LIGO-G020514-00-P 1 Case Study of PMCS Implementation/Tools - Advanced LIGO An Example Of Implementation In Progress Prepared by Thomas Frey, CCC, PMP.

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Work Breakdown Structures
Chpter#5 -part#1 Project Scope and Human Resource Planning
Advanced Project Management - CPH
Degree and Graduation Seminar Scope Management
Project Cost Management Estimation Budget Cost Control
Trust & Influence. About the PMI® Practice Standards and other ways to earn PDU’s Christopher Talmont, PMP, PMI-SP April 20, 2011.
Chapter 3 Managing the Information Systems Project
LIGO-G M Advanced LIGO Cost, Schedule and Management Gary H Sanders NSF Review of Advanced LIGO Caltech, June 11, 2003.
BUS 4017 Project Mgt. Wk. 9 Prof.essor Fred Pentney 1 Agenda. HR and Bus. program Estimates, costs, budgets, forecasts, variances and control Resource.
Chapter 3: The Project Management Process Groups
Chapter 5: Project Scope Management
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Project Management and MS Project. The project management triangle: Time Resources Scope.
Lesson 10: IT Project and Program Management. Lesson 10 Objectives  Identify resources for technical data  Identify project management fundamentals.
Project Management “Introduction to Project Management: Tools, Techniques, and Practices” BA 320 Operations Management.
Project Management Body of Knowledge PMBOK
Software Project Management By Assistant Prof. Samana Zehra
Chapter 10 Project Monitoring and Control
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
Project Management Lecture 5+6 MS Saba Sahar.
Office of Project Management Metrics Report Presentation
Project Management Methodology Project monitoring and control.
© 2006 ITT Educational Services Inc. System Analysis for Software Engineers: Unit 5 Slide 1 Chapter 3 Managing the Information Systems Project.
SA Capstone Requirements and Design Week 10 SYST Winter 2013 Instructors: Jerry Kotuba & Joe Varrasso.
© 2005 by Prentice Hall 3-1 Chapter 3 Managing the Information Systems Project Modern Systems Analysis and Design Fourth Edition.
IT Project Management Cheng Li, Ph.D. August 2003.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
After Lesson 6 next is Lesson 13 to fit topic on Software Development SOFTWARE PROJECT MANAGEMENT.
MEASUREMENT PLAN SOFTWARE MEASUREMENT & ANALYSIS Team Assignment 15
Project Management : Techniques and Tools (60-499) Fall 2014 / Winter 2015.
Recap from last week Understand organizations, including the four frames, organizational structures. Explain why stakeholder management and top management.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
Welcome to Session 4 – Project Management Process Overview (continued) Instructor:Phyllis Sweeney Instructor: Phyllis Sweeney Project Management Certificate.
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
1.  Describe an overall framework for project integration management ◦ RelatIion to the other project management knowledge areas and the project life.
Managing Engineering Design - Infrastructure. Presentation Overview 1.Tools and Techniques 2.Design and Documentation 3.Estimating and Scheduling.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Software Project Management (SPM)
Ahmad Al-Ghoul. Learning Objectives Explain what a project is,, list various attributes of projects. Describe project management, discuss Who uses Project.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Management & Development of Complex Projects Course Code MS Project Management Earned Value Concepts Lecture # 19.
© 2008 Prentice Hall2-1 Introduction to Project Management Chapter 2 The Project Management Life Cycle Information Systems Project Management: A Process.
The Project Management Life Cycle. What is the Project Management Life Cycle? A project life cycle simply includes the necessary steps, from beginning.
1 These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 5/e and are provided with permission by.
Project Cost Management
© 2014 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved. This material is protected by Copyright and written permission should be obtained.
Project Management Methodology
Systems Development Life Cycle
Chapter 3 Managing the Information Systems Project
Project Scope Management 1. 2 Learning Objectives Understand the elements that make good project scope management important. Explain the scope planning.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
LIGO-G M Advanced LIGO Cost, Schedule and Management Gary H Sanders NSF Review of Advanced LIGO Caltech, June 11, 2003.
Project Setup and Execution For PMPlan Enterprise Presented by AlNik Solutions Copyright ©
SCOPE DEFINITION,VERIFICATION AND CONTROL Ashima Wadhwa.
~ pertemuan 4 ~ Oleh: Ir. Abdul Hayat, MTI 20-Mar-2009 [Abdul Hayat, [4]Project Integration Management, Semester Genap 2008/2009] 1 PROJECT INTEGRATION.
SOFTWARE PROJECT MANAGEMENT
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
Introduction to Project Management Project Monitoring and Control Lecture a This material (Comp19_Unit9a) was developed by Johns Hopkins University, funded.
Project Cost Management
Managing the Information Systems Project
Project Integration Management
Project Theory and Application
Project Management Chapter 11.
CAD DESK PRIMAVERA PRESENTATION.
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

LIGO-G P 1 Case Study of PMCS Implementation/Tools - Advanced LIGO An Example Of Implementation In Progress Prepared by Thomas Frey, CCC, PMP

LIGO-G P 2 Nov 2002Adv. LIGO Presentation Outline l Introduction l Value to Stakeholders l PMCS Implementation General Practice »Model System »Tools »LIGO Lab Criteria l Why CPM »A Case Study of Scheduling Tools –MS Project vs. Primavera Project Planner l Real World Example of Tool Use l Conclusion l References

LIGO-G P 3 Nov 2002Adv. LIGO Introduction l My Background. l Focus of the Presentation. l Not the Focus of the Presentation. l Topic Definition

LIGO-G P 4 Nov 2002Adv. LIGO Speaker Background l Thomas L. Frey, CCC, PMP l Experience : 12 Yrs. Work Experience in Project Control Systems. l Education : BS Degree Project Mgmt. Purdue University at West Lafayette, IN. l Present : Working at LIGO Lab out of the Business Office. l Comments & Additional Info.: ;

LIGO-G P 5 Nov 2002Adv. LIGO Focus of Presentation l Focus of this presentation is: »to explain the elements of the implementation process. »to explain the why it is best to choose CPM tools. »to outline the tools being used by LIGO. »to present the project structure being used by LIGO. »to present a real world example of how the tools benefited LIGO and a collaborator. »To discuss some future / proposed tool selections by LIGO.

LIGO-G P 6 Nov 2002Adv. LIGO FOCUS of Presentation is NOT… l The focus of this presentation is not: »to discuss the pros and cons or history of CSC Criteria. »to discuss the origin of EV Analysis. »to suggest that EV Analysis / Reporting is a panacea. »to dictate specific means or methods. »to imply that EV Analysis has to be implemented on all projects. »To suggest that the tools LIGO uses, are the only options.

LIGO-G P 7 Nov 2002Adv. LIGO Topic Definition l What is implementation? »CARRY OUT, ACCOMPLISH; especially : to give practical effect to and ensure of actual fulfillment by concrete measures »to provide instruments or means of expression for.

LIGO-G P 8 Nov 2002Adv. LIGO Topic Definition Con’t l What is an Project Management Control System? A M.I.S. that... »Determines project status. »Makes a comparison of project status to planning. »Provides information regarding corrective action. »Manages the change process. »May or may not implement Earned Value Analysis.

LIGO-G P 9 Nov 2002Adv. LIGO Topic Definition Con’t l What is Implementation of a Project Management Control System? A M.I.S. that... »To give practical effect… –PMCS that provides useful information. »Actual fulfillment by concrete measures…. –PMCS that provides quantifiable benefit to project. »Provide instruments or means of expression –PMCS that has meaningful output.

LIGO-G P 10 Nov 2002Adv. LIGO l Still a form of Estimating! »This is a combination of cost estimation and time estimation. Both come with inaccuracies in the form of allowable variances. Allowable has to be defined by the management team and accepted. Variances will always be directly proportional to the quality and quantity of data available. Topic Definition Con’t

LIGO-G P 11 Nov 2002Adv. LIGO l Define Stakeholders l Define the Value of PMCS. l Objections / Misconceptions Value to Stakeholders

LIGO-G P 12 Nov 2002Adv. LIGO l Who are the stakeholders? »Anyone associated with the project or a benefactor of the project. »“Product of the Project” l Nee to have stakeholders at the highest levels in the organization that recognize the value of project controls. Value to Stakeholders

LIGO-G P 13 Nov 2002Adv. LIGO l What kind of stakeholders? »Anyone that works in a project environment. »Product independent. »Any process (Industry) can be accommodated. Value to Stakeholders

LIGO-G P 14 Nov 2002Adv. LIGO l Value? »Better decision making regarding corrective actions. »Better Resource Analysis. »Better Cost / Schedule Risk Analysis. »Can use for justifying schedule and cost impact due to changes. Value to Stakeholders

LIGO-G P 15 Nov 2002Adv. LIGO l Objections / Misconceptions? »Too complicated. »Makes us look bad. (Shoot the Messenger) »Micro Management. »We don’t need to control costs and resources. (?) (Ostrich Management Style) »Can’t afford the expertise. Value to Stakeholders

LIGO-G P 16 Nov 2002Adv. LIGO l Value? (Bottom Line) »Better Project Control, Better Budget Use! »Better Project Value. Value to Stakeholders

LIGO-G P 17 Nov 2002Adv. LIGO PMCS Implementation General Practice l Implementation Process l Basic System Elements l Criteria of LIGO Lab »Program Model

LIGO-G P 18 Nov 2002Adv. LIGO General Practices – Implementation l SDLC (System Development Life Cycle) »Recon (Needs Analysis) –The process of learning your customers unique business processes and determining how you can apply your knowledge of software tools to improve the management of those processes. »Development –The process designing and creating the solution for the customer. »Training and Procedures –The process of teaching your customers champions and staff how to use the developed solution and documenting how to use it. »Pilot Project (i1) –This is the preliminary phase of implementation and is a test of how well the developed solution will meet the expectations of the customers and users. »Rollout / Handover (i2) –This is the final phase of implementation and is a process of incorporating the changes to meet the expectations of the customers and users; and handing the system over to the customer. »Support & Maintenance –The process of tech support, continued education, continued improvement, and follow through.

LIGO-G P 19 Nov 2002Adv. LIGO General Practices – System Elements l Elements of the PMCS »WBS, tailored for effective management control. »OBS, define the organizational elements in which work will be planned and controlled. »Provide for integration with accounting systems. »Schedule methodology used should describe sequence of scope and identify sequencing that meets the requirements of the program. »Establish budgets for the scope and identify significant cost elements as needed for management control. »Establish and maintain a budget loaded baseline schedule, against which program performance can be measured.

LIGO-G P 20 Nov 2002Adv. LIGO General Practices – System Elements l Elements of the PMCS »At least on a monthly basis, reconcile any deviations that are not performance related. »At least on a monthly basis, generate Comparison of the amount of planned budget and the amount of budget earned for work accomplished. This comparison provides the schedule variance »At least on a monthly basis, generate comparison of the amount of the budget earned and the actual direct costs for the same work. This comparison provides the cost variance »At least on a monthly basis, generate the significant differences between both planned and actual schedule performance and planned and actual cost performance, and provide the reasons for the variances.

LIGO-G P 21 Nov 2002Adv. LIGO General Practices – System Elements l Elements of the PMCS (EVMS) Estimates / Budget Generation Accounting / Procurement Planning, Scheduling, and Performance Measurement Doc. Control / QAQC / Change Requests ActualsChanges

LIGO-G P 22 Nov 2002Adv. LIGO General Practices – System Elements l Tools and software work on a database concept. To make data integrate, common field values must exist to join data. For example: »Activity IDs »Code Fields »WBS Values »Cost Accounts »Cost Categories »Resource IDs Activity ID Code Field WBS Value Account Cost Category Resource ID Activity ID Code Field WBS Value Account Cost Category Resource ID Queries. Filters, Reports Cost DB Schedule DB

LIGO-G P 23 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 24 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 25 Nov 2002Adv. LIGO

LIGO-G P 26 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 27 Nov 2002Adv. LIGO

LIGO-G P 28 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 29 Nov 2002Adv. LIGO Note: the value “2011” is common.

LIGO-G P 30 Nov 2002Adv. LIGO Note: the value “40111” is common.

LIGO-G P 31 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool »Cost Estimating Plan »Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 32 Nov 2002Adv. LIGO This value is used as a unique resource ID and populates the resource dictionary for planning. This value is used as a FTE value for making head counts and evaluating resource usage.

LIGO-G P 33 Nov 2002Adv. LIGO Resource Database l Resource ID is as follows: »EN = Engineer »B2 = NSF Code for Technical Staff. We are changing this to be a specialty code and will move the NSF code to a data field. »CT = Organization Code for Caltech. »02 = Unique Counter l Resource database also performs the following solutions for LIGO: »OBS – Organizational Breakdown »Live data link that drives the LIGO Roster and LSC roster on the Web. »We are creating an / Reporting Utility on the web that will allow managers to generate lists and resource reports. Resource reports can be run by department, supervisor, discipline, and / or specialty.

LIGO-G P 34 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 35 Nov 2002Adv. LIGO Requirements l What Classification of Estimate: »Conceptual –Based on some for of technical capability roughly defined. Rough sketch of system. –Variance +50% to +100% »ROM (Rough Order of Magnitude) –Similar to a conceptual estimate and usually based upon some historical factors from a similar system. –Variance +25% to +75% »Unit Cost Estimate –Based upon historical cost and known units. –Variance -5% to +25% »Bottoms Up (Detailed Estimate) –This is the process of developing cost by counting units and quantifying labor. –Variance -5% to +20%

LIGO-G P 36 Nov 2002Adv. LIGO

LIGO-G P 37 Nov 2002Adv. LIGO

LIGO-G P 38 Nov 2002Adv. LIGO

LIGO-G P 39 Nov 2002Adv. LIGO

LIGO-G P 40 Nov 2002Adv. LIGO

LIGO-G P 41 Nov 2002Adv. LIGO

LIGO-G P 42 Nov 2002Adv. LIGO

LIGO-G P 43 Nov 2002Adv. LIGO

LIGO-G P 44 Nov 2002Adv. LIGO Activity Sheet Header

LIGO-G P 45 Nov 2002Adv. LIGO Activity Sheet Takeoff Area

LIGO-G P 46 Nov 2002Adv. LIGO Cost Extension Area

LIGO-G P 47 Nov 2002Adv. LIGO Risk and Cost Totals

LIGO-G P 48 Nov 2002Adv. LIGO Labor Summary (FTEs)

LIGO-G P 49 Nov 2002Adv. LIGO

LIGO-G P 50 Nov 2002Adv. LIGO

LIGO-G P 51 Nov 2002Adv. LIGO

LIGO-G P 52 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 53 Nov 2002Adv. LIGO Schedule Development l Data collection done using what ever method it takes. l Tools used by scientists and engineers: »MS Project (98, 2000, 2002, and ver. 4 for MAC) –NOTE: MS Project 98 and ver. 4 for MAC are not backward compatible with 2000 or »Excel Spreadsheets »Text Files »Sketches on Paper »I do them.

LIGO-G P 54 Nov 2002Adv. LIGO Level 1 Level 2 Level 3

LIGO-G P 55 Nov 2002Adv. LIGO Level 4

LIGO-G P 56 Nov 2002Adv. LIGO Level 5

LIGO-G P 57 Nov 2002Adv. LIGO Criteria for LIGO Lab l Use of a Traditional WBS (Work Break Down Structure) l Follow a defined project life cycle and structure. l Cost Codes that are linked to a WBS l Resource planning by Discipline. – »Resource Pool Listing by Discipline l Cost and Schedule Integration. – »LIGO II Cost Book Tool –Cost Estimating Plan –Cost Estimating Tool User Procedure l Reporting capability at any level within the WBS »Schedule Development »Example reports for pilot projects –LASTI –40-Meter l Earned Value Analysis - AKA Variance Analysis. – »Program Model Output from P3 (Primavera Project Planner »Program Model Output from P3 (Primavera Project Planner)

LIGO-G P 58 Nov 2002Adv. LIGO Planning for Performance Measurement l At what level do you cost load the schedule? »WBS Level is where we collect actual cost. »Cost Book Activity Sheet is where we load the estimate. »Schedule Activity level is where we measure progress that determines the earned value. l Performance Evaluation is executed at the rollup level for the WBS. »ACWP »BCWS »BCWP »Schedule Variance »Cost Variance WBS Grouping { { { WBS Level Cost Book Activity Sheet Level Schedule Task Level

LIGO-G P 59 Nov 2002Adv. LIGO Planning for Performance Measurement

LIGO-G P 60 Nov 2002Adv. LIGO Planning for Performance Measurement

LIGO-G P 61 Nov 2002Adv. LIGO Planning for Performance Measurement

LIGO-G P 62 Nov 2002Adv. LIGO

LIGO-G P 63 Nov 2002Adv. LIGO

LIGO-G P 64 Nov 2002Adv. LIGO Progress Data Collection l Primavera Project Planner comes with a built in free ware program called Post Office. »Using a built in feature within the application you can create a mail attachment that contains the activities to be updated. l Another option is using Excel spreadsheets. These can be easily imported.

LIGO-G P 65 Nov 2002Adv. LIGO Criteria for LIGO Lab – The Tools l For Planning and Scheduling we are using Primavera Project Planner. This provides: »Traditional WBS (Work Break Down Structure) »Use of defined project life cycle and structure. »Uses Cost Codes »Resource Dictionary by Discipline. – –Resource Pool Listing by Discipline »Reporting capability at any level within the WBS »Earned Value Analysis - AKA Variance Analysis. – l For Cost data development and integration we are using MS Access. This provides: »Cost and Schedule Integration. – –LIGO II Cost Book Tool on the Web. »Resource Data control and maintenance

LIGO-G P 66 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) l What elements make CPM work. l Sample Plan l Why MS Project is not true CPM. l Primavera Project Planner – True CPM tool.

LIGO-G P 67 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) l Elements of CPM »Uses activity logic. Most common application is precedence format. »Calculation algorithm uses forward and backward pass. »Tool provides critical path. »Provides information regarding float, free float, early dates and late dates. –Allows negative float as a means for quantifying delays. »Actual Cost can exceed budget. (Negative Cost and Schedule Variances)

LIGO-G P 68 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) From J. Lewis See References

LIGO-G P 69 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) From J. Lewis See References

LIGO-G P 70 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) From J. Lewis See References

LIGO-G P 71 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) l Sample Project »Yard Project. »We will show this sample project in MS Project and P3. »We will show how progress is represented in each case. »We will evaluate the application of constraints. –Haul Away Trash has a finish no later than date of June 19, »Using days as time unit for this exercise. From J. Lewis See References

LIGO-G P 72 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) Primavera Project Planner: Logic Diagram

LIGO-G P 73 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) Primavera Project Planner: Schedule Views NOTE: Progress shows negative float indicating the amount of delay and forecasting an early finish later than the planned finish.

LIGO-G P 74 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) Microsoft Project 2002 : Logic Diagram

LIGO-G P 75 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) MS Project 2002: Schedule Views NOTE: Progress does not show negative float indicating the amount of delay and the forecast finish has not changed to reflect the delay.

LIGO-G P 76 Nov 2002Adv. LIGO Why CPM (Critical Path Methodology) l CPM, With Out A Doubt. »CPM tool provides clear quantifiable data regarding delay. »Forecasts a new finish date based upon known progress. »Basis for making corrective action to recover delay.

LIGO-G P 77 Nov 2002Adv. LIGO Real World Example l Working with a LIGO Lab collaborator preparing a proposal we were asked to help. l We will discuss how LIGO Lab used the tools available to provide the following: »Detailed Cost Estimate »Detailed Schedule »Cost Loaded Schedule »Cost Profiles with Escalation

LIGO-G P 78 Nov 2002Adv. LIGO Real World Example l Using the Cost Book Tool, we coded the cost sheets that represented the collaborator’s scope. l Using MS Access and the data, we applied the collaborator's cost rules and labor rates. l We also provided cost data by institution for the collaborator.

LIGO-G P 79 Nov 2002Adv. LIGO Real World Example

LIGO-G P 80 Nov 2002Adv. LIGO Real World Example l Using the schedule, we coded the tasks that represent the collaborator’s scope. l Using the cost book Access database, we cost loaded the schedule and generated cost profiles.

LIGO-G P 81 Nov 2002Adv. LIGO Real World Example l Using the cost loaded schedule, we exported the cost profile data to a spread sheet in base year dollars. l Using MS Excel, we generated a cost profile by GB Fiscal Years and applied an escalation rate.

LIGO-G P 82 Nov 2002Adv. LIGO Conclusion l Keep Sharp, Beat Your Budget! »PMCS, PMIS, or EV MIS(s) offer greater PM value to stakeholders (customers and clients). »EV Analysis, when implemented with integrity, offers the best method for identifying project areas of concern. »EV Reports and Graphs can quickly communicate to stakeholders the status of the project. »EV is a method with a proven track record. It is not an experiment. »When executed on at least a monthly basis, it will provide the information needed for management to make good decisions.

LIGO-G P 83 Nov 2002Adv. LIGO References l Lewis, James P.. “PROJECT PLANNING, SCHEDULING AND CONTROL”. Irvin Professional Publishing, ISBN l Lewis, James P.. “FUNDAMENTALS OF PROJECT MANAGEMENT”. AMACOM Publishing, ISBN l Project Management Institute, “Project Body of Knowledge”, AKA. PMBOK. PMI, Four Campus Blvd., Newtown Square, PA , USA., ISBN: l Earned Value Management Web Site:

LIGO-G P 84 Nov 2002Adv. LIGO l THE END Case Study of PMCS Implementation/Tools - Advanced LIGO