1 TEC pilot run status Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I - 15 R7.

Slides:



Advertisements
Similar presentations
Status of Sensor and Hybrid Production LHCb Zurich Week T. Bowcock.
Advertisements

Electrical and thermal testing at Glasgow and Liverpool.
TEC X5 Setup (1) 1 Front + 1 Back petal, fully equipped (28 modules F.P modules B.P. + AOH + DOHM) Petal assembly IPN-Lyon (F.P.), RWTH-Aachen I.
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
Marco Bregant Vertex05 - Nikko, November 2005 Dipartimento di Fisica Universit à di Trieste & Istituto Nazionale di Fisica Nucleare (INFN) - Trieste ALICE.
Status Brussels GANTRY Ê We have observed a significant influence due to temperature 4 we had a lot of problems with our cooling system (ventilation) Ë.
Module Production Brussels Ê Problems with vacuum chambers in plate solved 4 Almost all plates back in Brussels (repaired in Aachen) Ë Problem with rotation.
Status Update on Mechanical Prototype in Rome November 6,
1 US Testing Update-Anthony AffolderTracker Meeting, Feb 10, 2004 Faulty Channel Sources (TOB) Fault Sources (excluding cable breaks and CMN)  Hybrid-0.004%
Tracker Week – UCSB Gantry Status – April 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara Dean White.
Tracker Week – UCSB Gantry Status – July 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave.
Slide 1Module Testing Meeting March 7, 2003US Hybrid/Module/Rod Testing Model-Anthony Affolder US Hybrid/Module/Rod Testing Model Anthony Affolder (for.
CMS Tracker Week – Gantry Meeting – 21 st October 2003 – Dean White 1 Status of the UCSB Gantry Dean White University of California Santa Barbara October.
Tracker Week – UCSB Gantry Status – Febuary 10, 2004 – Dean White 1 Gantry Status University of California Santa Barbara UCSB Gantry Team: Andrea Allen.
4/25/2006 Puneeth Kalavase, UC, Santa Barbara On behalf of US Tracker Outer Barrel group Construction and Testing of CMS “Rods”
Tracker Week April ‘03G.Sguazzoni1 FE hybrid assembly and quality assurance The hybrid team: Alan Honma, Michael Poettgens, Gabriella Pasztor, Bernd Reinhold,
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.
1 US Testing Status-Anthony AffolderModule Testing Meeting, Dec. 11, 2003 Update of US Testing Status Anthony Affolder On behalf of the US testing group.
Slide 1Rod Production presented by Jim Lamb (UCSB)April 9, 2004 Rod Production Rod Production, April , presented by Jim Lamb (UCSB)
Module Production for The ATLAS Silicon Tracker (SCT) The SCT requirements: Hermetic lightweight tracker. 4 space-points detection up to pseudo rapidity.
Status of the Tracker DB System Tk week april 03 D. Contardo Developments Applications.
1 US Testing Update-Anthony AffolderTracker Meeting, Feb 10, 2004 US Module Testing Update Anthony Affolder (On behalf of the US testing group) Update.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
Status Brussels GANTRY Ê Overview of the pilot run (second week of October) 4 aims and achievements 4 accuracy on position and angles 4 residual features.
CMS Week, CERN, December Dec 2004CMS Week - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working Group Meeting Salvatore.
Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)
CMS Tracker Week, CERN, April Apr 2005CMS TrackerWeek - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working Group.
Status Brussels GANTRY Ê Recovered from the Gantry PC crash during Pilot Run R6 4 same situation as before the Pilot Run is achieved for R6 Ë Comparison.
CMS Tracker Week, CERN, October Oct 2004CMS Tracker Week - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working.
CMS Week, CERN, Mar Mar 2004CMS Week - Module ProductionSalvatore Costa - Catania Report on Module Bonding Salvatore Costa Università di.
Tracker Week, CERN, Oct Oct 2003Tracker Week - Module ProductionSalvatore Costa - Catania Executive summary from Bonding WG Meeting 21 Oct.
Status Brussels GANTRY Ê Try to assemble modules with good precision 4 different calibration plates (Karlsruhe and Bari) 4 determination of pin positions.
Brussels Gantry Ê Problem with vacuum chambers in plate 4 leaks in plates with gives communication between positions Ë Problem with rotation motor (U-motor)
Guido_Tonelli / CMS_TSC / 5 February Time stability of ST sensors The problem The sensors re-measuring campaign Failure analysis Conclusions.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
Fermilab PMG - Results from module testing - April 9, 2004 – E.Chabalina (UIC) 1 Results from module testing E.Chabalina University of Illinois (Chicago)
Brussels Module Production Ê We have producted 57 R6 modules and 26 R5N modules 4 of which 67 grade A and 9 grade B and 7 outside specifications Ë We have.
Strasbourg status Ring 7 pilot run François Didierjean.
Status Brussels GANTRY Ê New measurements of pin positions 4 using short pins rather than long ones 4 improved the precision Ë Cross-check of precision.
Lyon Gantry Status CERN 15 Sept D. Contardo Calibration Plates and Tools Readiness for production.
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
Tracker Week, CERN, Feb Feb 2004Tracker Week - Module ProductionSalvatore Costa - Catania Report on Module Bonding Salvatore Costa Università.
Brussels Gantry Ê Problems with vacuum chambers in plate 4 mostly solved by the workshop in Aachen (thanks) Ë Problem with rotation motor (U-motor) 4 motor.
B2GM, Nov 2014 Laci Andricek, MPG Halbleiterlabor 1 PXD Ladder Assembly - Conceptual design of jigs -
Update on Pavia MM mechanical prototype
Ladder Assembly All tools and jigs produced Glue dispensing works
Module Loading Task Force Meeting October 21, 2004
Ladder Assembly All tools and jigs produced Glue dispensing works
Gluing jigs for Demonstrator
Status Brussels GANTRY
System Tests at Lyon From Aachen: ICB for front petal side A, disks 4-6, rings 4 and 6 From CERN: CCU25 Tests (M. Ageron): FEC ring and I2C addressing.
Status Brussels GANTRY
FNAL Production Experience
Hamburg Bonding Report
Results from module testing
UCSB Testing Status Anthony Affolder
Vienna Module Production
Module production in Italy
US Testing Update Anthony Affolder (On behalf of the US testing group)
Bari production centre resp. M. de Palma
Hybrid & Module Electrical Testing
Module Production in Brussels
US Hybrid/Module/Rod Testing Model
Module Production in Brussels
US Module Testing Progress Report
Setup for testing LHCb Inner Tracker Modules
US Module Testing Progress Report
Status of Bonding R1N, R1S, R3 of TEC University of Hamburg
TEC Ring 2 module prototypes J. Hrubec / Inst. für Hochenergiephysik
Presentation transcript:

1 TEC pilot run status Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I - 15 R7 modules assembled on Lyon Gantry and bonded in Strasbourg Detailed presentation given at the Gantry and TEC meetings By O. Bouhali, J.M. Brom, R. Haroutunian, T. Franke CMS Tracker week 2410/03 D. Contardo

2 Assembly of R6 modules at Brussels Gantry : - 2 real modules (04/09/03): Status valid, presently on DB - 2 dummy modules just before the pilot run: valid - 11 modules between 6/10 and 9/10 (4days): TEC pilot run ended due to a HD crash! 2 positions on 2 plates used 1 plate with leak under sensors (change of kapton thickness) Pilot run for R6 modules Monday2Plate 61 Tuesday (leak in pos. 2) Wednesday361 (2 mod), 62(1 mod) Thursday261

3 Distribution of all plate 61 modules : Sensor 1 Sensor 2 Measured-Nominal (  m) All positions are good

4 Measured angles (mdeg) Sensor 1 Sensor 2 Summary of qualification for 13 glued modules : 3 modules glued on plate with leaks out of specifications (plates will be modified) 10 modules within specifications

5 Modules shipped to Aachen I on 15th of October powerbonds and first module fully bonded on 16th of October after necessary reprogramming of the bonding machine due to missing fiducials on the pitch adapter 17th of October: next 3 modules fully bonded 20th of October: last 6 modules fully bonded Pitch adapter bonding: no problems Sensor–sensor bonding: failures (lift-offs) on source bonds (~1% ) preferentially at the end of the bond row (~ strip number 400) Bonding and test of R6 modules at Aachen I and III

6 IV Curves From database (300V & 450 V)  With powerbond only  Fully bonded

7 IV Curves II From database (300V & 450 V)  With Power Bond only  Fully bonded

8 Summary Table Almost no bonding faults (candidates for only 2 opens and 3 channels shorted) No additional pinholes with respect to sensor tests Typical duration of a full module test including the preparation of the module in the testbox is about 25 minutes All 8 modules of grade A quality

9 Cooling Test of 1 R6 module black curves room T before cooling blue curves -20° red curves room T after thermal cycle 5 more modules in the cold box in Aachen with similar fine behaviour

10 Pilot run for R7 modules Assembly of R7 at the Lyon Gantry : pre-pilot run : one plate of 3 R7 modules pilot run : - 1 plate per day using the 3 R7 modules - 5 consecutive days for production (one R7 plate available at that time) only one noticable problem : an hybrid can’t be picked by vacuum with the bridge (still 3 modules where glued uring the process) Summary : All 18 modules are wihin the specifications

11 XY precision for sensors Position of sensor markers for the 18 modules compared to their expected position Red boxes have 10µm side and centered on the expected positions.

XY precision for sensors Overall shifts for sensor markers wrt exp. Position in µm XX YY

13 Reference axis = frame pins axis a) Initial angle of sensor (m1-m2) on supply plate with reference axis, b) Final angle of sensor (m1-m2) on assembly plate with reference axis c) Angle between sensor : 14 over 15 modules have Dteta < 5m° Sensors angular positionning precision

14 With 1 operator : 1h30’ Preparation : 30’ - Check sensors and hybrids from DB, Arc test hybrids - Clean frames, Glue 1D label and register module composition in the DB - Put sensors frames and hybrids on plates - prepare glue Gantry assembly : 30’ - start assembly prog, glue test by eyes, all other gluiing steps Post-assembly : 30’ - position monitoring after curing - update de la DB - mounting modules on support plates - bias glue put by hand - put modules in transport box and initiate DB transfer. With 2 operators : 3 types of operation in parallels : 45’ Gantry assembly time per plate

15 Reception of 15 modules Searching on Data Base : data of Si sensors - I V curves - bad strips Bonding of R7 modules at Strasbourg

16 Bonding 6 modules are bonded 1. ARC tests (5' for fast test only, 10' for all tests) : 5’ 2. Bonding of the bias rings for the ARC tests and the IV 15’ curves and bonding of the 11 bonds form Si to Si and 11 bonds from PA to Si. Results : (will be done in the Data Base) 7.0 +/- 0.7 g on Pa – Si 7.0 +/- 0.4 g on Si – Si 3. ARC test and IV 5’ 4. Bonding of the entire Module. 40’ Immediate repair of the obvious unbonded channels. Number of repairs : Si - Si : 12 bonds / 3072 bonds PA - Si : 15 bonds / 3072 bonds 5. ARC test including LED illumination. 30’

17 I V curves with temperature compensation Red and blue sensor currents (nA) pink sum of the 2 sensors currents (nA) black our measurements Summary : - Bonding and test time per module 1h30 (test procedure can be reduced) - All bonded modules are good

18 Conclusions from the TEC pilot run From the Gantry centers : - Few problems related to first experience of production run (R6 plates to be adjusted to final kapton in Brussels) - the full time per plate assembly was measured to be about 1h30, - possibility to do in parallel the preparation tasks and the Gantry gluing when dealing with 2 plates and with 2 operators (reducing the prodution time to less than 1h). A stable production of 4 plates per day to fulfill nominal needs for a 1 year production should be reached in the coming months. There is clear room for yield improvement to 5 plates if 2 operators are working in parallel. From the Bonding centers : - The bonding time including all qualification steps was found to be 1h30 A nominal rate of 6 modules bonded per day was reached in Aachen and Strasbourg. There are ways for rate improvements (depending on failures, plus reduction of the number of tests in the process). The present tests of the 16 first bonded modules : ARC read-out and IV curves showed that the modules are of high grade quality. First 6 modules tested down to -25° with perfect pedestals, noise, pulse shape and no additional dead channels.

19 Readiness and next months plan for mass production Tools preparation status : - Frame assembly jigs are all ready - Bonding jigs are all ready apart for R1, Hambourg will receive R1 prototypes next week to prepare the jigs - Gantry all plates are there, R1, R2, R4, R7 and R6 plates are commissionned Plan for next months : - Finish commissioning of plate R3 and R5 at the Brussels Gantry, study commissioning of some existing plates on the second gantry for production back-up. - Commission new design with rigidifiers (successfully tested in Aachen) simple grooves milled in the plates at the rigidifier position plus test of procedure on the gantry gluing dummy and real modules. (still production can start for different geometries with gluing of rigidifiers by hand) - Built new modules to complete the TEC system test (8R1, 8R2, 7R3, 4R4, 8R5) (one TEC read-out loop is 2 to 3 petals) Needs hybrids with pitch (before final version) : 6 x R1N(6D), R1S(6U), R2N(6D), R2S(6U), R4(4U), R5N(6D), R5S(6U) 10 x R6(4U), R7(4U)

20 Ring 7