Infrastructure Development

Slides:



Advertisements
Similar presentations
Transform empower uplift 6/9/11 TCTA Strategic Plan for 2011/12 11 Date: 7 June 2011 Presentation to Parliamentary Portfolio Committee on Water Affairs.
Advertisements

PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
DEPARTMENT OF WATER AFFAIRS
MASS SPORT AND RECREATION PARTICIPATION PROGRAMME GRANT Select Committee on Appropriations National Council of Provinces 23 AUGUST 2011 Presented by: Intergovernmental.
STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February Briefing by Department of Water Affairs.
TECHNICAL OVERSIGHT MONITORING AND SUPPORT VISITS ON REGIONAL PROJECTS: 2014/15 Prepared by: R. Gillmer Chief Engineer : Technical Support 21 August 2014.
1 Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 18 August 2010.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Northern Cape.
Interim Executive Director June  Financial Management Practices Audit Results Fiscal Year Audit Results Fiscal Year Internal.
Province of the EASTERN CAPE Department of Roads & Transport “Quality Service Delivery through Transportation Excellence” Report on Conditional Grants.
REPORTING, MONITORING AND PERFORMANCE EVALUATION PROVISIONS ON NON-FINANCIALS – 2013/14 1 MIG Quarterly Workshop 3 – 4 September 2013.
SOUTH AFRICAN DIAMOND AND PRECIOUS METALS REGULATOR (SADPMR)
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Western Cape.
1 Presentation to the Portfolio Committee: Water & Environment Presentation by Mr Trevor Balzer Programme Manager: Special Projects 16 – 17 March 2010.
1 PROGRESS MADE AND RECOMMENDATIONS OF THE PORTFOLIO COMMITTEE ON THE RURAL HOUSING IINFRASTRUCTURE PROGRAMME 09 NOVEMBER 2011.
1 Public hearing on conditional grants and capital expenditure: 3rd quarter Presentation to Select Committee on Finance Northern Cape’s Department of Agriculture.
1 Date: 21/22 June 2011 Presentation to Parliamentary Portfolio Committee on Water Affairs.
PRESENTATION TITLE Presented by: Name Surname Directorate Date BRIEFING OF THE SELECTION PANEL FOR WATER SECTOR ENTITIES Name Surname: MR ANIL SINGH Designation:
MASIBAMBANE CO-ORDINATING COMMITTEE MEETING PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 22 nd JUNE 2012 MASIBAMBANE CO-ORDINATING.
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
Programme 4: Housing Development Finance Purpose: Fund national housing and human settlement development programmes in terms of the Housing Act (1997),
VOTE 38: ANNUAL REPORT FOR THE 2013/14 FINANCIAL YEAR FOR THE PERIOD 1 APRIL 2013 TO 31 MARCH 2014.
ILembe District Municipality Municipal Water Infrastructure Grant Projects and Project Readiness 13 TH SEPTEMBER 2013 iLembe District Municipality Municipal.
DWA - ORWRDP - Technical Workshop Mogalakwena Regional Raw Water Scheme (MRRWS) 21 Feb 2013 Ossie Rossouw Victor Couto Bertus Bierman.
Themba Wakashe Director - General Department of Arts and Culture 2009 / 10 DIVISION OF REVENUE BILL PRESENTATION TO SELECT COMMITTEE ON FINANCE NCOP 3.
1 CONCISE UPDATE ON ACID MINE DRAINAGE IN THE WITWATERSRAND April 2012 UPDATE BY Mr. MARIUS KEET.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
Briefing on the comprehensive investment programme for water infrastructure development 27 – 28 March 2013 Portfolio Committee: Water & Environmental Affairs.
Integrated National Electrification Programme (INEP): Overall Performance (End of January 2012) Dr Wolsey Barnard.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
1 Local Government Budgets and Expenditure Review 2001/02 – 2007/08.
STANDING COMMITTEE ON APPROPRIATIONS Water Trading Entity 1 Briefing on the 4 th Quarter Expenditure Report for the Financial Year 2011/12.
1 PRESENTATION expenditure for the 2008/09 financial year.
1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
Presentation to the Portfolio Committee: Water and Environmental Affairs Presentation by Department of Water Affairs 30 – 31 March 2011 Budget allocation.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
Parliamentary submission on the eradication of the Bucket Toilet System 22 & 23 February 2007 Cllr. Derrick Ndlovu.
1 Presentation of the Financial Performance of the Department to the Standing Committee on Appropriations 23 March 2011 Presented by Cathy Motsisi Chief.
PRESENTATION TITLE Presented by: Name Surname Directorate Date WATER RESEARCH COMMISSION ANNUAL PERFORMANCE PLAN PRESENTATION 2015/16 Presented by: Dhesigen.
James Ndlovu CEO 6 April  Strategic Overview  Annual Performance Framework ( )  Scorecard  Budget  Discussion & Clarifications.
Richland Creek Water Supply Program Status Update Paulding County, Georgia Board of Commissioners Work Session January 26, 2016.
CLANWILLIAM WATER PROJECT
Presentation to the Portfolio Committee on Energy
Briefing on Current Expenditure and their Performance Trends
Legislation Constitution of the Republic of South Africa, 1996 (Act No. 108 of 1996) Housing Act No.107 of 1997 The Housing Consumers Protection Measures.
DEPARTMENT OF WATER AFFAIRS & FORESTRY
EASTERN CAPE DEPARTMENT OF HOUSING
BRIEFING THE PORTFOLIO COMMITTEE ON WATER AND SANITATION
North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 June 2008.
PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT ANNUAL PERFORMANCE REPORT OF THE COMPENSATION FUND FOR THE FINANCIAL YEAR
Presentation by Department: Water Affairs 22 March 2011
FIRST QUARTER ANALYSIS REPORT
SELECT COMMITTEE ON PUBLIC SERVICE: REPORT ON QUALITY SANITATION TO HOUSEHOLDS PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP)
Provincial Budgets and Expenditure as at 31 December /08 Financial Year PUBLIC WORKS, ROADS AND TRANSPORT SCOF (NCOP) Hearings Presented by:
Major Vaal River Consultation Meeting Raw Water Use Charges for 2017/18 Financial Year 12 September 2016.
Major Vaal River Consultation Meeting Raw Water Use Charges for 2017/18 Financial Year 12 September 2016.
Responses to issues raised: report as submitted on 4 April 2018
Select Committee on Finance (SCoF) National Treasury 10 October 2007
STANDING COMMITTEE ON APPROPRIATIONS
Major Vaal River Consultation Meeting Raw Water Use Charges for 2019/20 Financial Year 24 October 2018.
Water & Environmental Affairs
PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL.
NCOP PRESENTATION 05 FEBRUARY 2008
Report on Conditional Grants
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
PROGRAMME 2 CONT - NATIONAL WATER RESOURCES INFRASTRUCTURE BRANCH.
Select Committee on Land and Environmental Affairs
Richland Creek Water Supply Program Program Update
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Presentation transcript:

Infrastructure Development Presentation to SCOA 28 August 2012 Cape Town aDDG: NWRI

Projects within Capital Projects 1 Olifants River Water Resources Development Project – Phase 2A (De Hoop Dam) 2 Olifants River Water Resources Development Project – Phase 2 Bulk Distribution System 3 Mdloti River Development. Hazelmere Dam Raising 4 Olifants – Doorn River Water Resources Project – Raising of Clanwilliam Dam 5 Mokolo and Crocodile River (West) Water Augmentation Project Phase 1 (MCWAP-1) 6 Komati Water System Augmentation Project (Off-budget) 7 Mooi Mgeni Transfer Scheme – Phase 2 (Off-budget) 8 Vaal River Eastern Sub-System Augmentation Project (VRESAP) (Off budget) 9 Nandoni Pipeline 30 April 2012

Impoundment delayed to August 2012 Olifants River Water Resources Development Project – Phase 2A (De Hoop Dam) Project description: Construction of the 80 m high De Hoop Dam and related infrastructure - to supply water to domestic and industrial users in the middle Olifants river catchment area. Status: Approved as Government Water Work. Province: Limpopo Jobs impact: Direct project construction jobs (peak): 1150 : De Hoop Dam 528 : Road re-alignment 250 : Housing infrastructure Jobs due to new industrialisation and growth: ±5000 Projected cost to completion: Phase 2A (Dam): R3.1bn Project Scope: Construction of the De Hoop Dam. Re-alignment of 20 km portion of P169-1. Housing infrastructure Project schedule: Construction started: June 2007 Construction Completion: March 2013 Progress/Challenges Impoundment delayed to August 2012 Green Scorpion’s allegations of non-compliance Sediment from upstream open cast mining polluting and decreasing dam storage capacity Community distress if primary water is not supplied Some workers’ contract completion processes to commence in February 2012 The section 19 pollution remediation directive has been issued. 30 April 2012

Olifants River Water Resources Development Project – Phase 2 Bulk Distribution System Project description: The construction of the bulk distribution system which will transfer water from the De Hoop and Flag Boshielo Dams to domestic and industrial users in the middle Olifants River catchment area. Status: Approved as Government Waterwork. Province: Limpopo Jobs impact: Direct project construction jobs: 2 000 jobs for the BDS Jobs due to new irrigation and industrialisation and growth: 5 000 Projected cost to completion: Phase 2B-H (Distribution): R12,975bn Project Scope: Construction of the Bulk Distribution system that will convey raw water from the De Hoop and Flag Boshielo Dams to domestic and industrial users. Project schedule: Construction of 2C commenced, completion by March 2014. Phased completion following implementation of water reconciliation study and funding availability Progress / Challenges The mining houses did not want to sign the off take agreements (citing that the water was too expensive); TCTA could not obtain funding from the capital market because of this, TCTA already had committed funds on the projects because of the detail design already 90% complete National Treasury had to fund the revised directive to implement Phase 2C (pipeline from the De Hoop dam to Steelpoort) Phase 2C important as the De Hoop dam is almost completed. Facilitation process amongst stakeholders to agree on the BDS configuration. Still a possibility of off budget funding when facilitation process is completed. 30 April 2012

Mdloti River Development Hazelmere Dam Raising Project description: This project is to augment the water supply to the KZN North Coast by increasing the yield of the dam for medium term supply. Status: Approved as Government Water Work. Province: KwaZulu Natal, ILembe District. Jobs impact: Direct project jobs estimated at 300. Projected cost to completion: The revised estimate (April 2012) is R 360 million (incl. VAT, contingencies, escalation) Project Scope: The installation of crest gates. Civil work for dam safety and stability. Acquisition of additional land in dam basin. Project schedule: Design of civil works started - October 2011 Civil contract award - July 2013 Gate contract award - November 2012 Project completion - September 2014 Progress & Challenges: Valuation of properties and tender for crest gates is on hold pending outcome of viability of project at increased cost. Due diligence analysis of preferred design option for raising, incl. geological investigation, has been completed. Report on preferred design option needs to be submitted to CD: IWR Planning. Connected issues: Construction of infrastructure by Umgeni Water. Decisions required: Economic viability of project needs to be confirmed by Chief Director: IWR Planning. 30 April 2012 5

Olifants-Doorn River Water Resources Project – Raising of Clanwilliam Dam Project description: Raising of existing full supply level by 13 metres to provide additional water to supply full existing allocation, establish resource poor farmers and address dam safety aspects. Status: Approved as Government Water Work. Province: Western Cape, Cederberg Municipality. Jobs impact: Direct project construction jobs: 650 Jobs due to new irrigation and growth: 2 500 Projected cost to completion: R1 830 million Project Scope: Raising of the dam wall and spillway. Construction of a multi-level outlet works. Re-alignment of Route N7 and Provincial roads. Compensation for affected properties. Project schedule: Design of N7 re-alignment started - July 2011 Design of dam wall started - March 2011 Construction of N7 re-alignment - Nov 2012 Construction of dam wall raising - April 2013 Completion of project - May 2017 Progress & Challenges: Design of the N7 re-alignment is in progress. Investigation of Provincial roads has started. Detailed design of dam wall raising and outlet works is in progress. Determination of dam boundary line is in progress. Connected issues: Upgrading of existing conveyance system and allocation of water to users. Decisions required: Record of Implementation Decisions. Confirmation of funding from National Treasury for construction of project. 30 April 2012

Approved as Government Waterwork. Province: Limpopo Jobs impact: Mokolo and Crocodile River (West) Water Augmentation Project Phase 1 (MCWAP-1) Project description: Construction of a pumping station and 46 km of pipeline, with a diameter of 1m to deliver bulk raw water from the Mokolo Dam to Medupi and Matimba Power stations, Exxaro and for the expected growth in the Lephalale Municipality. The existing pipeline will be refurbished following commissioning of the new works. Status: Approved as Government Waterwork. Province: Limpopo Jobs impact: Direct project construction jobs: 1 600 Projected cost to completion: R2,138 billion Project Scope: Construction of a pumping station. Construction of a 46 km, 1m diameter pipeline. Refurbishment of existing pipeline TCTA to obtain off budget funding (75% commercial) Project schedule: First delivery of water at the end of 2013 Forecast project close out: August 2015 Progress& Challenges: Project advanced to detail design and construction phase. Water supply agreements concluded between Eskom, Exxaro and DWA. DWA-TCTA Implementation Agreement concluded December 2011. Fitch rating AA+ achieved, funding secured Contract awarded in June 2011. Site handed over to contractor on 14 Sept 2011 and physical activities started during November 2011 Environmental baseline studies ongoing No significant challenges at this stage Agreement on subsequent phases to be obtained 30 April 2012

Komati Water System Augmentation Project - KWSAP (Off-budget) Project description: Construction of a pumping station and two pipelines to provide water to Duvha and Matla Power Stations. Status: Approved as Government Waterwork. Province: Mpumalanga Jobs impact: Direct project construction jobs: 800 Projected cost to completion: R1,736 billion Project Scope: Construction of a pumping station at Rietfontein Weir. Construction of a 58,4 km , 1,1m diameter pipeline to Duvha Power station Construction of a 12,9 km , 600mm diameter pipeline to Matla Power station. TCTA to obtain off budget funding (100%) Project schedule: Construction commenced in January 2011 Forecast project close out in October 2013 Progress & Challenges: Water supply long term funding for the project had been secured. Delays in pipe manufacturing solved 17,5 km pipes laid, expect water delivery end January 2013 No significant challenges reported 30 April 2012

Mooi Mgeni Transfer Scheme – Phase 2 (Off-budget) Project description: Construction of the 42 m high Spring Grove Dam, the associated transfer system and the refurbishment of existing MMTS-1 pumping station and transfer system. Status: Approved as Government Waterwork. Province: KwaZulu Natal Jobs impact: Direct project construction jobs: 850 Jobs due to growth: 800 Projected cost to completion: R1,67billion Project Scope: Refurbishment of existing MMTS-1 pipeline system. MMTS-2A:Construction of the 42 m high Spring Grove Dam. MMTS-2B: Construction of a transfer system. Acquisition of off budget funding by the TCTA (100%). Project schedule: Construction Commenced during Feb 2011 Forecast Project Closure Jan 2015 Progress/Issues: The sod turning event was held on the 16th May 2011. Municipal off-take Agreements between Umgeni Water (UW) and eThekwini, uMgungundlovu and Msunduzi Municipalities were signed Progress & Challenges: Stage 2 River Diversion works are completed. Excavation completed EMPR restriction of 30 heavy duty trucks per day hindering supply of construction materials was lifted Impoundment delayed to January 2013 Environmental authorisation of pipeline route contested and upheld resulting in reassessment of environmental impact assessment, started during February 2012 Pre-qualification of contractors commenced 30 April 2012

Vaal River Eastern Sub-System Augmentation Project (VRESAP) (Off-budget) Project description: Construction of a raw water conveyance system of an abstraction system, storage reservoir, a high lift pump station, a 121 km pipeline, surge tank and diversion structure. Status: Approved as a Government Waterwork. Province: Mpumalanga Jobs impact: Direct project construction jobs: 1 600 Projected cost to completion: R2,698 billion Project Scope: Construction of an abstraction works. Construction of a storage reservoir. Construction of a high lift pump station. Construction of a surge tank and a diversion structure. TCTA to obtain off budget funding (100% commercial) Project schedule: Forecast project close out: July 2012 Expenditure: Project 99% complete (permanent abstraction works not complete) Earning revenue from June 2009 Progress & Challenges: Works commissioned, snags being addressed Abstraction works to be completed by May 2012. Challenges experience with the coffer dam demolition. Potential legal action by contractor (C-MC) due to premature contract termination for poor performance. DWA O&M staff challenges 30 April 2012

Luvuvhu River Government Water Scheme: Nandoni Steel Pipelines Project schedule: The Lukalo-Lambani, NN20B and NR6 bulk lines to the north of Nandoni Dam and Xikundu Weir respectively will be completed by end of October 2012. The construction of the Vuwani bulk pipeline has been split into three contracts. The contractors established the site in June 2012 and the work will be completed by May 2013. The Valdezia bulk pipeline, is being constructed by DWA Construction: North and will be completed by April 2013. Progress/Challenges Updated water demand figures are significantly higher than the previously estimated, requiring larger pipe diameters . Approval for roll-over of R200 incl vat has not yet been received from National Treasury. Risks or challenges Possible delay with supply of pipe materials Cash flow of emerging contractors Labour/Industrial action/strikes or go slows Compliance with stringent environmental conditions Local Water distribution Infrastructure to be implemented by Local Authorities Decisions required: None Project description: Construction of the five new pipelines to complete Nandoni bulk distribution system and to replace problematic GRP pipelines, including the Valdezia Pipeline Reasons for under-spending in the 2011/2012 year : The budget of R203 million was allocated before the design had commenced. The appointment of the professional service provider who is responsible for the design and construction supervision was finalized during February 2012, which impacted on the completion of the designs and caused a significant delay. The pipe diameters had to be changed because of the higher water demands due to the later design options (previously 2010 and now 2025). The project was accelerated by awarding the construction of the pipeline to three different contractors. Province: Limpopo Jobs impact: About 300 jobs Projected cost to completion: R750,1 million Project Scope: This project includes new steel pipelines for Xikundu Distribution Scheme and Nandoni Distribution Scheme

Dam Safety Rehabilitation Programme (DSRP) The Klein Maricopoort Dam near Zeerust and Rust de Winter Dam near Hammanskraal was successfully completed in the fourth quarter to bring the total number of dams completed to four for the financial year. Various rehabilitation design projects are carried out using internal staff and progressing well. Numerous projects are promoting labour intensive methods and maximising job creation. Slow procurement processes are hampering progress where DWA Construction is involved. Shortage of staff doing rehabilitation design internally is delaying progress. Non appointment of consulting engineering PSPs are delaying implementation of various projects. Non appointment of mechanical term contracts are delaying implementation of various work. Unavailability of as-built drawings increases the possibility of variations on contracts

TCTA Tender and implementation process Directive by Minister Project Charter including SED prescripts in terms of legistation Preparation and approval of tender documentation by TCTA Board Public invitation to select preferred bidders (pre-qualification of contractors) Submission of tender documentation to preferred bidders Adjudication of bids Awarding of contract Credit rating obtained from financial markets Secure loan funding Supervision of construction contracts Submission of contractor invoices Monthly certification of work performed to specification 22/04/2017

TCTA Tender and Implementation Process cont. Project ready for operation Project ready for commission Handover to DWA for operation and maintenance Commencement of defects liability period Commencement of debt repayment period Customer invoiced for water consumption as per capitol unit charge Users, TCTA and DWA meet annually to set tariffs in accordance with agreement 22/04/2017

END