1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II ASAC-2007, April. 23, 2007 Injection System with a Booster in Separate Tunnel T. Shaftan for the NSLS-II team.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Authorization Basis Steve Hoey, NSLS-II ESH Manager Project Advisory Committee February 8-9, 2011.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Geoff Pile FAC Review - Undulator 12 November 2008 LCLS Undulator System Overview and Fabrication Geoff Pile.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
David H. Dowell Injector Physics/Diagnostics/Gun&L0 RF April 29-30, 2004 Injector Physics / Diagnostics / Gun & L0 Linac.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Operations Erik D. Johnson, Deputy ALD for Programs NSLS-II Project Advisory Committee February 8-9, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Review of May 29 Excursion Bob Casey.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
1 BROOKHAVEN SCIENCE ASSOCIATES The Path to Accelerator Commissioning F. Willeke Accelerator Systems Director NSLS-II PAC Meeting December 10-11, 2009.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
1 BROOKHAVEN SCIENCE ASSOCIATES LBT Diagnostics Installation Update Dan Padrazo Diagnostics & Instrumentation Group Feb 1, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Commissioning Plans F. Willeke 9 th ASAC Meeting for NSLS-II Project February 1-2, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Systems for Accelerator Operations Safety Erik Johnson ASD Deputy Director and Interface Manager NSLS-II ASAC Meeting October.
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
BROOKHAVEN SCIENCE ASSOCIATES 0 Top-Off Safety Yongjun Li ASAC Meeting October 22, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
1 1. Some recent views ( ) 2 Linac tunnel
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
Environment, Safety and Health
EBIS ARR Jim Alessi May 4- 7, 2010 Technical Overview.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
NSLS-II Transfer Lines BUDKER INSTITUTE OF NUCLEAR PHYSICS NOVOSIBIRSK.
1 BROOKHAVEN SCIENCE ASSOCIATES High Level Applications Infrastructure and Current Status Guobao Shen, Lingyun Yang* Controls Group & Accelerator Physics.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
1 BROOKHAVEN SCIENCE ASSOCIATES Injector Status Timur Shaftan, Injector Group Leader 9 th ASAC meeting for NSLS-II Project February 1-2, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
LHC Injectors Upgrade Project 1/12/2010 R. Garoby.
Dfernandez Computing & Controls Dec 3/4 MaxIV Control Systems for Accelerators and Automation David Fernández. ALBA Computing & Controls.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Installation Gregory Fries, Project Engineer 8 th ASAC meeting for NSLS-II Project May 10-11, 2011.
Notes from Tom’s visit 1. Controls is under-staffed 2. Common Diagnostics platforms (BPM, FCT, DCCT, BLM,…) 3. Where possible, ‘Smart’ Diagnostics, running.
ESS Vacuum Standardization
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
Have a chance to operate your own beam at CERN
WG2 Summary: Diagnostics, measurements, and commissioning
Injector Performance Requirements Conventional Facilities Update
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
Advanced Research Electron Accelerator Laboratory
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Electron Beam Systems Wrap-up
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
ThomX – Commissioning Meeting – 25/01/2018
Injector/Linac Design Status C. E
LCLS e- Beams System Overview
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS e- Beams Systems Manager
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11, 2011

2 BROOKHAVEN SCIENCE ASSOCIATES Introduction Linac Commissioning is scheduled to start November 7, It is anticipated to last until the end of the year. Obtaining authorization is required prior to commissioning. The authorization process involves the NSLS-II project, the lab ESH committee, lab management and the DOE. The focus of this talk is path to authorization.

3 BROOKHAVEN SCIENCE ASSOCIATES Linac Commissioning Task Force On December 15, Ferdinand appointed the Linac Commissioning Task Force who’s task is to coordinate commissioning of the NSLS-II linac Members: Ray Fliller – Injection Systems, Task Force Lead Brett Parker – Injection Systems Joe Delong – Controls Feng Gao – RF Om Singh – Diagnostics Bob Casey – ESH Andrew Ackerman – ESH Mike Buckley – ESH Randy Church – Operations Mike Santana – Operations Timur Shaftan – Injection Systems Group Leader Jim Rose – RF Systems Group Leader Ferdinand Willeke – Accelerator Systems Division Head Meetings are held bi-weekly and as needed. Current focus has been the Authorization Basis documentation required for linac commissioning in culminating in the Accelerator Readiness Review.

4 BROOKHAVEN SCIENCE ASSOCIATES Zoom in to linac vault Equipment installation proceeds through the penetration and ends at a gate valve. This section will not see beam during commissioning End of Linac ICT LB-B2 LB-B1

5 BROOKHAVEN SCIENCE ASSOCIATES Operation Authorization Process We are here, Send to DDO this week Courtesy of Steve Hoey. May 28, 2011 May 31, 2011 October 17, 2011 November 7, 2011 April 12, 2011 ~2009

6 BROOKHAVEN SCIENCE ASSOCIATES Linac Commissioning Schedule Lab ESH committee reviews the Authorization Basis (AB) Documentation – April 12, 2011 – finished. Deputy Director of Operation approval of AB documentation – package to DDO this week BHSO receive AB Documentation for Review – May 28, 2011 ARR Team Appointment – May 31, 2011 BHSO Approval of AB documentation – July 8, 2011 Injector Building Beneficial Occupancy Date - July 28, 2011 Linac Installation Begins - August 11, 2011 Linac ARR - October 17, 2011 Linac Commissioning Begins – November 7, 2011

7 BROOKHAVEN SCIENCE ASSOCIATES Immediate Next Steps Develop the Linac Commissioning Plan and other necessary documentation Linac Commissioning Plan outlines what needs to occur to be ready for commissioning. Get necessary AB documentation approvals from DDO and BHSO. Interface with Research Instruments to develop a linac commissioning sequence A draft sequence exists. I will travel to RI in late June with this as one of my tasks. Finish High Level application requirements and specifications Prepare to the ARR

8 BROOKHAVEN SCIENCE ASSOCIATES Linac Beam Parameters

9 BROOKHAVEN SCIENCE ASSOCIATES Diagnostics Available for Commissioning Flag ICT BPM Faraday Cup Faraday Cup FCT Installed but sees no beam Safety Shutter

10 BROOKHAVEN SCIENCE ASSOCIATES Linac Parameters and Measurements necessary for commissioning Beam ParameterValueMeasurement Energy200 MeVDipole & Flag Current0.5nC/bunch in SPM and 15 nC train in LPM Wall Current Monitors in Linac, Integrating Current Transformer at Linac output, Faraday cup in both beam dumps. Fill Pattern1 bunch in SPM, bunches separated by 2 ns, 10% relative charge difference per bunch in LPM Wall Current Monitors in Linac, Fast Current Transformer at Linac output, Faraday cup in Dump on straight ahead transport line Energy Spread0.5%Dipole and 2 flags Transverse Emittance 4  x  x ’ =155nm Three Screens and Quadrupole scan in transport line

11 BROOKHAVEN SCIENCE ASSOCIATES List of High Level Applications (not exhaustive) operators panel vacuum status PS status Temperature measurement beam loading compensation Water/ Compressed air status synchronization panel/ bunch select bunch pattern monitor RF feedbacks charge/ trajectory/ beam size measurements energy/ energy spread measurement emittance measurement (3 screen + quad scan) charge/ bunch pattern measurements interlock status + shutters status rad monitors status loss measurement system Linac current monitor panel Want to have specifications for all high level applications by the end of May

12 BROOKHAVEN SCIENCE ASSOCIATES Conclusion Linac Commissioning Task Force has been assembled to coordinate commissioning tasks. Task force’s main focus to date has been on developing the AB documents with ESH. This is on schedule The path to commissioning is clear both from ESH and physics point of view.

13 BROOKHAVEN SCIENCE ASSOCIATES SPARES

14 BROOKHAVEN SCIENCE ASSOCIATES

15 BROOKHAVEN SCIENCE ASSOCIATES

16 BROOKHAVEN SCIENCE ASSOCIATES