E Huedem, Nov 27 20071 ILC VALUE ENGINEERING SESSION of POWER & COOLING (Focus on Main Shaft 7) November 27, 2007 INFORMATION PHASE Conventional.

Slides:



Advertisements
Similar presentations
M. Ross Project Advisory Committee Review 13 December, 2012 KEK Main Linac Layout – Two variants for two different types of sites GDE PAC Review.
Advertisements

Nov. 17, 2008 ILC08 Global Design Effort 1 Americas KlyCluster Cost Analysis Overview Tom Lackowski RF & Sum reported by Peter H. Garbincius.
11/27/2007ILC Power and Cooling VM Workshop Mike Neubauer 1 RF Power and Cooling Requirements Overview from “Main Linac Power and Cooling Information”
Nov. 07 DR-KOM-CFS 1 Damping Rings KOM Conventional Facility & Siting Overview Tom Lackowski Acknowledgment: Atsushi Enomoto, Jean-Luc Baldy, John Osborne,
9/17/07 ILC Detectors 1 Conventional Utilities Tom Lackowski.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
November 17, 2008 ILC08 HVAC and VE Update November 17, 2008 ILC CFS Workshop 2008 Chicago Lee Hammond, Fermilab Global Design Effort.
CONVENTIONAL ELECTRICAL TDR DESIGN Randy Wielgos March 22, 2012 ILC CFS Baseline Technical Review.
1 ILC Mechanical & Electrical Review Conventional MECHANICAL System Design Summary Emil Huedem, FNAL Lee Hammond, FNAL Parsons Mechanical Team (Tim Sheehan,
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
1 HVAC OVERVIEW and VALUE ENGINEERING ITEMS August 13, 2008 CLIC Working Group CES Lee Hammond, Fermilab.
Value Engineering Session Air Treatment / HVAC November 27, 2007 Lee Hammond, FNAL CFS.
Central Region Discussion Power and Cooling GDE Beijing-CFS.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 Process Water and Air Treatment 01 June 2007 Emil Huedem, Maurice Ball, Lee Hammond Fermilab.
ILC Energy Efficiency Marc Ross and Ewan Paterson, SLAC CFS-ADI Joint Meeting ICEPP University of Tokyo 9 April 2014 Three examples: 1) higher quality.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Positron Source Relocation 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
Global Design Effort - CFS LCWS CONVENTIONAL FACILITIES AND SITING GROUP Parallel Session Overview A. Enomoto, V. Kuchler, J. Osborne.
ILC CFS AD&I Daresbury Lab Summary J.Osborne / V.Kuchler / A.Enomoto.
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update November.
BDS Magnet-Power System-Facility Optimization1 ILC BDS Kickoff Meeting Basis for Magnet, Power System and Cooling Facility Optimization Discussion Paul.
November 17, st XFEL / ILC Meeting 1 ILC GLOBAL Design Effort The Current ILC Twin Tunnel Design Wilhelm Bialowons and Nicholas Walker · MPY.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
RDR Report Writing Nan Phinney SLAC. 7/20/06 VLCW06 Global Design Effort 2 GLC Report Working model is the 2003 GLC Report ch 4-7
Date Event Global Design Effort 1 ILC UPDATE Vancouver to Valencia Ewan Paterson Personal Report to SiD Collaboration Oct 27, 2006.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
Global Design Effort 1 Possible Minimum Machine Studies of Central Region for 2009 Reference, ILC Minimum Machine Study Proposal V1, January 2009 ILC-EDMS.
SLAC_OCT07 BDS-KOM-CFS 1 Beam Delivery System & Interaction Region KOM Conventional Facility & Siting Overview Fred Asiri/SLAC Acknowledgment: Atsushi.
Global Design Effort1 September 20-22, 2006 MAC Review Power and Water breakout (mixed results) Marc Ross GDE.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
ILC BDS Kickoff Meeting Magnet Power Supplies RDR Concepts and Completeness Paul Bellomo SLAC Power Conversion Department October, 2007.
Nick Walker – SA meeting KEK Treaty Points and Costing Guidance Nick Walker 1 st System Area Managers Meeting KEK –
Aug 23, 2006 Half Current Option: Impact on Linac Cost Chris Adolphsen With input from Mike Neubauer, Chris Nantista and Tom Peterson.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
Process Water VE Updates (Main Linac Only) Emil Huedem FNAL ILC Meeting - CHICAGO Nov E. Huedem 2008.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
Aug 23, 2006 Low Power HLRF System and Impact on Distributed RF System Shigeki Fukuda and Task Force Team of DRFS in KEK KEK.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP CFS.
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update December.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Global Design Effort - CFS ILC Integrated Design Meeting, DESY, May ML Single Tunnel Configurations In Deep Underground Accessed with Long.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
1 CFS Utilities – What’s included in RDR for IR July CFS Utilities – IRENG WG C WATER COOLING: none. Unknown loads on IR. Only have water plants.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
E Huedem, June RDR PROCESS WATER & VALUE ENGINEERING ITEMS June 5, 2008 GDE Meeting-ILC CFS Workshop in Dubna, Russia Emil Huedem, Fermilab.
CFS EDR KICK OFF MEETING Air Treatment August 23, 2007 Lee Hammond, FNAL CFS.
E- source kick-off meeting e- Source RDR- Conventional Facility & Siting Overview Fred Asiri/SLAC.
ILC Utility Design Study for Kitakami-site
Update on the PSB Cooling and Ventilation Systems
ILC Power and Cooling VM Workshop
Conventional Facility & Siting (CF&S) Overview for the Positron Source
CFS EDR KICK OFF MEETING Process Water August 23, 2007
Americas KlyCluster Cost Analysis Overview
CONVENTIONAL FACILITIES presented by Peter H. Garbincius
COOLING & VENTILATION INFRASTRUCTURE
CLIC Civil Engineering Update
ILC CFS AD&I Daresbury Lab Summary
Maintenance at ALBA facility: Strategy for the conventional services
ILC - Global Design Effort
Presentation transcript:

E Huedem, Nov ILC VALUE ENGINEERING SESSION of POWER & COOLING (Focus on Main Shaft 7) November 27, 2007 INFORMATION PHASE Conventional Facility Process Cooling Water Concept Emil Huedem FNAL

E Huedem, Nov Outline Introduction Heat Loads (Total, Main Linac only) Conceptual Design Previous “Cost Reduction” Items Items going forward (criteria/heat load, delta T) Summary

E Huedem, Nov Introduction Some non-conventional abbreviations used RDR (Reference Design Report) -work done between ~Mar 2006 to Nov 2006 Various Area in the machine –BDS (Beam Delivery System) –DR (Damping Ring) –ML (Main Linac) –IR (Interaction Region) –RTML (Ring To Main Linac) EDR (Engineering Design Report) -work to be performed from Oct 2007 to Mid 2010? CFS (Conventional Facility and Siting) -our group (civil, electrical, hvac, process water, safety, survey)

E Huedem, Nov ML RF equipment BDS Magnets Power Supplies Water Dump RTML Magnets RF Equipment Power Supplies Water Dump Sources ?magnets? Power supplies IR ?detector components? Others AC Transformers What are the heat producing equipment to water/air? e- (electron side)e+ (positron side) Machine is expected to run all season of the year DR Magnets RF Equipment Power Supplies Introduction

E Huedem, Nov ML RF equipment BDS Magnets Power Supplies Water Dump RTML Magnets RF Equipment Power Supplies Water Dump Sources ?magnets? Power supplies IR ?detector components? Others AC Transformers e- (electron side)e+ (positron side) Machine is expected to run all season of the year FOCUS DR Magnets RF Equipment Power Supplies What are the heat producing equipment to water/air? Introduction Remove Equipment Heat (to Water/Air)

E Huedem, Nov Nov 2006Sep 2007 RDREDR Mar 2008?? Criteria GatheringCosting Status Cooling infrastructure in RDR was conceptual, and very little on paper. Criteria and heat loads were incomplete. Most only have total KW (use scaling approach) Still need to layout/conceptualize LCW water system, establish other heat load components in service tunnel, get updated loads, firm up environmental criteria. Various Cost reduction sessions We’re here Jun 2006 No work done-this periodDesign/Costing Changes/ reviews Introduction Perspective reviews

E Huedem, Nov SEE SEPARATE LARGE PRINTOUT Heat Loads IR = None

E Huedem, Nov SEE SEPARATE LARGE PRINTOUT Heat Table dated 11/27/06 – used in RDR Current Heat Table (dated 10/31/07)- ongoing SEE SEPARATE LARGE PRINTOUT Heat Table dated 11/27/06 – used in RDR Current Heat Table (dated 10/31/07)- ongoing LCW/Process Water Load is about 100 KW per RF (RDR) Racks require separate cold water system Low Conductivity Water (LCW) Heat Loads These are the RF equipment

E Huedem, Nov KLYSTRON SOCKET TANK/GUN RF TRANS- FORMER CHARGING SUPPLY MODULATOR PULSE TRANSFORMER CONV TRANS- FORMER WAVEGUIDE 24 LOADS AND 26 CIRCULATORS SERVICE TUNNEL BEAM TUNNEL ATTENUATOR KLYSTRON SOLENOID KLYSTRON BODY/ WINDOW KLYSTRON COLLECTOR Plan View of ONE ML RF UNIT used in RDR

E Huedem, Nov ELECTRON SIDE BDSRTML 2 BDS 4 RTML 8 6 POSITRON SIDE Design Constraints Surface Plant Locations Tunnel Depth DR ML ~ 5 Km Start of ML Tunnel about 450 ft depth

E Huedem, Nov RF64 RF56 RF58 RF64 RF 104 RF114 RF + 50% of e-plus load 64 RF + 50% of e-plus load ELECTRON SIDE BDS RTML 2 BDS 4 RTML RF64 RF 54 RF56 RF64 RF 104 RF64 RF110 RF + e-minus load POSITRON SIDE No of RF UNIT used in RDR for MAIN LINAC only DR Start of ML 560 RF for ML !

E Huedem, Nov RF64 RF56 RF58 RF64 RF 104 RF114 RF + 50% of e-plus load 64 RF + 50% of e-plus load ELECTRON SIDE BDS RTML 2 BDS 4 RTML RF64 RF 54 RF56 RF64 RF 104 RF64 RF110 RF + e-minus load POSITRON SIDE No of RF UNIT used in RDR for MAIN LINAC only DR Start of ML FOCUS on RDR

E Huedem, Nov

E Huedem, Nov Cooling Tower 85F Process Water Heat Exchangers (Cavern ) 90F Process Water Each LCW Skid Serve 4 RF 95F LCW Chiller Chilled Water There are 104 RF stations served by Shaft 7 Chilled Water Fan Coil To RF system components. No detailed equipment info during RDR. Assumed average plant 20 delta F during RDR Use Shaft 7 Service Tunnel BeamTunnel 78F Wet Bulb Basic Design Concept in RDR Pump/ HX skid for racks Constant Flow Pumps

E Huedem, Nov Cooling Tower 85F Process Water Heat Exchangers (Cavern ) 90F Process Water Each LCW Skid Serve 4 RF 95F LCW Chiller Chilled Water There are 104 RF stations served by Shaft 7 Chilled Water Fan Coil To RF system components. No detailed equipment info during RDR. Assumed average plant 20 delta F during RDR Use Shaft 7 Service Tunnel BeamTunnel 78F Wet Bulb Basic Design Concept in RDR Pump/ HX skid for racks Constant Flow Pumps Since Sep 07, for EDR, get as much info, and evaluate to get HIGH DELTA T (started-see later slides)

E Huedem, Nov x 26 skids Water Plant at Shaft MW (2,956 Ton) x 26 qty Basic Design Concept in RDR

E Huedem, Nov Cooling Tower Used BAC (BaltimoreAircoil) HXV Closed Circuit Tower in RDR Used in RDR

E Huedem, Nov Heat Exchanger Used in RDR Used Tranter Plate Heat Exchanger in RDR

E Huedem, Nov About RDR Costs Approach: estimated cooling infrastructure at Shaft 7, and other areas were scaled (full & partial) depending on the total heat loads CFS cost is about ?? % of the whole ILC cost Process Water is about 15% of the total CFS cost (less if chilled move to HVAC) Cost Drivers in Process Water (% of Process Water Cost) High Heat Load LCW system 38% Process Piping 12% Chilled Water related items 28% (will be part of HVAC in EDR)

E Huedem, Nov Run both tunnel and electronics hotter using 85F tower water supply Increase all primary cooling pipe diamters to reduce shaft horsepower Reduce number of cooling skids Stack heat loads to reduce primary flow and increase delta T ML Meeting May July to Sep cost/power reduction exercises 2006 Evaluate power usage Cut number of skids Raise delta to klystron collector 2X Reduce or eliminate chilled water usage Need watt per watt number Increase all primary cooling pipe diameters to reduce shaft horsepower requirements on water flows. The pumping costs for the primary cooling loops are larger than desired. Remove use of deionized water (LCW vs Non-LCW Water)           Need Component Info (ongoing) Can’t due to HX & IL wetbulb, 85F amb was spec Ray has watercooled racks, tunnels has load to air Users against, 100% non-lcw not doable Examples of previous various “Cost-Reduction” (not VE) sessions Need more Info (ongoing)

E Huedem, Nov Caltech Review Oct   Examples of previous various “Cost-Reduction” (not VE) sessions

E Huedem, Nov Mac Meeting Review Jan 2007 Orsay Cost Review May 2007 Water System Delta T Pipe Velocity vs size vs HP Need Component Info (ongoing) Examples of previous various “Cost-Reduction” (not VE) sessions

E Huedem, Nov Cooling Plant watt* per watt** information (It VARIES!!) Sep 2006 *electrical **heat removed Centrifugal chillers (only *no pump, no tower* ) full load (~ 0.55 KW per ton0.16 watt per watt Data Centers typical (from Uptime Institute) = 0.55 watt per watt Packaged Chilled water plant ( from Superior (0.7KW/ton)0.199 watt per watt Above average (0.85 KW/ton)0.242 watt per watt Below Average (1.3 KW/ton)0.370 watt per watt Inferior (1.6 KW/ton)0.455 watt per watt CUB installed (LCW & chilled) watt per watt Tevatron -installed(mostly LCW to pond from Maurice)0.18 watt per watt Main Injector -installed (mostly LCW to pond from Maurice)0.16 watt per watt Shaft 7 COMBINED Chilled & process *wag on equipment pressure drop* using closed circuit towers (preliminary layout around Sep 2006) 0.17 watt per watt Shaft 7 process only *wag on equipment pressure drop* NO Chilled (preliminary layout around Sep 2006) 0.11 watt per watt Shaft 7 chilled only *wag on equipment pressure drop* NO process (preliminary layout around Sep 2006) 0.35 watt per watt Udated Shaft 7 *wag on equipment pressure drop* using closed circuit towers (RDR conceptt around Nov 2006) TBD watt per watt TYPICAL e.huedem

E Huedem, Nov To EDR Finish criteria / Heat Table VE Evaluate for High Water Delta T / Pipe Sizes Update concept design / Refine estimate

E Huedem, Nov Heat Table improvement! Oct 2007, but still incomplete

E Huedem, Nov Heat Table improvement! Oct 2007, but still incomplete Loads Increasing Chris Nantista Shigeki (check min Flow?) Beam Tunnel Temperature? Chris and Keith? Cassell Jensen Shigeki ??

E Huedem, Nov TUNNEL PENETRATION KLYSTRONMODULATOR LLRF ATTENUATORS Heat Loss from Cryo ~5w/m (T.Peterson)~(-0.18KW) Heat Loss from RockWallignored Heat Loss (Air ) ~38 w/m ~(-1.3 KW) *15F delta T air at 2.5Km Heat Gain (Waveguide) = 5.9 KW~ +5.9 KW NET LOAD to AIR (beam tunnel) KW At Service Tunnel (to air -load to fancoil) = 1.17KW At Penetration (water) = 0.676KW? At Beam Tunnel (to air )= 5.9KW* Assume issue with mixing air between tunnel, watercooled waveguide in the penetration by??? * if the straight run of waveguide in beam tunnel are watercooled, the remaining load to air becomes 5.4KW Sealed cn eh Oct Waveguide Heat of ONE RF UNIT (Oct ) See HVAC slides later, for option of aircooled wavgd at penetration & about rock contrbtion See HVAC slides later, for option of aircooled wavgd at penetration & about rock contrbtion

E Huedem, Nov Cooling Tower 85F Process Water Heat Exchangers (Cavern ) Each LCW Skid Serve 4 RF 95F LCW To RF system components. No detailed equipment info during RDR. Assumed 20 delta F during RDR Use Shaft 7 Service Tunnel BeamTunnel 78F Wet Bulb High Delta T Impact– Process Water only Immature LCW in RDR: need to layout and understand cost impact Tunnel Header ~ 8% of Process water cost Other piping ~ 4% of Process water cost Equipment

E Huedem, Nov Cooling Tower 85F Process Water Heat Exchangers (Cavern ) Each LCW Skid Serve 4 RF 95F LCW Chilled Water To RF system components. No detailed equipment info during RDR. Assumed 20 delta F during RDR Use Shaft 7 Service Tunnel BeamTunnel 78F Wet Bulb High Delta T Impact– Process Water only Immature LCW in RDR: need to layout and understand cost impact Tunnel Header ~ 8% of Process water cost Other piping ~ 4% of Process water cost Equipment Samples on next few slides

E Huedem, Nov Tunnel Pipe Sizes Reasonable Balance between increased pumping hp, piping first cost, noise/vibration.

E Huedem, Nov Tunnel Pipe Sizes Reasonable Balance between increased pumping hp, piping first cost, noise/vibration. RDR but higher pipe velocity

E Huedem, Nov Means 2006 Schedule 40 Welded Steel Pipe Cost

E Huedem, Nov Tunnel Pipe Sizes Reasonable Balance between increased pumping hp, piping first cost, noise/vibration.

E Huedem, Nov Tunnel Pipe Sizes Reasonable Balance between increased pumping hp, piping first cost, noise/vibration.

E Huedem, Nov Tunnel Pipe Sizes Reasonable Balance between increased pumping hp, piping first cost, noise/vibration.

E Huedem, Nov Tunnel Pipe Sizes Reasonable Balance between increased pumping hp, piping first cost, noise/vibration.

E Huedem, Nov Impact on others Equipment =? Other Piping =? LCW =?

E Huedem, Nov High DELTA-T RDR has incomplete component criteria to evaluate the delta T. Used 20Fdelta average for Shaft 7 plant. LCW SKID 1 RF =100KW ? Pipe Distribution ?

E Huedem, Nov Stacking of Loads / High Delta T 1 RF

E Huedem, Nov Stacking of Loads / High Delta T 1 RF

E Huedem, Nov RF Stacking of Loads / High Delta T

E Huedem, Nov High DELTA-T RDR has incomplete component criteria to evaluate the delta T. Used 20Fdelta average for Shaft 7 plant. LCW SKID 1 RF =100KW ? Pipe Distribution ?

E Huedem, Nov Stacking of Loads / High Delta T 8 liter per min per load SEE SEPARATE LARGE PRINTOUT 2 RF

E Huedem, Nov Stacking of Loads / High Delta T 3 liter per min per load SEE SEPARATE LARGE PRINTOUT 2 RF

E Huedem, Nov Piping implications /more piping?? (work for EDR) Flow at Loads/circulators can be reduced??(Help from Chris Nantista of Slac) Other missing info (Chris Nantista, Keith, etc) Change other low delta T components & compare value?? (Jensen? Maurice?) We assume the current numbers are right. How about minimum flow for Collector?? (Shigeki working on this with vendors)..maybe more than what’s currently specified (37 liter per min), maybe around ?100?, if so delta T reduced unless small pump dedicated to collector (power implication)??

E Huedem, Nov Summary Design concept presented (RDR) is preliminary, had incomplete criteria, BUT many cost reduction meetings We’re in the early EDR data/criteria gathering period, (incomplete criteria). Showed preliminary iteration with delta T, expect many meetings Need criteria frozen (not a moving target),and time/resources to actually work on this (EDR), and whatever list this VE will generate continue main focus on FIRST COST REDUCTION??? Hope to see lots of constructive discussions, and HOPE TO HAVE A PRODUCTIVE SESSION Thank you for your attention.