RPC project status report RPC IB meeting 28 June 2011 Pigi Paolucci
Outline CMS and RPC news Organization chart Manpower issues Upgrade structure 2011 ESP 29/03/112RPC IB meeting - Pigi Paolucci
CMS reached the fb -1
LHC plans
Trigger L1-RPC : 0:04:02min/ 535 hours A closer look to that 0% !.... No any significant RPC downtime & dead time during the last 3 months
Trigger history plot 29/03/11RPC IB meeting - Pigi Paolucci6 FullBarrel Endcap Mu 10Beam Halo
Run 2011 RPC shift The present table contains the requested shift per institution. The shift are calculated considering 48 weeks of runs and 3 shifter per week (DOC, DM and CAF) plus 15% of contingency. The request is to provide 2 shift(weeks)/EPS Shifts done or assigned up to 06/30/2011 M&O 2010# ESPNumber of required 2011 shifts (weeks)DOC 2011 (weeks) DM 2011 (weeks) CAF 2011 (weeks) Total shift done up to 06/30/2011 Peking univ SKK Univ (Korea) 2411 Korea Univ (Korea) Chonnam (Korea) 00 Mumbai-Barc (India) 12 Chandigarh (India) Ghent (Belgium) Brussel Univ (Blgium) 12 Uniandes 24 Pakistan Asrt-Enhep (Egypt) 3611 CERN 48 Bari INFN - LNF Napoli Pavia Sofia Univ Sofia INRE RPC TOTAL See Gabriella talks
Project Manager P. Paolucci M. Tytgat & G. Pugliese Project Manager P. Paolucci M. Tytgat & G. Pugliese Run Coordinator L. Benussi H. Shahzad N. Zaganidis Run Coordinator L. Benussi H. Shahzad N. Zaganidis DPG D. Piccolo K. Bunkowski C. Carillo DPG D. Piccolo K. Bunkowski C. Carillo Upgrade G. Iaselli A.Sharma S. Buontempo Upgrade G. Iaselli A.Sharma S. Buontempo Institution Board L. Litov Resource manager A. Colaleo Steering committee W. Van Doninck, M. Maggi H. Hoorani, A. Colaleo, A. Sharma (PM+DPM+RC+TC+DPG) 29/03/118RPC IB meeting - Pigi Paolucci Tech. Coordination S. Buontempo A. Dimitrov Tech. Coordination S. Buontempo A. Dimitrov Conference Committee S. Park, B. Pavlov Conference Committee S. Park, B. Pavlov Editorial board S. Qian, M. Abbrescia S. Bianco Editorial board S. Qian, M. Abbrescia S. Bianco
29/03/119RPC IB meeting - Pigi Paolucci Technical Coordination S. Buontempo A. Dimitrov Technical Coordination S. Buontempo A. Dimitrov Mainten. & repair. (RE,RE) Dimitrov & Shahzad Mainten. & repair. (RE,RE) Dimitrov & Shahzad Upgrade G. Iaselli A. Sharma S. Buontempo Upgrade G. Iaselli A. Sharma S. Buontempo Bakelite HPL CERN test stand CERN CERN test stand CERN Gap production Chamber mechanics Chamber mechanics Ghent site M. Tytgat Ghent site M. Tytgat India site L. Pant India site L. Pant CERN site CERN CERN site CERN Chamber QC at CERN Chamber design Off-detector electronic Off-detector electronic Cooling J. Crotty Cooling J. Crotty Gas Benussi Gas Benussi Trigger Warsaw Trigger Warsaw Documentation Dimitrov Documentation Dimitrov Equipment DB D. Uzunova Equipment DB D. Uzunova Electronics F. Loddo Electronics F. Loddo DCS hardware Resp. DCS hardware Resp. Test beam Nicolas Test beam Nicolas R&D N. Zaganidis R&D N. Zaganidis GIF activity Power system Power cable Signal cable Chamber production High eta Chamber instal. Cable instal. Commissioning at P5 Commissioning at P5 RE1/1 at P5 Run coordination & Upgrade Manpower needed Not covered Covered
Critical task (March 2011) We still have few important tasks not covered: – Online Database (Warsaw is looking for a student) – Detector Control System (none) – Power system (temporary solution) – Offline Database (Bari group) – WMB (none from July 2011) 29/03/11RPC IB meeting - Pigi Paolucci10
Critical tasks (Today) 2 tasks have been now covered: – Online Database (Warsaw is looking for a student) – Detector Control System – Electronic Coordinator (F. Loddo) Power system (Hassan and Anton) – Offline Database (Korea Univ & Bari group) Time needed to have experts – WMB (covered until October 2011) Mihee will work with Umberto on noise in WMB 29/03/11RPC IB meeting - Pigi Paolucci11
Next issues (March 2011 and now) WBM deployment at CAF/P5 !!! manpower needed Working at CAF/P5 very well OK Historical plots and noise have to be included DQM efficiencies and DB Under test Noise and DB Geometry and noise per roll ready Noise per strip asap CMS center instructions for shiftersOK Upgrade schedule and milestones – under definition Upgrade money matrix- still under discussion in CMS 29/03/11RPC IB meeting - Pigi Paolucci12 PVT
2011 manpower Cimmino2 monthsFebRC/DPG Mircho3 monthsMayRC/DPG Umberto3+3 months (RPC & CERN)JuneRC/DPG – 1+1 month (CERN + RPC)Sept Alaa3+3 months (RPC & Egypt)AugDPG Uzunova5 months (RPC & upgrade)JulyTC/Up – 2 months from CMS TC – 2 months from RPC upgrade Dec Anton12 monthsDecTC 29/03/11RPC IB meeting - Pigi Paolucci13
manpower news We have two very critical position to assure for the next two year: – Detector expert & Trigger and DAQ expert positions are now covered in the best way by – Anton and Karol Karol fellow has been extended to Dec 2011 – Project associate for the 2012 Anton contract finish in June 2011 – Project associate for the /03/11RPC IB meeting - Pigi Paolucci14
News about RPC organization 28/06/114th RPC General Meeting - Pigi Paolucci15 RPC MB, coordinators and experts have access to a shared google documents used to prepare the weekly report to the XEB meeting: Very good way to share info ! Please ask to have access June 14th: TC: Everything was perfectly stable before the gas kill on 31th May. Then after a power-cut in SG5 and a gas kill we had 5 trips in the barrel and 1 in the endcap. All have been recovered. One chamber temporarily in SG mode till next access. Trigger: Muon Trigger rate variations observed (~9%) in last weeks, the most probable reason is variation of the RPC chamber efficiency (by 2-3%) with the pressure variation (impacting the trigger efficiency in the endcaps by 3- 4%, and thus the rate). Still not clear is the variation of the cluster size could impact the probability of promoting the low pt muons to high pt (impacting the rate on given threshold). Variation is not present with low PT cut (Mu0 and Mu7) and increase from Mu16 to Mu20 RC: stable since the HV scan - no problem with the new set of WP and efficiency very stable in time (2-3% of variation due to the pressure) P/T correction in PVSS has been discussed and defined and will be tested during the next TS DPG:DQM: experts are investigating in the offline DQM to speed-up it. Right now we are using 4MB and we already deleted histograms. Work is on going. MC: Comparison of number of RPC hits in Muon Reco of 2011 data with summer2011 MC, show nice agreement in barrel and endcap. Some small discrepancy in overlap region under study Upgrade: MB:
News about RPC organization 28/06/114th RPC General Meeting - Pigi Paolucci16 Shared google calendar with meetings and vacation (Pigi and Gabriella) – please ask to be included in the list Minutes provided by all the coordinators – thanks a lot XEB and XEC minutes circulates in real time MB and FB minutes and news in a week All info sent to Group Leader (we ask to circulate)
Action Items 28/06/114th RPC General Meeting - Pigi Paolucci17 1.HV setting with P/T correction – approved by CMS but in a human version 2.Improve history plots monitoring (current, noise, efficiency) using WBM and database 3.Include DQM trigger check in CAF duties 4.Spare components procurement 5.Long 2012shut-down plan 6.Bakelite and gap production 7.Link and Control board prototype tests at 904 (Oct- Dec)
ESP 2011 ESP 2011 have been approved by RPC and CMS Most of the RPC pledges have been approved after having consulted TC/RC/DPG/Upgrade – Some DPG task to be checked: PVT6 needed13.6 pledge Analysis3656 Up soft40 Gap prod816 End of the year RPC MB will fill the work done with the help of the coordinators Few tasks without any results. To be double checked 29/03/11RPC IB meeting - Pigi Paolucci18
ProjectActivityTaskNeeded (months)FteTotal x cat. Muon-RPCDetector HardwareTechnical coordinator6,000,50 Muon-RPCDetector HardwareChamber10,000,83 Muon-RPCDetector HardwareElectronics3,000,25 Muon-RPCDetector HardwareServices3,000,25 Muon-RPCElectronics and DAQPower System3,000,25 Muon-RPCElectronics and DAQDCS-DSS3,000,25 Muon-RPCElectronics and DAQElectronic configuration10,000,83 Muon-RPCElectronics and DAQGas Gain Monitor3,000,25 Muon-RPCElectronics and DAQDAQ and online DB4,000,33 45,00 Muon-RPCSoftware and DQMDPG coordinator6,000,50 Muon-RPCSoftware and DQMDQM12,001,00 Muon-RPCSoftware and DQMDCS & WBM12,001,00 Muon-RPCSoftware and DQMPVT6,000,50 Muon-RPCSoftware and DQMSimulation4,000,33 Muon-RPCSoftware and DQMDatabase10,000,83 Muon-RPCSoftware and DQMPrompt Analysis36,003,00 86,00 Muon-RPCOperationRun coordinator6,000,50 Muon-RPCOperationOperation Manager shift*11,000,92 Muon-RPCOperationCAF shift*11,000,92 Muon-RPCOperationData Manage shiftr*11,000,92 39,00 Muon-RPCOperationUpgrade coordinator6,000,50 Muon-RPCUpgradeSoftware4,000,33 Muon-RPCUpgradeBakelite production and test3,000,25 Muon-RPCUpgradeGap production8,000,25 Muon-RPCUpgradeChamber design2,000,25 Muon-RPCUpgradeChamber construction24,002,00 Muon-RPCUpgradeChamber test at 9047,000,58 Muon-RPCUpgradeFront-end electronic3,000,25 Muon-RPCUpgradeTrigger electronic7,000,58 Muon-RPCUpgradeServices4,000,33 Muon-RPCUpgradeR&D at high eta2,000,17 Muon-RPCUpgradeSimulation at high eta2,000,17 72,00 Muon-RPCManagementLV324,002,00 Muon-RPCManagementLV2 IB - CC - EB chairman3,000,25 Muon-RPCManagementLV2 steering committee3,000,25 272,0021,33 29/03/11RPC IB meeting - Pigi Paolucci19
ESP status (June 2011) 29/03/11RPC IB meeting - Pigi Paolucci20
2011 ESP status (country & institution) 29/03/11RPC IB meeting - Pigi Paolucci21
EPS hot task 29/03/11RPC IB meeting - Pigi Paolucci22
Conclusion Project is in good shape and many improvements have been done during the shut-down ESP pledge letters deadline is in 2 weeks. Manpower: DCS – WBM – Online experts – detector expert 2010 expenditure were in line with our budget 269 KCHF : we have to cover 2 critical tasks 2011 budget is necessary – contribution request in few days 29/03/11RPC IB meeting - Pigi Paolucci23