through partnership Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 1: Portfolio Management Infrastructure Planning: The U-AMP Sonny Schmidt 1

DP1: Portfolio Management DP1-1 Infrastructure PlanningDP1-2 Programme Management Develop U-AMP (including prioritised MTEF works list) Develop C-AMP (including work plans) Manage Implementation Develop/review IPMP DP2: Project Management DP2-1 Planning (Develop IPIP) DP2-2 Design DP2-3 WorksDP2-4 Close Out Package prep Package definitio n Works plannin g Design develop t. MFC Info Con/Del works Handovr works Project Close Out G3 G4G5G6(a)G6(b)G7G8 P C2 P C3 P C4 a P C5 P C4 b DP3: Operations & Maintenance DP3-1 Recognise & accept assets DP3-2 Mobilisation for Facilities Mgt DP3-3 Operations DP3-4 Maintenance DP3-5 Demobilise Facilities Mgt Prov Infr Strat G1(a) G2 G1(b) Dev Proc Strat P C1 PF1. 4 PF1. 3 PF2. 1 PF2. 2 PF2. 3 PF3PF4 PF5 PF1. 4 PF1. 3 PF2. 1 PF2. 2 PF2. 3 PF3PF4 PF5 PF1. 4 PF1. 3 PF2. 1 PF2. 2 PF2. 3 PF3PF4 PF5 T1T2 Update Asset Register G8 The IDMS

User and Custodian Portfolio Management Outputs User organisations Custodian organisations  U-AMP  Construction procurement strategy  IPMP  Organisation and Support plan  Monitoring reports  Recommended actions  C-AMP  Work Plans  Organisation and Support plan  Monitoring reports  Recommended actions 3

6 Infrastructure Planning Methodology

Basic 3 Gaps to be determined: Space Gaps Utilisation Gaps Functional Gaps Condition Gaps Efficiency Gaps Other Gaps: Capacity gaps Funding Gaps

Project Cost Estimating & Budgeting SCOA: Category of Expenditure: –Capital: Acquisition (new, additions) Upgrading, Alterations, Conversions Renovation, Refurbishment (Rehabilitation) Disposal –Current: Routine maintenance Staff, systems Based on Life Cycle Costing 8

Life Cycle Costing (1) All costs (estimated & actual) over the life cycle of an asset are taken into consideration in order to make future decisions about the asset. Includes: – capital e.g. initial acquisition cost and future upgrades, –rehabilitations –operations and maintenance 9

Life Cycle Costing (2) 10

Estimate for new infrastructure asset 11

Portfolio Budget build up 12

“Programme View” of Budget 13

The Need for Budget Revision Project Budget –The “Control” Budget? Financial Year Budget: Demand for work exceeds available fund: –Re-schedule work –Apply robust Prioritisation Criteria –Document prioritisation decisions 14

Budget Revision due to Progressive Improvement of Cost Estimates Cost estimating through the Project Life Cost Estimate NameGateway Process stage ConceptualInfrastructure Planning Pre-feasibilityPackage Preparation Preliminary (Feasibility)Design Development TenderDesign Documentation DefinitiveWorks FinalClose Out 15

Alignment of Budget and Infrastructure Planning Cycles (1) Expenditure characterised by spike (hockey stick!) Resulting in: –Roll over of funds –Over expenditure –Value not achieved –Incorrect services procured Cabinet approved framework (2007) –Allows for due process to take place 16

Alignment of Infrastructure Planning and Budgeting (1) 17

Summary: Infrastructure Planning User:  U-AMP (G1a)  Consider service delivery mandate  Infrastructure required (“Gaps”)  Life cycle costs  Collaboration with custodian 18

19 Thank you