Mariusz Sapinski BI/BL Acknowledgements: 1 Planning of quench tests - QTSWG 13.01.18 Latest news concerning planning of quench tests Quench Test Strategy.

Slides:



Advertisements
Similar presentations
DS Quench TEST 2  MOTIVATION and METHOD: 1. Achieve 500kW on beam 1 – TCP7 collimators.(so far 500kW with beam 2 and 235kW over 1s with beam 1 were reached.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC 14 & 15 April :22: Ramp to 6.5 TeV lost due to MUFO, resulting in quench 10:30: Access during cryo recovery 16:00: Pre-cycle 17:05: RB.A78 short.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
Tuesday 10 th April - morning Access for:  point 3 Jerome Landaro TCSG one jaw didn't move  point 5 Qps expert on RPMBB.UJ56.RCBXH1.R5  point 6 TCDQ.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Mariusz Sapinski BI/BL Acknowledgements: 1 Planning of quench tests - LMC158 Draft planning of beam induced quench tests at the end of 2013 run LHC Machine.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
● Main goals for week 33: – Luminosity production; – First 150 ns bunch train attempts; – Roman Pots: check movement at 3.5 TeV, with 1b; – Off momentum.
Monday h34: beam (1020b) lost after 10 Hz RF trim. Fill h56: XPOC to be reset by expert. 08h18: Masked QPS_STATE SIS interlocks for RB.A12.
● 08h00: Adjust mode for end-of-fill study. Scraping test for determining transverse beam profile (beam 2, vertical). As expected, beam dumped with BLM.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
LHC status Wednesday 15 th July 2015 Coordination: Wolfgang Hofle, Mike Lamont.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Shortened program (2 days), as decided in LMC. MD program worked very well  all MD’s on plan with ~foreseen beam time. LHC in very good shape with excellent.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
Beam Induced Quench Session 2: quench test at LHC B. Dehning, C. Bracco.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Draft MD Planning Thu (3.11.) DayTimeMDMP Thu05:00 Ramp down, cycle 07: GeV: Injection stability and losses – check steering constraints, define.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
11:56 Stable beams  7-8 e29 cm-2s-1 peak at start Losses  beam – two dips plus emittance blow-up  Substantial drop in luminosity 16:15 Thunderstorm.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
:30 meetingEBH 1  No beam during the morning:  4:15 – 9: V distributor: Recovery after electrical interruption  access for TI services.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Workshop on Beam Induced Quenches, Sept. 15, 2014
Ion Commissioning: Thursday & Friday
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
MD2036: UFO dynamics studies and UFO fast detection
Saturday 21st April 00:33 Interlock during ramp on BLM HV
MD2490 Measurement of the TMCI threshold at flat-top
Fast losses at collimators during 16L2 dumps
MD2490: Measurement of the TMCI Threshold at Flat-Top
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Monday 6th August & night
LHC Injection and Dump Protection
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday March 4th 08h32: Access for beam dump system.
Friday 14th December - morning
MD#2 News & Plan Tue – Wed (19. – 20.6.)
LHC progress report Week
Wednesday 03/11 – The Plan Finish electron-cloud program:
Saturday 7th May Sat – Sun night
Friday 23rd March 08:00 Access
Summary Thursday h21: Stable beams fill #1303.
MD Planning Fri – Sat (1. – 2.7.)
Summary for LPC (March 7th, Ralph Assmann)
Fri :52 Stable beams fill #2536
Friday 15th February - morning
Another Immortal Fill….
Wednesday 6.10 Morning: Quench test at 450 GeV
Daniel, Gianluca and Belen (for the Collimator team)
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Mariusz Sapinski BI/BL Acknowledgements: 1 Planning of quench tests - QTSWG Latest news concerning planning of quench tests Quench Test Strategy WG, 2013/01/18

Acknowledgements: 2 Planning of quench tests - QTSWG Preparation planning dateaction Friday, January 18th QTSWG meeting, checking status of preparation Tuesday, January 22nd Deadline for MPP EDMS documents (sooner is better). Friday, January 25th MPP, presentations : Vera and Anton concerning beam screen temperatures Mariusz – quench test planning and … 6 hour MD time to set ADT and test the fast loss procedure at injection with collimators. (exact date depends on ion owen refill) Monday, January 28th Collimation WG: presentation about collimators settings for quench test (Belen) Wednesday, January 30th LMC: presentation about final tests schedule (Mariusz)

Acknowledgements: 3 Planning of quench tests - QTSWG Quench tests planning (I) ADT fast loss Collimation protons Collimation ions Steady state with bump Q6 injection High priority, most difficult High priority Can be done during other magnet recovery

Acknowledgements: 4 Planning of quench tests - QTSWG Quench tests planning (II) ADT fast loss Collimation protons Collimation ions Steady state with bump Q6 injection High priority, most difficult High priority Can be done during other magnet recovery End of lead in the oven Not easy bricolage in MPS

Acknowledgements: 5 beam induced quench tests - LMC158 Quench tests planning (III) TimeMDbeamcommentsaccumulated time 06:00Ramp down if needed Prepare BLM thresholds (easy), ADT settings (probably tricky), QPS acquisition 08:00 ADT fast loss QT, ramp 1 10 x 1e9 4 TeVQuench expected (12L6) 10:00 ramp down, quench recovery, precycle 2 15:00 ADT fast loss QT, ramp 2 10 x 1e9 4 TeV (contingency?) Quench expected (12L6)7 17:00 Ramp down, quench recovery, precycle Preparation of BLM thresholds (complex), ADT settings 9 22:00 Proton collimation QT, ramp 1 4 TeVassumed no quench14 00:00Ramp down, precycle 16 02:00 Proton collimation QT, ramp 2 4 TeVQuench expected (L7)18 04:00 Ramp down, quench recovery, precycle 20 09:00 Proton collimation QT, ramp 3 4 TeV (contingency?) Quench expected (IR7) (Maybe the other beam?) 25

Acknowledgements: 6 beam induced quench tests - LMC158 Quench tests planning (IV) TimeMDbeamcommentsaccumulated Time 11:00 Ramp down, quench recovery, precycle Prepare BLM thresholds (very complex and critical), ADT settings, 27 16:00 Ion collimation QT, ramp 1 5e11 (charges, ie. 3x24 4 ZTeV Quench expected (IR7). Additional ramp if enough time 32 18:00 ramp down, quench recovery, precycle 34 23:00 Orbital bump steady state QT, ramp 1 10 x 4 TeV Quench expected (12L6). Additional ramp if enough time :00 Ramp down, quench recovery, precycle Preparation of BLM thresholds (easy) and QPS fast acquisition 41 03:00Q6 injection QT Fat pilot at injection B2, Q6 magnet at higher currents (5 TeV +) Can start independently of quench recovery in 12L6. Quench expected (6L8) :00END 45 3 spare hours: possibility to make another ramp for ion collimation QT or Orbital bump steady state QT.

Acknowledgements: 7 Planning of quench tests - QTSWG ADT fast losses QT - idea blow-up and scraping bump 1. Inject and ramp 2. Blow-up vertically and scrape 3. Excite horizontally and quench Quench (*) Not in scale

Acknowledgements: 8 Planning of quench tests - QTSWG Open points concerning ADT fast losses QT Inject and ramp octupoles and chroma bump blow-up and scraping Horizontal kick and quench blow-up and scraping Dump during scraping? octupoles and chroma bump H/V coupling – horizontal blow-up how big bump? octupoles and chroma blow-up and scraping bump H/V coupling – horizontal blow-up how big bump?