SunGuide SM Software Development Project Status Meeting March 9, 2004.

Slides:



Advertisements
Similar presentations
Current Status of the FDOT SunGuide SM Software Project Robert W. Heller, Ph.D. March 16, 2005.
Advertisements

SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting for SunGuide Release 4.1 October 14,
Deploying GMP Applications Scott Fry, Director of Professional Services.
Managing the Information Technology Resource Jerry N. Luftman
APPLICATION DEVELOPMENT BY SYED ADNAN ALI.
Systems Engineering Management
Configuration Management
Module 16: Software Maintenance Using Windows Server Update Services.
16.1 © 2004 Pearson Education, Inc. Exam Managing and Maintaining a Microsoft® Windows® Server 2003 Environment Lesson 16: Examining Software Update.
Statewide Transportation Management Center Software Library System Status Meeting February 17, 2004.
Web Development Process Description
Pre-Project Activities Text Chapters 5 and 6. Pre-Project Activities 1.Contract Review 2.Development Plan 3.Quality Plan.
Server Virtualization: Navy Network Operations Centers
SunGuide SM Software Development Project Ramp Meter Firmware Discussions August 8, 2006.
Configuration Management T3 Webinar Feb 21, 2008 Chuck Larsen ITS Program Coordinator Oregon Department of Transportation.
SunGuide SM Software Development Project Status Meeting February 23, 2005 CDRL
Software Configuration Management
1 ITS America Palm Springs, CA June 6, 2007 SunGuide SM Software – Florida's ITS Software ITS America Palm Springs, CA June 6, 2007 Trey Tillander, P.E.
Current Job Components Information Technology Department Network Systems Administration Telecommunications Database Design and Administration.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting for SunGuide Release 4.0 August 18, 2008 August 18,
SunGuide SM Software Development Project Status Meeting (via teleconference) October 4, 2005 CDRL
Module 13: Maintaining Software by Using Windows Server Update Services.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting January 11, 2005.
Module 7: Fundamentals of Administering Windows Server 2008.
January 11, 2007Map Alternatives Workshop 1 SunGuide SM Map Alternatives Workshop.
May 16, 2007Change Management Board Meeting1 Local: Toll-Free: Ext
Module 9 Planning a Disaster Recovery Solution. Module Overview Planning for Disaster Mitigation Planning Exchange Server Backup Planning Exchange Server.
16 1 Installation  After development and testing, system must be put into operation  Important planning considerations Costs of operating both systems.
SunGuide® Software Development Project Release 4.3 Express Lanes Enhancements Design Review December 15, 2009 December 15, 20091R4.3 Design Review.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting August 27, 2007.
Statewide Transportation Management Center Software Library System (SunGuide SM ) TIM & SunGuide SM Coordination Meeting October 21, 2004 Orlando, Florida.
Computer Emergency Notification System (CENS)
Statewide Transportation Management Center Software Library System Software Requirements Review (SRR) and Status Meeting January 8, 2004.
SunGuide SM Software: Development Status Robert W. Heller, Ph.D. July 14, 2004.
Software Quality Assurance
SunGuide SM Software Development Project Status Meeting December 7, 2004.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.
Presentation to the Information Services Board March 6, 2008 Bill Kehoe, Chief Information Officer Bill Kehoe, Chief Information Officer.
SunGuide SM Software Development Project Status Meeting July 13, 2004.
SunGuide SM Software Development Project Status Meeting May 10, 2005 CDRL
SunGuide SM Software Development Project Status Meeting November 9, 2004.
SunGuide SM Software Development Project Administrator Training CDRL
SunGuide TM 4.0 Functionality Data Fusion: How Data is Managed June 24, 2008.
Quick Recap Monitoring and Controlling. Lesson 11: Monitoring and Controlling Project Work Topic 11A: Identify the Monitor and Control Project Work Process.
SunGuide TM Software Development Project Release 4.0 Kick-off Meeting October 15, 2007.
Connecting with Computer Science2 Objectives Learn how software engineering is used to create applications Learn some of the different software engineering.
SunGuide SM Software Development Project Status Meeting April 29, 2004.
SunGuide SM Software Development Project Status Meeting October 13, 2004.
Module 9 Planning and Implementing Monitoring and Maintenance.
Rational Unified Process Fundamentals Module 4: Core Workflows II - Concepts Rational Unified Process Fundamentals Module 4: Core Workflows II - Concepts.
Software Configuration Management SEII-Lecture 21
SunGuide SM Software Development Project End of the Year ITS Working Group Meeting December 7, 2005.
State of Georgia Release Management Training
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.
SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting November 27, 2007.
April 29, 2004 Project Status Meeting Liang Y. Hsia, P.E. ITS Engineer Administrator Florida Department of Transportation.
Waste Management Inspection Tracking System (WMITS)
ITS Device Standards & Procurement Project PURPOSE  Develop a series of Standards & Strategies designed to guide and provide consistency across the development.
ITIL® Service Asset & Configuration Management Foundations Service Transition Thatcher Deane 02/17/2010.
Planning Server Deployments Chapter 1. Server Deployment When planning a server deployment for a large enterprise network, the operating system edition.
SunGuide SM Software Development Project Software Design Review May 12, 2004.
Introduction for the Implementation of Software Configuration Management I thought I knew it all !
Software Configuration Management
Agenda Time Item Lead 8:30 – 8:35 Introductions Liang Hsia 8:35 – 8:50
SunGuideSM Software: Development Status Steven W. Dellenback, Ph. D
Agenda Time Item Lead 10:00 – 10:05 Introductions Liang Hsia
Experience with an IT Asset Management System
Department of Licensing HP 3000 Replatforming Project Closeout Report
Agenda Time Item Lead 8:30 – 8:35 Introductions Liang Hsia 8:35 – 8:45
SunGuideSM Software Development Project Status Meeting and Demonstration April 5-6, 2005 CDRL
Presentation transcript:

SunGuide SM Software Development Project Status Meeting March 9, 2004

March 9, 2004SunGuide Status Meeting 2 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 3 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 4 Configuration Management Definition: The process of selecting items whose configuration and change status will be controlled (baseline items), defining the process by which those items will be controlled, and then implementing that process. Following slides: –Project view of CM –Statewide view of CM

March 9, 2004SunGuide Status Meeting 5 Project View of CM

March 9, 2004SunGuide Status Meeting 6 SunGuide SM Software CM Requirement Scope of Services Requires –Use of Rational© ClearCase© for Configuration Management (CM) –Initial delivery of CM baseline corresponding to software before modifications –Delivery of CM repositories with each release

March 9, 2004SunGuide Status Meeting 7 CM Repositories Active Repositories –ClearCase repository utilized for baselines –Microsoft© Visual Source Safe© (VSS) for daily development –Department repository per SwRI Software Engineering Process (SEI CMM-Level 3) –Project web-site for delivered documents Backed up daily through Division IT services

March 9, 2004SunGuide Status Meeting 8 Daily CM Process Visual Source Safe is tightly integrated with Microsoft Visual Studio Developers responsible for check-in and check-out cycles: –Encourage daily check-in / check-out –Facilitates coordinated builds –Multiple projects under VSS are active MS Windows share backed up by Division IT group

March 9, 2004SunGuide Status Meeting 9 Department Process Repository All artifact deliveries to FDOT placed in department CM repository: –Maintained by administrative support staff –Part of SEI CMM approved process –Backed up by Division IT group

March 9, 2004SunGuide Status Meeting 10 SunGuide.datasys.swri.edu Project Web Site Contains copies of all deliverables Maintained by project staff Updated as deliveries made via Source backed up by division IT group

March 9, 2004SunGuide Status Meeting 11 ClearCase Repository Initial Baseline (delivered) consists of source code and documents from –Chart II Incident Management –TxDOT Traffic Operations Division Deferred baselined source code: –TransGuide Three More baselines anticipated –Release 1 –Release 2a –Release 2b Resides on Microsoft Windows share Backed up by Division IT group

March 9, 2004SunGuide Status Meeting 12 Baseline Release Preparation Prior to release of baseline perform –Functional Configuration Audit Formal test Report is written –Physical Configuration Audit Delivery media prepared Delivery media all “parts” to build baseline Report is written Copy to Department Repository

March 9, 2004SunGuide Status Meeting 13 Statewide View of CM

March 9, 2004SunGuide Status Meeting 14 CM Common Terms Baseline Item: A product of an effort which is to be maintained under configuration management. Typical baseline items include plans, ITS Architectures, Standards, specifications, and software source code. Engineering Change Requests (ECRs): A formal request for a change to requirements. Configuration Management Board (CMB): A group of people responsible for evaluating and approving or disapproving proposed changes to baseline items, and for ensuring implementation of approved changes. Configuration Manager: Person selected by the CMB to manage the configuration management activities; including the oversight of the CMB.

March 9, 2004SunGuide Status Meeting 15 Statewide Perspective Centralized Baseline Issue submission CMB composition and purpose Configuration Management Process

March 9, 2004SunGuide Status Meeting 16 CM Centralized Baseline Master SunGuide SM products are stored in a central location: –Documents –Source code –Installation scripts For each active development project: –Code copied to a project repository –Development occurs against the local repository –After acceptance testing, moved back to statewide location

March 9, 2004SunGuide Status Meeting 17 CM Issue Submission ECR is submitted Reviewed by CMB If approved: –ECP (Engineering Change Proposal) that contains cost and schedule –If ECP is approved: ECO (Engineering Change Order) issued

March 9, 2004SunGuide Status Meeting 18 CM CMB Purpose –Select Configuration Manager –Evaluate proposed changes (ECRs) –Approve/Disapprove ECRs –Interact with Other Organizations

March 9, 2004SunGuide Status Meeting 19 CMB Composition

March 9, 2004SunGuide Status Meeting 20 CM Process - Summary Identify Issue Review Locally and Resolve (if possible) Develop and Submit ECR to Statewide System Review ECR with CMB If ECR approved, software developer generates a ECP that contains cost and schedule FDOT reviews and approves ECP and provides a ECO to the software developer Software developer implements ECO Release product Install product

March 9, 2004SunGuide Status Meeting 21 CM Questions / Comments

March 9, 2004SunGuide Status Meeting 22 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 23 Discussion Topics Status of current ITS construction projects Planned ITS deployments Deployment specific questions: –Server operating system: Microsoft Server 2000 Microsoft Server 2003 –Workstation operating system: Microsoft Server XP

March 9, 2004SunGuide Status Meeting 24 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 25 Software License Issues SwRI / FDOT License –License executed before the contract started. –TxDOT informed SwRI on January 22, 2004 that TransGuide software was on “hold”. TxDOT / FDOT MOU –FDOT provided TxDOT with comments and legal opinion on March 2, 2004 FDOT / TransGuide License –FDOT provided TxDOT with customized License Agreement on February 19, 2004 SwRI / FDOT Sublicense for District 2 FDOT / WsDOT Term of Use FDOT / MDX Joint Program Agreement (JPA)

March 9, 2004SunGuide Status Meeting 26 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 27 History of Computer Sizing Estimates SwRI asked during Kick-off meeting to provide sizing estimates (Action Item #9). SwRI has performed initial sizing analysis and provided a sizing report to FDOT on February 5, Provides a technique to “estimate” computer needs. Contents are preliminary and conservative: document will be updated as software testing continues.

March 9, 2004SunGuide Status Meeting 28 Computer Sizing Estimates: Conceptual Deployment

March 9, 2004SunGuide Status Meeting 29 Computer Configurations Workstations: –Microsoft Windows XP, Internet Explorer 6.01 or greater –SVG Viewer 3.0 or greater –2.4 to 3.0 GHz processor –512 MB RAM –20 GB disk SunGuide SM Database Server (these requirements will vary widely based on how much data the SunGuide SM implementation chooses to log and the backup policies implemented by the SunGuide SM implementation computer staff): –Microsoft Server 2000 –Oracle 9i –> 2.4 GHz processor –> 2 GB RAM (Oracle likes RAM – the more the better) –70 GB of disk using RAID architecture (this disk space will vary based on the amount of historical information logged to the database) SunGuide SM Application Servers (SunGuide SM processes): –Microsoft Server 2000 –Executive Handler –> 2.4 GHz processor –1 GB RAM –36 GB of disk

March 9, 2004SunGuide Status Meeting 30 Sizing Table Used to estimate computing resources Process can be “mixed and matched” Impacts: –Number of users –Number of devices –Multi processors District specific evaluations will be made during initial stages of implementation

March 9, 2004SunGuide Status Meeting 31 Sample Exercise Assumed: –100 DMSs –200 Detectors –10 simultaneous uses Summary: –Need a database server –3 dual processor application servers (provides growth capacity) Note: –Size estimates will be re- evaluated after integration (and probably go down) Application Servers Only

March 9, 2004SunGuide Status Meeting 32 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 33 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 34 Project Web Site

March 9, 2004SunGuide Status Meeting 35 Release-Oriented Development Approach Release 1 Release 2a Release 2b not in scope

March 9, 2004SunGuide Status Meeting 36 Scope of SunGuide SM Effort Release 1: –Core software framework: Database Process viewer Status logger User interface Map –DMS subsystem, drivers for: NTCIP Florida MIB Mark IV version 2.5 –CCTV subsystem, drivers for: NTCIP camera support American Dynamics 2050 switch –Traffic Detection, driver for: Bitrans 238I-95 –Incident management subsystem Release 2a: –Core software framework upgrade –Center-to-Center –FDOT Central office configuration –Ramp metering –CCTV subsystem, drivers: SunGuide SM protocol –RWIS –Archive data –HAR –Web server –Emergency evacuation Release 2b: –Inventory and maintenance

March 9, 2004SunGuide Status Meeting 37 Status of Release 1 Activities Project Management: –PM / Meetings / Reviews –Process documents –Interface Control Documents (ICDs) Core software framework: –Database –Process viewer –Status logger –User interface –Map DMS subsystem, drivers for: –NTCIP Florida MIB –Mark IV version 2.5 CCTV subsystem, drivers for: –NTCIP camera support –American Dynamics 2050 switch Traffic Detection, driver for: –Bitrans 238I-95 Incident management subsystem

March 9, 2004SunGuide Status Meeting 38 Status of Release 2a Activities CCTV subsystem, drivers for: –SunGuide SM protocol camera support – stopped per FDOT request Ramp Metering: –Developing requirements –Plan to perform a site visit to WashDOT operations facility

March 9, 2004SunGuide Status Meeting 39 Screens: Executive Handler

March 9, 2004SunGuide Status Meeting 40 Screens: Executive Handler - continued

March 9, 2004SunGuide Status Meeting 41 Screens: Maps

March 9, 2004SunGuide Status Meeting 42 Screens: Maps - continued

March 9, 2004SunGuide Status Meeting 43 Screens: XML Client Tester

March 9, 2004SunGuide Status Meeting 44 Deliverable Status Pending: –Final version of Software Requirements Specification Future documents: –Software Design Document: HTML based See next page –Software Acceptance Test Plan –Software Integration Plan All available on project web site.

March 9, 2004SunGuide Status Meeting 45 SDD Snapshots

March 9, 2004SunGuide Status Meeting 46 Cost Status Release 1: –Budget amount: $3,208,052 –As of 2/11/04, ~$997,000 has been expended Release 2a: –Budget amount: $2,074,276 –As of 1/2/04, $34,631 has been expended Release 2b: –Budget amount: $245,311 –As of 1/2/04, $0 has been expended

March 9, 2004SunGuide Status Meeting 47 Schedule Status Current schedule is posted to project web site Overall project status: –Ahead in many places –SunGuide SM is operational in the lab: Support processes (executive, logging) GUI Map Data Bus DMS: –Mark IV –NTCIP CCTV: –Master process –NTCIP driver –“Pelco” driver (for testing purposes only) TSS: –Master process –Simulator process (up to 1000’s of detectors) Incident management

March 9, 2004SunGuide Status Meeting 48 Schedule Status - continued Current areas of concern: –Documents: None –Lack of final device drivers –Baseline software (TransGuide component)

March 9, 2004SunGuide Status Meeting 49 Schedule Status - continued

March 9, 2004SunGuide Status Meeting 50 DMS Functional Thread: GUI - Data Bus – DMS Subsystem - Device

March 9, 2004SunGuide Status Meeting 51 CCTV Functional Thread: XML Simulator - Data Bus – CCTV Subsystem - Device

March 9, 2004SunGuide Status Meeting 52 TSS Functional Thread: Device Simulator - TSS Subsystem - Data Bus – XML Simulator

March 9, 2004SunGuide Status Meeting 53 Schedule Status - continued Project status meeting after ITS America (April 26 – 28 in San Antonio) on April 29th –Agenda: Project status See SunGuide SM operating in a multi-server, multi- workstation environment with REAL EQUIPMENT Meet the development team DMS Milestone Demo: –District 4: Schedule still being evaluated

March 9, 2004SunGuide Status Meeting 54 SwRI Development Labs

March 9, 2004SunGuide Status Meeting 55 Action Items

March 9, 2004SunGuide Status Meeting 56 Action Items - continued

March 9, 2004SunGuide Status Meeting 57 Action Items - continued

March 9, 2004SunGuide Status Meeting 58 General Comments / Feedback on Project Status

March 9, 2004SunGuide Status Meeting 59 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 60 Draft Contract Amendment List: Sent by Central ITS Office on 2/9/04

March 9, 2004SunGuide Status Meeting 61 Device Drivers Device functionality isolated by “ICDs” (Interface Control Documents) Subsystems are “generic” and not specific to device functionality Device drivers easy to add once base subsystem is complete and operational

March 9, 2004SunGuide Status Meeting 62 Device Drivers In BAFO That Were Approved For Implementation DMS: –NTCIP –Mark IV (v 2.5) CCTV (Cameras): –NTCIP –SunGuide SM (Stopped development) Video Switch: –American Dynamics 2050 (Stopped development) Traffic Detectors: –BiTrans 238I-95 Ramp Metering: –WsDOT (firmware) RWIS: –NTCIP HAR

March 9, 2004SunGuide Status Meeting 63 SwRI Asked To Evaluate Adding New Devices to Development Effort IP-Video Device Driver EIS RTMS TSS Device Driver Wavetronix RTMS TSS Device Driver 3M (Canonga) Microloop TSS Device Driver Trailblazer Device Driver and GUI Support Intelligent Devices Incorporated (IDI) Support Barco / Argus: –Video Switch Device Driver –Wall Configuration Software DTS Video Switch

March 9, 2004SunGuide Status Meeting 64 All Development Efforts Include… The device driver compliant with the appropriate SunGuide SM device driver Interface Control Document (ICD). Development efforts will include: –Design –Peer Review –Implementation –Testing –Integration

March 9, 2004SunGuide Status Meeting 65 IP Video Scope: –SwRI will develop an IP-Video video switch device driver that will instruct “decoders” to listen to “encoders”. –The device driver will issue SNMP commands to the following decoders: CorTec Teleste VBrick iMpath Assumptions: –SwRI will not be performing inter-operability testing between different brands of encoders and decoders.

March 9, 2004SunGuide Status Meeting 66 RTMS TSS Device Driver(s) Scope: –A device driver for a Electronic Integrated System (EIS) RTMS device will be developed. –A device driver for a Wavetronix SmartSensor device will be developed. –A device driver for a 3M Canoga, model C400/C800/C990E device will be developed. Assumptions: –The serial port of the EIS RTMS device shall be connected to a terminal (port) server so that a TCP/IP interface can be used to retrieve data. –TCP/IP interface of the Wavetronix RTMS device shall be used to retrieve data. –The serial port of the 3M device shall be connected to a terminal (port) server so that a TCP/IP interface can be used to retrieve data. Notes: –Concurrent development of these drivers will results in a cost savings.

March 9, 2004SunGuide Status Meeting 67 Trailblazer Device Driver and GUI Support Scope: –Develop a device driver (to be included in the DMS subsystem) to support Trailblazer devices, SunGuide SM protocol will be used to communicate to the devices. –Develop a GUI that will provide the operator with the capability to request display modifications on a Trailblazer. –Development staff will travel to Miami for two on-site test periods (up to four days each).

March 9, 2004SunGuide Status Meeting 68 Intelligent Devices Incorporated (IDI) Support Scope: –Work with FDOT staff to identify candidate devices –Observe NTCIP testing with FDOT staff –Once devices accepted by FDOT, perform integration testing with SunGuide SM software framework Assumptions: –FDOT will procure all devices –All NTCIP compliance testing to be performed by FDOT (TERL) –No software development effort by SwRI

March 9, 2004SunGuide Status Meeting 69 DTS Video Switch Scope: –SwRI will develop video switch driver that will instruct the DTS video system to connect video inputs to video outputs. –The device driver shall be compliant with the SunGuide SM CCTV Video Switch Interface Control Document (ICD) interface Assumptions: –SwRI assumes that camera control and video switching both need to be supported by this driver. –SwRI needs protocol documents from DTS before we can initiate and design or development. –SwRI needs access a FDOT provided DTSS unit for testing and development. SwRI has included funds to travel to FDOT specified locations. Note: –The estimated cost SwRI has provided is an conservative costs; SwRI has been given limited access to technical information about how to communicate to the DTS switch from an external source. –Non-disclosure has been put in place – waiting for technical detail.

March 9, 2004SunGuide Status Meeting 70 Barco / Argus Scope: –SwRI is proposing two applications: Video switch device driver: –SwRI will develop a video switch driver that will instruct the video wall to change displays in the “Barco Windows”. –The device driver shall be compliant with the SunGuide SM CCTV Video Switch Interface Control Document (ICD) interface Video wall configuration software: –SwRI will extend the SunGuide SM GUI to allow the Barco video wall to be reconfigured using SunGuide SM software. –The software will allow virtual windows to be defined and input streams associated with each of these windows. –Note: this software would replace the Barco provided software for configuring the video wall. Assumptions: –SwRI requires access to a Barco unit for fact finding. –SwRI requires a Barco software development environment at SwRI. –SwRI requires access to DTS development staff for questions / answers.

March 9, 2004SunGuide Status Meeting 71 Device Driver Costs SwRI was asked to evaluate the current device driver costs Current device drivers were included in the BAFO approved by FDOT New drivers can be added: –SwRI based cost estimates on some assumptions (see previous slides) –SwRI has developed cost estimates –Schedule impact may vary based on timing and number of new drivers added

March 9, 2004SunGuide Status Meeting 72 Device Driver Costs - continued IP-Video Device Driver: $134,322 EIS RTMS TSS Device Driver: $103,684 Wavetronix RTMS TSS Device Driver: $103,684 3M (Canonga) Microloop TSS Device Driver: $129,074 Trailblazer Device Driver and GUI Support: $56,381 Intelligent Devices Incorporated (IDI) Support: $89,910 Barco / Argus: Video Switch Device Driver: $184,788 Wall Configuration Software: $178,471 DTS Video Switch: $202,003

March 9, 2004SunGuide Status Meeting 73 Device Driver Costs - continued Cost reductions: –CCTV American Dynamics Driver:~$69,000 –CCTV SunGuide SM Driver:~$52,000 Net cost impact to project: –Additions:$1,182,317 –Reductions: $123,000 –NET:$1,061,317

March 9, 2004SunGuide Status Meeting 74 Tentative Schedule

March 9, 2004SunGuide Status Meeting 75 Agenda TimeItemLead 2:00 – 2:05IntroductionsHsia and all participants 2:05 – 2:25Configuration Management:  CM during development  CM during / after deployment Dellenback / Heller 2:25 – 2:50Districts’ TMC and Software Deployment Schedule Updates (Sorted by scheduled or planned deployment date) Faquir - District 4 Bitting - District 7 Martinez - District 6 Campo - MDX Birosak - District 1 Vega - District 2 Rivera - District 5 McCrary - District 3 Birenbaum - Turnpike Enterprise 2:50 – 2:55MOU between FDOT and TxDOT, Software License Updates: TransGuide, and TxSoftware Sublicense Modification for D2 Hsia / Dellenback 2:55 – 3:15Computer Size Estimates for TMC Dellenback 3:15 – 3:30Break 3:30 – 4:00 Project Status Report:  Development status  GUI / Map Screen Snapshots  Cost and schedule status  Action item follow-up Dellenback 4:00 – 4:15New device drivers:  Driver details  Cost and schedule Dellenback 4:15 – 4:30Open Discussion / Action Item Summary Dellenback

March 9, 2004SunGuide Status Meeting 76 Future Meetings Outreach Meeting: March 10 th (1:45 to 2:00) Next Status Meeting: –April 29 th (in conjunction with ITS America): Status Report Significant software demonstration Need to schedule: –Software Design Review Need to confirm: –May Status Meeting –June Status Meeting

March 9, 2004SunGuide Status Meeting 77 Questions / Comments

March 9, 2004SunGuide Status Meeting 78 Action Item Recap NumberPersonAction