Folded Plate Bridge: Steel Alternative for Short Span Bridges Maury Tayarani Accelerated Bridge Program MassDOT
Folded Plate Girder System is currently applicable to simple span bridges with lengths up to 60 ft.
Folded Plate Girders are fabricated using press breaks
The bend locations are very precisely determined
The fabrication process requires rotating the girder
1 3 2 4 Fabrication Steps are Minimal 1- Bending girders 2- End Plates 3- Minimal Tie Plates 4- Shear Studs 1 3 2 4
To Resolve Availability and Rapid Delivery 1- Plate thicknesses are limited to ½ or 3/8 inches 2- Total plate width is limited to 118 inches
Stable Shape During Casting Deck No need for internal cross frames No need for external cross frames
Design is conservatively based on girders being supported at two ends, when casting deck. The actual production is based on girder sitting on prestress bed and supported continuously.
Open bottom allows easy inspection
Experimental work Concept has been extensively tested
7,500,000 Cycles
Shear Test
Uxbridge Project – Boston Mass Opened to Traffic on Nov 2011
Folded bending – Kansas Galvanizing – Valmont, Kansas Casting deck- Carrara- Vermont Contractor – John Rocchio Design – Highway Bridge Services Independent design check- G.F. Owner – MassDOT Bridge instrumentation – University of Mass
Four Folded plate with partial Depth deck delivered to site
Edge girders will have the curbs cast
Anchor bolts are provided to bolt The railing onsite
Fabrication
Delivery of girders to precast Plan for casting sub-deck
Girder Delivery
Deck Forms
Steel Reinforcement
Casting Deck
Unit Ready for Delivery
Rigging for Lift
Placing Girder Unit
Placing Girder Unit
Girder Ends
From Below
Finished Structure
Finished Roadway