Joint Commissioning (2) Commissioning plan Gene Flanagan Purdue University.

Slides:



Advertisements
Similar presentations
Campus Testbed for Network Management and Operations Nick Feamster Georgia Tech Joint with Ankur Nayak, Russ Clark, Ron Hutchins, Campus OIT Also input.
Advertisements

Status of the CTP O.Villalobos Baillie University of Birmingham April 23rd 2009.
1 System Calls (TRAPS) and Subroutines Patt and Patel Ch. 9.
Final Commissioning Plan and Schedule Cheng-Ju Lin Fermilab Installation Readiness Review 09/27/2004 Outline: - Work to be done during shutdown - Work.
Chapter Six 1.
LKr for the dry run (and not only…) R. Fantechi 23/5/2012.
Project Control Techniques
3. Hardware Redundancy Reliable System Design 2010 by: Amir M. Rahmani.
Summary Ted Liu, FNAL Feb. 9 th, 2005 L2 Pulsar 2rd IRR Review, ICB-2E, video: 82Pulsar
Ionization Profile Monitor Project Current Status of IPM Buffer Board Project 10 February 2006 Rick Kwarciany.
Testing - an Overview September 10, What is it, Why do it? Testing is a set of activities aimed at validating that an attribute or capability.
OEP infrastructure issues Gregory Dubois-Felsmann Trigger & Online Workshop Caltech 2 December 2004.
Introduction to Computer Networks 09/23 Presenter: Fatemah Panahi.
Cambodia-India Entrepreneurship Development Centre - : :.... :-:-
National Manager Database Services
EPICS Meeting, APS, June 14 th 2006 MCS-8 The 8 axes motion control system Rok Šabjan
Pulsar System Overview and Commissioning Plan Cheng-Ju Lin Fermilab Installation Readiness Review 02/08/2005 Outline: - Items from last review - Pulsar.
Trigger Software Validation Olga Igonkina (U.Oregon), Ricardo Gonçalo (RHUL) TAPM Open Meeting – Mar. 1, 2007 Outline: Status of infrastructure Schedule.
CMSC 345 Fall 2000 Unit Testing. The testing process.
AC031S/32S safety monitor: New functionality SAFETY AT WORK Date: 5/18/2009.
14 Sep 2005DAQ - Paul Dauncey1 Tech Board: DAQ/Online Status Paul Dauncey Imperial College London.
CPS216: Advanced Database Systems (Data-intensive Computing Systems) Introduction to MapReduce and Hadoop Shivnath Babu.
Cluster Finder Report Laura Sartori (INFN Pisa) For the L2Cal Team Chicago, Fermilab, Madrid, Padova, Penn, Pisa, Purdue.
IT253: Computer Organization
Database System Development Lifecycle 1.  Main components of the Infn System  What is Database System Development Life Cycle (DSDLC)  Phases of the.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
Technical Part Laura Sartori. - System Overview - Hardware Configuration : description of the main tasks - L2 Decision CPU: algorithm timing analysis.
H2OS Audit Trail And History page. What is the Audit Trail? The Audit Trail is a companion for the H2OS Customers table. It contains a historical record.
Software Engineering 2 Software Testing Claire Lohr pp 413 Presented By: Feras Batarseh.
New perfSonar Dashboard Andy Lake, Tom Wlodek. What is the dashboard? I assume that everybody is familiar with the “old dashboard”:
CMX status and plans Yuri Ermoline for the MSU group Level-1 Calorimeter Trigger Joint Meeting CERN, October 2012,
3rd April 2001A.Polini and C.Youngman1 GTT status Items reviewed: –Results of GTT tests with 3 MVD-ADC crates. Aims Hardware and software setup used Credit.
CMPE 421 Parallel Computer Architecture
L2 Upgrade review 19th June 2007Alison Lister, UC Davis1 XFT Monitoring + Error Rates Alison Lister Robin Erbacher, Rob Forrest, Andrew Ivanov, Aron Soha.
An Introduction to Designing, Executing and Sharing Workflows with Taverna Katy Wolstencroft myGrid University of Manchester IMPACT/Taverna Hackathon 2011.
Simple ideas on how to integrate L2CAL and L2XFT ---> food for thoughts Ted May 25th, 2007.
Precomputation- based Prefetching By James Schatz and Bashar Gharaibeh.
RICH upgrade simulation: updates RICH upgrade-software meeting 1 S.Easo.
TK Dry Gas System Operation  System overview  Dry Gas Consumption  Interlocks and thresholds  Documentation  Operational model  Final comments.
L2 Status and Plan Matt Worcester, Heather Ray, Monica Tecchio, Myron Campbell, Jane Nachtman, David Saltzberg, Tom Wright, Steve Kuhlmann, Karen Byrum,
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Trigger Commissioning Workshop, Fermilab Monica Tecchio Aug. 17, 2000 Level 2 Calorimeter and Level 2 Isolation Trigger Status Report Monica Tecchio University.
Online monitor for L2 CAL upgrade Giorgio Cortiana Outline: Hardware Monitoring New Clusters Monitoring
New L2cal hardware and CPU timing Laura Sartori. - System overview - Hardware Configuration: a set of Pulsar boards receives, preprocess and merges the.
Pulsar Status For Peter. L2 decision crate L1L1 TRACKTRACK SVTSVT CLUSTERCLUSTER PHOTONPHOTON MUONMUON Magic Bus α CPU Technical requirement: need a FAST.
Hardware: Software:
L2TS and Plan for Integration Cheng-Ju Lin Fermilab Pulsar Meeting 06/11/2004.
L2toTS Status and Phase-1 Plan and Pulsar S-LINK Data Format Cheng-Ju Lin Fermilab L2 Trigger Upgrade Meeting 03/12/2004.
Joint Commissioning (1) Data size issues Gene Flanagan Purdue University.
CHAPTER 6: STATIC ROUTING Static Routing 2 nd semester
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
I/O and Metadata Jack Cranshaw Argonne National Laboratory November 9, ATLAS Core Software TIM.
Advanced Taverna Aleksandra Pawlik University of Manchester materials by Katy Wolstencroft, Aleksandra Pawlik, Alan Williams
BIG DATA/ Hadoop Interview Questions.
1 CMBG 2009 Planning for Obsolescence June 27, 2009 John Parler South Carolina Electric & Gas.
Taverna allows you to automatically iterate through large data sets. This section introduces you to some of the more advanced configuration options for.
Overview B A B AR L1 DCT Upgrade FDR Masahiro Morii Harvard University Scope of the Project Current Status Schedule  Commissioning.
ANALYSIS TRAIN ON THE GRID Mihaela Gheata. AOD production train ◦ AOD production will be organized in a ‘train’ of tasks ◦ To maximize efficiency of full.
Unit Hardware Troubleshooting
Managing Windows Server 2012
CMS November Upgrade Week
Level 1 (Calo) Databases
Quick Start Guide for Visual Studio 2010
Static Routing 1st semester
L1 simulation review Aug 2005 Jamie Boyd
L2 CPUs and DAQ Interface: Progress and Timeline
Distance Vector Routing Protocols
Static Routing 2nd semester
MS Confidential : SharePoint 2010 Developer Workshop (Beta1)
Presentation transcript:

Joint Commissioning (2) Commissioning plan Gene Flanagan Purdue University

Outline The plan Status What next

The plan thus far 1)To “commission” both systems independently in order debug and get to the point of taking/validating physics data Ping pong stores between running l2xft & l2cal 2)Combine upgrades into one system (some of this ideally done in parallel with (1)) 3)Setup/validate new build node/ trigger tables 4)Learning to drive ( driving with new pc’s ) Items 3 & 4 allow us to decouple from the old pc’s and start running upgrades as part of a default configuration. A lot of the work associated with these tasks were done in the context of L2CAL but are required for both upgrades

General; current situation Have 2 new pc’s and multiple copies of all inputs New default decision PC runs –(SVT,MUON,RECES,CLUSTER,4xL2CAL) –Currently runs PHYSICS_4_02[7,894,690] The spare pc runs parasitically with –(3(6)XFT, SVT, with merged CLUSTER+RECES+MUON, 4xL2CAL) –Same table as decision pc

Status of individual systems L2Cal –Data integrity: see Giorgio/Dans talks –Test triggers running ( officially built table ) –Currently working on validation of algorithms L2XFT –Data integrity: see talks by Andrew & Alison –Working on test triggers

What individual upgrades still need to do L2CAL –Finish physics validation –Need to take care of Tau triggers –Need to move all monitoring to official TrigMon –… L2XFT –Need to move toward test triggers and physics validation † –Understand features upstream in data path (such as bc mismatches) –Address issues with data volume –…

Status of combined system Running L2CAL & L2XFT (3 input) fails at 240e30 ( works below 190e30 ) –Has been hard to get detailed information about failure mode –Current information suggests large data size & bus contention (see earlier talk) Need to alleviate the problem fast in order to have a chance of validating the full system before the shutdown

The plan (2) Full system commissioning schedule will likely depend on how data volume issue is resolved Regardless of how the data volume issue is resolved it is desirable to put a event size cut upstream of the PC

Summary 1)We are counting on the review committee to help us find a solution to the data volume issue soon 2)Meanwhile we will continue the current plan of running the combined system with 6-L2XFT parasitically to see what we can learn at high lumi 3)Need to make sure the new system is not on the edge