TS-CV contracts case study LHC pipelines and HVAC for Experimental Areas R. Principe, J. Inigo-Golfin.

Slides:



Advertisements
Similar presentations
A Joint Code of Practice Objectives and Summary Presentation
Advertisements

MASBO February Information to purchase Services Information to purchase Construction.
HEAT TRACING SPECIALIST
TITAN Group …….Managing Site Build up for the telecom sector TICS Telecom Projects Consultancy Pvt. Ltd.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
1.040/1.401 Project Management Spring 2007 Lecture 7 Dr. SangHyun Lee Department of Civil and Environmental Engineering Massachusetts Institute.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Contractor Safety Management
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Accounting Specialist Basic Functions : To provide essential data by computing and distributing collections to their respective allocations. Knowing the.
Bilan du contrat Renco Piping contract F467 TS workshop Archamps Mai 25 th 2005 R. Principe TSCV.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
Oxfordshire Clinical Commissioning Group Contracting to support integration for mental health and older people Oxfordshire CCG’s approach to contracting.
LHC HARDWARE COMMISSIONING SAFETY TRAINING DAY S. Claudet (AT-ACR-OP) With great help from G. Lindell (Safety commission) CRYOGENICS.
Tim Watson ST-CE CE Experience with External Consultants for the LHC Project.
Contractors & contracts
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
LINKED Administrative & Finance overview18/03/2010 LINKED Leveraging Innovation for a Network of Knowledge on Education LIFE LONG LEARNING PROGRAMME LLP.
Construction Work Packaging
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
TENDERING PROCEDURE IT- 3927/EN
Ch. 5: Project Planning Good Quote: Plans are only good intentions unless they immediately degenerate into hard work Lame excuses for not planning: Takes.
Purchasing Supplies at CERN
Note Excerpts from Object-Oriented Software Engineering WCB/McGraw-Hill, 2008 Stephen R. Schach
Chapter 2 Introduction to Construction Procedures
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
PITFALLS IN DEALING WITH TENDERS &CONTRACTS Shiv Kumar Director/IRICEN.
Engineering Department ENEN What is changing in EN 1. Streamlining and boosting remote handling and manipulation activities 2. Bringing small works closer.
PLANNING ENGINEERING AND PROJECT MANAGEMENT By Lec. Junaid Arshad 1 Lecture#03 DEPARTMENT OF ENGINEERING MANAGEMENT.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
About Us  We are a group of Mechanical Engineers specialized in Construction & Engineering Services.  Our mission is to provide highest quality of construction.
Managing Construction Chapter 16. Contractor Projects are overseen by a contractor who owns and operates a construction company. Projects are overseen.
Thursday 6 th May 2004 C. Martel – Cooling Ventilation - CERN TS/CV TS/CV/BE COOLING VENTILATION TECHNICAL DESIGN OFFICE TS Workshop Archamps 2004.
Associated detection/extinction systems D. Swoboda.
Marc Tavlet - GLIMOS1 Paperwork needed to come and work at CERN 1. Access Rights – Registration 2. Tests with Beams 3. Safety Procedures to work at Point-2.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Unit 18: CADD in Construction Lesson Objective Be able to explain the use of Building Information Modelling in buildings.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
T. KurtykaLinac4 meeting 12 March 2009 Guidelines from the sLHC Specification Committee 1). sLHC Specification Committee 2). Schedule of tenders for Linac4.
EN/CV/DC IT-3673 Presentation done by Elena Perez Rodriguez For further information contact For the purchase of cooling fluids.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
University of Calgary Continuing Education Construction Contract Law and Documents Week 12 Changes Delays Claims Contract Documentation.
INVITATION TO TENDER PROCEDURE INVITATION TO TENDER PROCEDURE IT–4082/EN Design, Supply, Installation and Commissioning of the ventilation of the BAF3.
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
Purchasing supplies at CERN Procurement Rules Someone FP-PI.
PROCUREMENT RULES FOR EXPERIMENTS AT CERN Dante Gregorio CERN Procurement Service.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
For more information, please contact 24/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
IT-4135/EN Supply of Air Handling Units for Industrial HVAC Projects at CERN Technical Specification Paul Pepinster / EN-CV.
Construction Work Packaging
The Design Team Carl James.
CERN Construction Planning and Scheduling (LHC installation)
Change Management V.N.Bhaskar Rao Engineering & Construction Director Amec Foster Wheeler India Operations.
Particular Conditions of Contract & Appendix to Tender
Project General Data Beneficiary: Rosenergoatom
Mauro Morandin & Antoine Daël
Low temperature chiller Market Survey
Particular Conditions of Contract & Appendix to Tender
Well Repair Installation of Well Liners
6th. Semester Schedule: 1st. Week
CDM 2015: PCI, CPP, Client Duties, IOSH Tyne & Wear Branch
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Powering and Safety day Underground access during powering tests
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

TS-CV contracts case study LHC pipelines and HVAC for Experimental Areas R. Principe, J. Inigo-Golfin

Table of contents Case studies Introduction Major issues coming from the experience during the  Design phase  Execution phase  Commissioning Conclusion

Case Study 1 LHC pipeline Contract F467

Contract characteristics F467 LHC pipeline 220 km pipelines Demineralised water distribution circuit, compressed air, drainage, helium quench, recovery and ring lines Stainless steel AISI 304L From DN65 to DN250 From PN10 to PN25 and From 50°C to -196°C Very short time available for MS and IT No basic engineering available in 2000 Installation depending from the basic engineering production Estimation 24 MCHF

Tendering 15 consortia selected after a large market survey Dossier for the invitation to tender ready in three months DQE based on basic engineering available in 2000 Re-measurement contract Commercial and juridical aspects probably required a better check: i.e. schedule variation vs. cost impact Contract to the cheapest offer : lowest bid below CERN estimates, delta 6 MCHF Contract award on May 22 nd, 2002

Design phase Drawings CDD procedure and Euclide Execution methods: from 3D to 2D and isometrics Quality of the first drawings Timing in the delivery Approval process Engineering Specification of the components and CERN specific requirement: i.e. rad-hard material or chemicals (i.e. MSDS) Procedures for installation (i.e. method of statement), testing, cleaning, etc.

Approval process Basic engineering Survey Installation dwgs Approval Installation Purchasing 8 weeks 16 weeks

Execution phase First months: CERN environment  Safety, i.e. PPSPS, VIC, etc..  Access conditions, permits, space availability  Method of statement Technical aspects, i.e. orbital welding DN200, taping construction CERN work supervision Timing due to engineering Schedule Non continuous basis, not even in a sector Access to the working areas Recently high production rate vs. logistics vs. engineering  stand-by hours, claims

Commercial approach Very aggressive commercial policy No clear interface (CERN PE vs. Site manager, construction manager, project manager) No stable management team at CERN No clear issues (PE vs. Contractor) Continuous by-pass  Work stops or late delivery  Schedule and work site coordination concerns  Claims – amendment – claim A real continuous fight, high pressure

Performance of F467 Around 130 km of pipelines 5-6 out of 8 sectors installed 300 tons of supports: ~ 25’000 ~ 15’000 welds (orbital and TIG) Welding: 0% repairs in the last sectors No helium leaks detected during He leak tests, pressure tests always successful

Case Study 2 HVAC for Experimental Areas at points 1 & 5, F405.

Contract characteristics Basic engineering and integration done at CERN. Detail engineering and selection of material by Contractor. Supply and installation of HVAC of underground areas at points 1 & 5, comprising: Heating and Ventilating of surface buildings, Air conditioning of underground spaces, More than 80 air handling units, Steel structures in SUXs 1 & 5, Some 1000 m of large (above 1000 mm) ducts, Two supervision systems and more than 10 PLCs, Tens of electrical cubicles, Tests and Commissioning.

Tendering Technical specification sent out in summer Lowest bid below CERN estimates (15 MCHF). Bid of poor quality (incomplete technical information). Discussions held at the time to ensure that scope defined in specification would be respected. Contractor had no large experienced in HVAC field (except marine environment). Contract F405 placed in 2001.

Design phase Difficulties by the Contractor in setting a stable project team. Several engineers left project/firm during the detailed engineering stage of project. Production of drawings not uneventful, linked to proposal of material of inferior quality to bid’s. Detailed engineering missing or late. Contractor subcontracted also detailed studies to inexperienced companies. Electrical diagram software (unavailable in Italy) implemented very late by Contractor.

Execution phase Inexperienced project engineer and site managers. Volatile Contractor’s teams. Several changes over the extent of installation at point 1. All of site work subcontracted until late stages. Poor quality of S & I. Contractor unable to supervise his subcontractor’s work. Site management very poor. Uncontrolled delivery and storage lead to damage or loss of material. Only a few people could identify pieces! Clear misunderstanding of applicable laws. Contractor’s staff in illegal situation in CH. Safety neglected (in design and execution phase). Contractor put in place a larger and more experience team when situation became impossible.

Performance of F405 Ductwork of poor quality, accepted for schedule reasons in some cases but, unacceptable in experimental cavern. Allotted “prime” time wasted largely due to Contractor’s fault but…CERN’s cranes not available when required and CERN supervision not incisive enough. Safety concerns and legal situation of staff lead to stop of works and eventually replacement of subcontractor for PX15 (and PM54). Contractor accepted responsibility and accepted to work in given “secondary” time slots. New ductwork subcontractor’s material of much better quality. Difficulties in commissioning of SCX1. Commissioning of USA/UX units to start in coming weeks.

Conclusions Both contracts very different. F467 enough competent technically but commercial policy very aggressive. CERN not adapted to cope with this approach. F405 clearly not experienced in necessary scope. This (hinted from early stages) would have required a CERN supervision much closer to the contractor. CERN legal service involvement in the running of contracts, in a similar fashion to Purchase office, clearly needed. The risks (announced and) assumed at the placing of the contracts should have been translated into additional measures. Daily work on site must be carefully addressed. The smallest site occurrence or indiscretion becomes a potential claim in hours. Communication with contractors via the responsible groups for good reasons.