This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. Current status of the Danube Limes project Coordination meeting, Budapest Judit Saád
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF Progress reports approved and paid - 4th progress report approved and forwarded for payment to the MA on 19 September th progress report submitted to JTS on12 August 2011 Status of Progress reports
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. WP1 - all outputs completed, but Interim reportings: reports and certified cost list WP2 - PP3 WP3 - all outputs completed Status of all outputs/1
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. WP4 4.1 Stakeholder consultations , , completed, scientific assessment is in progress (PP6) 4.2.Implementation best practice Best practice in access and site information on selected sites (PP6) Best practice of a Roman park (Lussonium) (PP7) Status of all outputs/2
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. WP Integration of remaining sites Draft of HU nomination documents – completed, translated and presented at stakeholder conference, discussed by experts Draft of SK nomination documents – completed, and presented at stakeholder conference, not yet translated and discussed by experts Draft of general guidelines (PP3) Status of all outputs/3
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. WP Nomination documents HU nomination document – will be completed by mid October - proof reading PP5 by mid November, editing, layout, printing – in November/December SK nomination document (PP2) Guidelines (PP3) Project closing scientific conference (PP6) Status of all outputs/4
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. Status of indicators/1 – output indicators Name of indicatorplannedreachedPR6 A1a) Transnational strategy developed 431 A1b) Transnational strategy implemented/adopted 202 B2) Number of entities of private sector and related services B4) Number of entities providing intermediarey services and training 15132
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. - Contributing to srengthened co-operation among businesses - Contributing to establishment or development of transnational clusters - Contributing to cooperation of key players of regional innovation systems - fostering entrepreneurship Status of indicators/2 – economic indicators
This project is implemented through the CENTRAL EUROPE Programme co-financed by the ERDF. - Contributing positively to the maintenance ofbiodiversity - Contributing to the reduction of land take for urban development Pilot actions Status of indicators/3 – environmental indicators