Turkish Power System Overview March 2012

Slides:



Advertisements
Similar presentations
DEWETRON - Power Product Line
Advertisements

Black Sea Regional Transmission Planning Project - renewables integration - By Predrag Mikša EKC - Electricity Coordinating Center Simferopol, June 2011.
RES-E Impact on Transmission Grid and Power System Reserves
Sistan & Balouchestan Electric Power Distribution Company
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
Challenge of Large Scale Wind Power Integration - Introduction to the Workshop Pradeep Perera Principal Energy Specialist Asian Development Bank.
Regulatory framework in the Energy Sector Chairman Ph.D. Tserenpurev Tudev Energy Regulatory Commission of Mongolia Energy Mongolia-2012 Ulaanbaatar Mongolia.
Integrating Multiple Microgrids into an Active Network Management System Presented By:Colin Gault, Smarter Grid Solutions Co-Authors:Joe Schatz, Southern.
System Strength Discussion
The Kazakh Operator of Electric Power and Capacity Market
Cihangir Gençoğlu , Joint Transmission System Operator – Utility Regulator Renewable Energy Workshop, Istanbul Integrating Intermittent Renewable.
Dr. Yüksel MALKOÇ TWEA Vice President. Turkey’s current financial outlook, Demand growth and supply development, Wind potential and capacity development,
THE FUTURE OF SOLAR ENERGY IN LITHUANIA OPTIONS AND OPPORTUNITIES FOR DEVELOPMENT Vitas Mačiulis Lithuanian Solar Energy Association 19 September, 2013.
BALTIC ELECTRICITY REGIONAL INITIATIVE Riga, 24 April, 2009 LATEST UPDATE IN LATVIA Ainārs Meņģelsons Public Utilities Commission.
Interconnection of Distributed Generation
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
E.ON on the Romanian Energy Market ZF Power Summit Bucharest, February 27, 2013 Frank Hajdinjak CEO E.ON România.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
Highlights of Commission Activities Little Rock ASHRAE Monthly Meeting October 12, 2011 Presented By: John P. Bethel.
Grid Integration of Renewable in India - Challenges and Policy Responses Sanjay Garg General Manager General Manager PGCIL/ Ministry of Power.
Dr. Osman Bülent TÖR Power System Planning and Analyse Group Jordan, 2012 Responses of IPPs against Incentive Mechanisms for Renewable Generation in Turkey.
Generation & Trading CIST REGIONAL ENERGY MARKET IN SOUTH EAST EUROPE (REM) Athens – 27 th of October 2004.
Organization of the electricity market and renewable energy sources in the Republic of Croatia" Dubrovnik, 2 nd October th Dubrovnik Conference.
Eagle Crest Energy Company February Page 2 New Hydro: Making it Happen Background on the Eagle Mountain Pumped Storage Project Need for Eagle.
World Bank Water Week – 2004 Jerson Kelman. Hydroelectric power accounts for more than 90% of the total electric energy produced in Brazil.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa
E P D K 1 Turkish Electricity Market and Recent Developments Cemal Çelik Energy Expert EMRA-TURKEY March ANTALYA.
Black Sea Regional Transmission Planning Project By Predrag Mikša EKC - Electricity Coordinating Center Istanbul, March 2011.
Energy Gateway Update for Wyoming Infrastructure Authority January 27, 2009 Darrell Gerrard Vice President Transmission System Planning.
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
Sanjay Garg General Manager PGCIL/ Ministry of Power
Generation and transmission interconnections 4 July, 2013 Virgilijus Poderys CEO of LITGRID AB.
Privatization and Liberalization of the Electric Power Industry in Taiwan Energy Commission Ministry of Economic Affairs October 5, 2001.
Croatian Power System 1 The Electric Power System - Croatia -
K E M A T & D C O N S U L T I N G Power System Conference, Clemson, South Carolina, March 8-11, 2005 Principles and Issues Relating to the Interconnection.
Energy Agency of the Republic of Serbia
JUNTOS CONSTRUIMOS UN PAIS DE CALIDAD HONDURAS RENEWABLE ENERGY 2012.
Wind Generation in New Zealand Kieran Devine, Doug Goodwin System Operations Transpower New Zealand Limited.
UPDATES ON THE LATEST DEVELOPMENTS IN LITHUANIA Aistija Zubaviciute National Control Commission for Prices and Energy 3 April 2007, Riga.
Secondary legislation on renewable today and tomorrow Nicolae Opris Vicepresident, ANRE ANRE ROMANIAN ENERGY REGULATORY AUTHORITY.
Northern Europe Electricity Regional Initiative 5th Stakeholder Group Meeting Transparency in the region 26. May 2010, Copenhagen Jan-Welf Selke Bundesnetzagentur.
1 Regional electricity market Belgrade, 23. April Ljiljana Hadzibabic Council member Energy Agency of the Republic of Serbia.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
Power Plant Construction and QA/QC Section 4.3 – Electrical Interconnections Engineering Technology Division.
1 19 th World Energy Congress – 2004 Round Table 1 – Non Fossil Fuels: Will They Deliver? Jerson Kelman President, Brazilian Water Agency - ANA.
Perspectives of Nuclear Energy Further development in Armenia A. A. Gevorgyan Obninsk, RF 27 June – 2 July 2004.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Distribution Systems-General
BI Marketing Analyst input into report marketing Report TitleElectricity in Texas Report Subtitle State profile of power sector, market trends and investment.
POWER SECTOR, ENERGY RELATED RESEARCH POTENTIAL in LITHUANIA by dr. Anzelmas Ba čauskas Lietuvos energija AB, Lithuania CENTRAL-EASTERN EUROPEAN ENERGY.
Goran Majstrovic Davor Bajs Energy Institute HRVOJE POŽAR Croatia PREPARATION FOR LARGE SCALE WIND INTEGRATION IN SOUTH EAST EUROPE Joint TSO.
1 SYMPOSIUM: U G A N D A A F T E R I D I A M I N A N D M I L T O N O B O T E Hamburg, Germany 29 th September 2008 INVESTMENT OPPORTUNITIES IN POWER GENERATION.
Wind Production intermittency Cross border compensation: what to expect in Western Europe? Analysis of Winter 2010/2011 Hubert Flocard and Jean-Pierre.
Energy Sector of Turkey “General Overview and Policy Objectives” Sinem ÇAYNAK General Directorate for Energy Affairs IEA Turkey IDR Meeting December 8,
GRID INTEGRATION COST OF PHOTOVOLTAIC POWER GENERATION G. Strbac, D. Pudjianto, P. Djapic, J. Dragovic Energy Futures Lab.
Renewable energy support schemes in the Republic of Moldova
Operation of power systems with high shares of wind power
(Energy Market Regulatory Authority)
Damitha Kumarasinghe Director General
GEORGIAN ELECTRICITY MARKET OPERATOR
“Caucasus Power Transmission Network’’ (Armenia-Georgia overhead transmission line/substations) Loan Project.
Loan Project of Construction of Iran-Armenia 400kV third power transmission line (“ Noravan’’ 400/220/20 kV) and related substation.
Khuzestan Regional Electric Company
Sustainable Energy Planning for Autonomous Power System of Crete
STATE ENERGY AND WATER REGULATORY COMMISSION
Overview on Renewable energy in Bulgaria
EU-IPA12/CS02 Development of the Renewable Energy Sector
Sami Repo Tampere University of Technology FINLAND
Presentation transcript:

Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

TURKISH POWER SYSTEM NUMBER OF SUBSTATIONS 400 kV 78 220 kV 2 TOTAL: 614 (103.100 MVA) LENGTH OF TRANSMISSION LINES 400 kV 15830 km - 154 kV 32513 km - 220 kV 85 km - 66 kV 508 km 154 kV and 400 kV cable length 220 km TOTAL 49.159 km

INSTALLED CAPACITY & PEAK LOAD Installed Capacity : 53.235 MW Renewable(hydro,wind,jeo.) : 36 % Thermal : 64% Peak Load (2010) : 33.392 MW Peak Load (2011 July) : 36.122 MW 3

GENERATION FOR 2011 Total : 229,3 TWh Thermal : 73,7 % Renewable : 26,3 %

CONSUMPTION   1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Consumption (TWh) 114,0 118,5 128,3 126,9 132,6 141,2 150,0 160,8 174,6 190,0 198,1 194,1 210,4 228 İncrease (%) 8,1 3,9 8,3 -1,1 4,5 6,5 6,3 7,2 8,6 8,8 4,3 -2,0 8,4 9,0 5

PEAK LOAD AND ELECTRICITY CONSUMPTION 2001-2020

INTERCONNECTIONS (Existing Situation) BULGARIA 145 km 400kV 136 km 400kV 300 MW GEORGIA 28 km 220kV 160km 400kV 15-80 MW 400 MW 0 MW ARMENIA 80,7 km 154kV GREECE 130 km 400kV NAHCİVAN 87 km 154kV 40 MW 40 MW 150 MW IRAN 73 km 154kV 100 km 400kV TÜRKİYE 380MW 0 MW IRAQ 42 km 400kV 400 kV Existing 400 kV Underconstruction 220 kV Existing 154 kV Existing SYRIA 124 km 400kV KKTC 7 7 7 7

PLAN FOR 2013 1200MW 700 MW 1200 MW 40 MW 40 MW 350 MW 500 MW 350 MW 8 BULGARIA 145 km 400kV 136 km 400kV If ENTSO-E connection will be approved 1200MW GEORGIA 28 km 220kV 160km 400kV 700 MW 1200 MW 0 MW ARMENIA 80,7 km 154kV GREECE 130 km 400kV 40 MW NAHCEVAN 87 km 154kV 40 MW IRAN 73 km 154kV 100 km 400kV TÜRKİYE 350 MW 500 MW 350 MW IRAQ 42 km 400kV 400 kV Existing 400 kV Underconstruction 220 kV Existing 154 kV Existing SYRIA 124 km 400kV KKTC 8 8 8 8

PLAN FOR 2015 1200MW 350 MW 700 MW 1200 MW 40 MW 40 MW 600 MW 600 MW BULGARIA 145 km 400kV 136 km 400kV If ENTSO-E connection will be approved 1200MW GEORGIA 28 km 220kV 160km 400kV 350 MW 700 MW 1200 MW ARMENIA 80,7 km 154kV GREECE 130 km 400kV 40 MW NAHCEVAN 87 km 154kV 40 MW 600 MW IRAN 73 km 154kV 100 km 400kV TÜRKİYE 600 MW Planning phase IRAQ 42 km 400kV 400 kV Existing 400 kV Under Construction 220 kV Existing 154 kV Existing SYRIA 124 km 400kV KKTC 9 9 9 9

UCTE/ENTSO-E Trial Run period started with ENTSO-E on 18th of September 2010. The first phase system stability tests approved by ENTSO-E Planary Group on 8th of February. Without any trade Import-Export tests for the second phase found successfull by ENTSO-E. The third phase (import-export with trade) related with the synchronous parallel operation of Turkey with European Power System started on 1th of June 2011 and it will be ended on September 2012. Trade will be limited with 400 MW from Bulgaria and Greece to Turkey; 300 MW from Turkey to Europe via these countries.

POWER PLANTS CONNECTION REQUESTS( December 2011) MW POWER PLANTS CONNECTION REQUESTS HPP WPP TPP TOTAL NGCCP Other CAPACITY APPROVED BY TEİAŞ 4.741 2.528 24.250 7.838 39.357 CAPACITY HAS BEEN LICENCED BY EMRA 10.114 5.066 5.765 2.715 23.660 CAPACITY HAS CONNECTION AGREEMENT BY TEİAŞ 6.473 3.464 5.715 6.391 28.267 21.328 11.058 35.730 16.944 85.060 11

INCENTIVES FOR RENEWABLE POWER PLANTS The Turkey’s Parliament approved a new law 29 December 2010, on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of: 7.3 U.S. cents per kWh for wind energy and hydroelectric power, 10.5 US cents for geothermal energy and 13.3 US cents for energy from waste products and solar energy These prices will cover energy firms that are established between May 13, 2005 and Dec. 31, 2015. For energy purchases from companies founded later than Dec. 31, 2015, new prices defined by the Cabinet will be implemented. The prices for the new companies will not exceed the current figures, the law said. In the event that operators use local equipment and technology in renewables energy facilities, an additional support of 0.4 cents to 2.4 $ per kw will be provided for a five year term to companies that started producing energy before the end of 2015. The surplus generation from the renewables will be bought by the distribution companies for ten years guarantee with the defined energy prices. The law limits the total production of licensed solar energy with 600 MW until the year of 31 December 2013 and authorizes the cabinet to determine the limits afterwards.

WPP INTEGRATION PROCESS TO THE GRID TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID? -EVALUATING OVERLAPPING WPP’S APPLICATION? ? 1 NOVEMBER 2007 SINGULAR APPLICATIONS AND LICENCE – CONNECTION TO THE GRID 3500MW CAPACITY ALLOCATED 78.000 MW TOTAL OVERLLAPPING APPLICATIONS

Wind Power Plants

WPP INTEGRATION PROCESS TO THE GRID TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID? THE FACTORS THAT LIMIT THE CAPACITY OF THE AVAILABLE WPP CONNECTION TO THE NATIONAL GRID GENERATION- CONSUMPTION BALANCE FREQUENCY RESERVE THE FACTORS THAT LIMIT THE CAPACITY OF THE AVAILABLE WPP CONNECTION TO THE REGIONAL GRID VARIATIONS OF POWER FLOW REGIONAL ENERGY QUALITY ADDITIONAL INVESTMENTS FACTORS THAT LIMIT THE CAPACITY OF THE AVAILABLE WPP CONNECTION TO THE BUSBARS ENERGY QUALITY SHORT CIRCUIT POWER ON MEDIUM VOLTAGE LEVEL TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE NATIONAL GRID? AVAİLABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE REGIONAL GRID? AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE BUSBARS?

WPP INTEGRATION PROCESS TO THE GRID DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM Evaluation of the available wind power capacity can be connected to the system Power Flow studies Evaluation of wind variability on the effect of power flow and local grid Planning the investment of basin substation and transmission lines

WPP INTEGRATION PROCESS TO THE GRID TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID? APPLIED APPROACHES IN THE WORLD -Integration to the 1/3 ratio to the demand of system minimum -Integration to the 25% ratio to the demand of system maximum APPLICATION 78.000 MW 2013 Estimated Minimum System Peak 2013 Estimated Maximum 18.703 MW 46.757 6.727 MW (1/3 of Peak ) 11.689 MW (25% of Peak)

WPP INTEGRATION PROCESS TO THE GRID DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM NEGATIVE EFFECTS OF WIND POWER PLANTS ON GRID - FAULT-RIDE TROUGH CAPABILITY OF WPP’S FLICKER (Turbulence/Output Power Source) VOLTAGE FLUCTUATION(Cause of Output Power fluctuation and insufficient of reactive power support) HARMONICS( Cause of Power Electronic Equipments) Figure: Variable of wind generation

Wind Power Plants

QUEUE MANAGEMENT OF WIND POWER PLANTS Process: The available capacity of substations for connecting wind powerplants are published by TEİAS. WPP applications are forwarded to TEIAS for studying connection opportunities. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications. If there are multiple applications in one substation, compitition process is done by TEIAS to determine the owner of the capacity. After taking license the investor sign a connection agreement with TEIAS. Project will be approved by MENR. After the realization of the project System Usage Agreement will be signed by TEIAS. 20

Competitions competition organisation number of invited companies number of substations number of winner companies total connection capacity (MW) 1 27 12 16 626 2 11 5 6 281 3 26 8 500 4 31 395 30 9 520 38 289,4 7 46 15 427 54 607 41 74 10 37 217 175 1199 33 7  198 13 47  6 166 TOTAL 596 87 147 5500 Weighted average of the competition prices is 1,91 kurus/kwh

Winner prices and installed capacities

Future Problems What will be the operation problems if ~11000 MW wind power plant will be in service ? Wind applications are concentrated in west side of Turkey. This will cause excessive voltage changes in the region Effective regional voltage control ; Effective secondary reserve control Effective ENTSO-E interconnection tie line control will be needed All these issues can be managed by an effective wind forecast and monitoring system

WPP INTEGRATION PROCESS TO THE GRID FAULT RIDE THROUGH CAPABILITY of WPPS Existed regulation Annex-18 New regulation for wind

WPP INTEGRATION PROCESS TO THE GRID REACTIVE POWER CAPABILITY Existed regulation Annex-18 New regulation for wind -0.4 -0.3 -0.2 -0.1 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 Total Reactive Power (pu) Total Active Power (pu) PF 0.95 enductive PF 0.95 capacitive PF 0.835 capacitive PF 0.835 enductive 0.1 pu under output power (total active power) , Reactive power capacity is not checked. Over Excited Region Under Excited Region

WPP INTEGRATION PROCESS TO THE GRID AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE BUSBARS? According to the Transmission System Supply Reliability And Quality Regulation in the third section Generation Connection Principles - Design Principles of Generation Facility Switchyards defined that “Connection of generation facility based on wind energy is permitted for a capacity up to 5 % of the system short circuit power at the connection point ” New regulation which will be published in the near future, IEC 61400 standarts are applied to determine available wind power capacity For example, A substation, minumum3 ϕ Short Circuit Power is Sk=3000 MVA Available wind power capacity for this busbar is 3000x5/100 = 150 MW

Solar Energy in Turkey 27 27

Connection points for solar Power Plants The capacity of 600MW for Solar Power plants has been approved by TEIAS according to regions. *Applications has to sellect the most nearest substation for system connection according to the regulations

Hydraulic Power Plants Capacities in North East Region (In Operation &Planned) 2500 MW 2500 MW 1500 MW

Thank you for your attention