Review on PSB 160 MeV H- Injection Nov 9-10, 2011 Closeout by P. Cruikshank, M. Giovannozzi, D. Johnson, B. Jones, B. Pine, M. Plum, D. Tommasini.

Slides:



Advertisements
Similar presentations
December 10, 2008 TJRParticle Refrigerator1 The Particle Refrigerator Tom Roberts Muons, Inc. A promising approach to using frictional cooling for reducing.
Advertisements

EMMA Magnet Design Ben Shepherd Magnetics and Radiation Sources Group ASTeC STFC Daresbury Laboratory.
K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
Upcoming Review of the Hall D Photon Beam and Tagger Richard Jones, University of Connecticut, for the GlueX collaboration GlueX Collaboration Meeting.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
H 0 -H - PSB INJECTION VACUUM REQUIREMENTS C. Pasquino, P. Chiggiato, J. Hansen PSB - H0-H- injection review meeting, 18th April 2013.
E.Benedetto, 30/05/13, LIU-PSB Meeting, PSB chicane magnets: Inconel chamber PSB H- chicane magnets: Inconel vacuum chamber option & consequences on beam.
E. Benedetto SC meeting 19/3/15 Update on the LIU curve emittance vs. intensity.
Linac4 Beam Commissioning Committee PSB Beam Optics and Painting Schemes 9 th December 2010 Beam Optics and Painting Schemes C. Bracco, C. Carli, B. Goddard,
Sergey Antipov, University of Chicago Fermilab Mentor: Sergei Nagaitsev Injection to IOTA ring.
Introduction Status of SC simulations at CERN
PSB h- injection Layout issues –Are 3 or 4 KSW needed –Geometry of the injection –Element lengths and locations Element performance specifications H 0.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
AGS Polarized Proton Development toward Run-9 Oct. 3, 2008 Haixin Huang.
FACET Machine Performance and Expectations M. Sullivan for the FACET Accelerator group SAREC Review July 25, 2013.
PS Booster Studies with High Intensity Beams Magdalena Kowalska supervised by Elena Benedetto Space Charge Collaboration Meeting May 2014.
IR summary M. Sullivan Nov. 3, 2011 JLAB MEIC IR workshop.
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
Simulation of direct space charge in Booster by using MAD program Y.Alexahin, A.Drozhdin, N.Kazarinov.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
F Proton Plan Eric Prebys, FNAL Accelerator Division.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
Optics considerations for ERL test facilities Bruno Muratori ASTeC Daresbury Laboratory (M. Bowler, C. Gerth, F. Hannon, H. Owen, B. Shepherd, S. Smith,
The Stripping Foil Test Stand in the Linac4 Transfer Line
The Quadrupole Pick-up in the CPS -intro and progress report PPC 3 Dec 1999 A. Jansson.
STATUS OF H0/H- DUMPS M. Delonca – LIU meeting 29/11/2012 Thanks to: C. Maglioni, A. Patapenka, C. Pasquino, A. Perez, N. Mariani.
Overview of Booster PIP II upgrades and plans C.Y. Tan for Proton Source group PIP II Collaboration Meeting 03 June 2014.
Managed by UT-Battelle for the Department of Energy SNS Injection and Extraction Systems Issues and Solutions by M. Plum for the SNS team and our BNL collaborators.
Injection Energy Review D. Schulte. Introduction Will review the injection energy So could answer the following questions: Which injection energy can.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Low Emittance Generation and Preservation K. Yokoya, D. Schulte.
Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV B.Goddard F.Velotti, A.Parfenova, R.Steerenberg, K.Cornelis,
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
Review on shorter PSB main bending magnets Injection layout with short magnets Advantages & Disadvantages Wim Weterings
PSB Injection Overview + Specification changes ABT LIU Project Review Wim Weterings.
The Introduction to CSNS Accelerators Oct. 5, 2010 Sheng Wang AP group, Accelerator Centre,IHEP, CAS.
E.Benedetto, 1/07/13, LIS Meeting, PSB chicane magnets: Inconel chamber PSB H- chicane magnets: Inconel vacuum chamber option & consequences on beam dynamics.
Draft MD Planning Thu (3.11.) DayTimeMDMP Thu05:00 Ramp down, cycle 07: GeV: Injection stability and losses – check steering constraints, define.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
Beam collimation in the transfer line from 8 GeV linac to the Main Injector A. Drozhdin The beam transfer line from 8 GeV Linac to the Main Injector is.
ECR - PSB: New KSW magnet in 16L1 Luis Feliciano, 4 th February.
PAC Meeting, December 12, Prebys 1 The Problem.
Workshop on Accelerator R&D for Ultimate Storage Rings – Oct Nov.1 – Huairou, Beijing, China A compact low emittance lattice with superbends for.
HISTORY OF SNS DESIGN AND TECHNOLOGY CHOICES PROJECT X WORKSHOP NOVEMBER 12-13, 2007 R. KUSTOM.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
Global Design Effort RTML KOM Close-out Ross, Walker.
Proton Economics Eric Prebys FNAL Accelerator Division.
ESLS Workshop Nov 2015 MAX IV 3 GeV Ring Commissioning Pedro F. Tavares & Åke Andersson, on behalf of the whole MAX IV team.
Wim Weterings Remy Noulibos
Threading / LTC/ JW1 How difficult is threading at the LHC ? When MADX meets the control system … J. Wenninger AB-OP &
Third ILC Damping Rings R&D Mini-Workshop KEK, Tsukuba, Japan December 2007 Choosing the Baseline Lattice for the Engineering Design Phase Andy Wolski.
LINAC4 ADVISORY COMMITTEE
Minimum Hardware Commissioning – Disclaimer
Installation of an Instrument on a CERN machine
Options and Recommendations for TL and Dumps
The LHC - Status Is COLD Is almost fully commissioned
Joint Meeting SPS Upgrade Study Group and SPS Task Force
A Cold SCU Phase-Shifter
CLIC damping rings working plan towards the CDR
SLHC-PP kick-off meeting, CERN 9 April 2008
Negative Momentum Compaction lattice options for PS2
Optics Measurements in the PSB
Electron Collider Ring Magnets Preliminary Summary
IR Beam Transport Status
Crab Crossing Named #1 common technical risk (p. 6 of the report)
Presentation transcript:

Review on PSB 160 MeV H- Injection Nov 9-10, 2011 Closeout by P. Cruikshank, M. Giovannozzi, D. Johnson, B. Jones, B. Pine, M. Plum, D. Tommasini

Overall The world’s most complex ring injection system is about to become more complex… But if anyone can do it, CERN can No show stoppers found in the material that was presented Very high quality work Thank you for the excellent presentations and the great hospitality

PSB H- Injection Concept Congratulations on a design that meets the extremely tight space constraints. The maintainability, accessibility, upgradability will be difficult in this area. If there is a significant advantage, it may be reasonable to consider building shorter main dipole magnets to free up some space. Concern about non-zero dispersion option, due to linac energy jitter and longitudinal painting causing the injected beam to move on the foil We believe it is important to have a good understanding of the PSB optics prior to installation. Suggest measuring lattice functions prior to installation. Need to have this capability after installation anyway. Also could benchmark simulations of existing ring. Space charge simulations and benchmarking would be useful.

Chicane Magnets Biggest issue in this project seems to be the chicane magnets. These magnets create large lattice distortions, due to a vertical quad component, which needs compensation. The present design also requires large (0.8 m^3) transformers in the tunnel. Options discussed: – 16 supplies, which gives the maximum flexibility, but at a high cost – Put all chic. #1 magnets on one supply, etc. (4 supplies) – Put all chicanes in one ring on one supply (4 supplies total) – Optimization study needs to be performed. There were questions on the best way to correct the beam steering through the chicanes. – Are separate trim supplies and trim magnets required? (Case of multiple magnets on one supply) – Can this be done with the existing ring dipole correctors?

Chicane Magnets (cont.) Recommend 3D field calcs with all chicane magnets together from one main dipole to the next main dipole, followed by particle tracking through these fields. Recommend exploring the option of increasing the number turns on the chicane magnet windings and optimizing fall time (now 5 ms to allow quad compensation tracking). May be able to get rid of those big (0.8 m^3) transformers in the tunnel.

KSW Painting magnets Question: is it possible to reverse the bump to keep the beam off the foil? Suggest fabricating new kickers with RF screens (option 2). It seems the budget will accommodate this.

Internal H0/H- Dump Make dump as short as possible to improve aperture and clearance issues. Consider higher density materials and/or composite materials. Do not support dump on metal plate due to eddy current effects. Is it practical to have any support? Baking dump is a complication. Make sure that really need to do it. May just be able to use cooling system to heat. May be able to use beam to heat it. This will influence choice of graphite material. Four sigma clearance between dump and circulating beam seems tight. How well the injected beam angle can be measured and controlled is a related concern. Suggest evaluating contribution of the graphite dump to the machine impedance.

Injection foils and handling system The work to date is impressive to fit the mechanism into the available space Prototype foil changer seems to be working well. Some details left to work out (e.g. method to accommodate bellows sag). There was a lot of discussion on the idea of a mechanism with just one foil, with no clear consensus. May want to re-evaluate this issue. Make sure that can change one foil at a time

PSB H- Injection Vacuum analysis The design integration is a work in progress The graphite beam stop options need to be known so the material can be selected, and its outgassing properties characterized Make sure have vacuum monitoring and interlocks on all closed volumes

Beam instrumentation Make sure that have a good method to measure beta function and beta beating. Measuring (or estimating) the angle of the injected beam at the foil is desirable to ensure proper injection and clearance of the circulating beam at the dump. Maybe measure current on "polarizing rings,” or may want to consider other methods such as segmented foils in front of the dump. Loss monitor coverage (~1 every 10 m, for two rings) seems a little thin. Video system to look at view screen and foil is very conceptual at this point and difficult to evaluate. Consider upgrading BPM system prior to installation to allow optics function measurements of existing machine.

Beam losses 5% beam loss predicted by simulations. This is high compared to other machines. Why? There was some discussion on a ring collimation system, with no clear consensus at this time. Outside the scope of this review.

Commissioning strategy and timeline Six months for installation and commissioning seems tight and has little to no contingency The greatest risk is in the commissioning due to the difficulty in predicting how long it will take. Commissioning schedule will likely be dominated by equipment performance and availability. Consider preparing for installation in advance. Need to finalize the remaining design choices in order to accomplish this.

Conclusions Project is in good shape for this stage of the game, for installation that could begin as early as Some systems are well along in the design phase, some are still conceptual. Some major decisions are still to be made – How to power the chicane magnets – 16 supplies, or 4 (all chicane #1’s together, etc.) or 4 (all chicanes in 1 ring together) – Inconel vs. ceramic vacuum chambers – Can the wall be cut away to relieve the space constraints? This will have an impact on the design choices. – Suggest setting a deadline for when the outstanding designs should be complete